Detail Letting Schedule for Kerr County (FY 2012)
Detail Letting Schedule for Kerr County (FY 2012) | ||||
Last Update: Monday, September 24, 2012 |
Kerr County (FY 2012) |
CCSJ: 0193-01-037 | |||
District: | San Antonio | Let Date: | MAR 2012 |
Highway: | SH 39 | Let Status: | Actual |
Project ID: | STP 2012(421)HES | CSJ: | 0193-01-037 |
Description: | WIDEN NARROW ROADWAY TO ADD SHOULDERS | Handling Code: |
|
Limits From: | 3.067 MI E OF RM 187 | Fund Cat: | 8 |
Limits To: | 5.070 MI E OF RM 187 | Estimate: | $675,810 |
Length: | 2.0 Miles | Actual: | $738,383 |
Back... |
Totals for 0193-01-037 | ||
---|---|---|---|
Length: | 2.0 Miles | ||
Estimate: | $675,810 | ||
Actual: | $738,383 | ||
CCSJ: 0193-02-031 | |||
District: | San Antonio | Let Date: | AUG 2012 |
Highway: | SH 39 | Let Status: | Actual |
Project ID: | C 193-2-31 | CSJ: | 0193-02-031 |
Description: | UPGRADE TO 2 LANE WITH CONTINUOUS LEFT TURN LANE | Handling Code: |
|
Limits From: | 0.1 MI E OF SH 27 | Fund Cat: | 3 |
Limits To: | NEW INGRAM LAKE DAM | Estimate: | $6,999,685 |
Length: | 1.3 Miles | Actual: | $7,644,986 |
Award Status Bid Tabulations Back... |
Totals for 0193-02-031 | ||
Length: | 1.3 Miles | ||
Estimate: | $6,999,685 | ||
Actual: | $7,644,986 | ||
CCSJ: 0829-04-031 | |||
District: | San Antonio | Let Date: | MAR 2012 |
Highway: | FM 1340 | Let Status: | Actual |
Project ID: | STP 2012(382)HES | CSJ: | 0829-04-031 |
Description: | WIDEN NARROW ROADWAY TO ADD SHOULDERS | Handling Code: |
|
Limits From: | 3.0 MI E OF CEDAR CLIFF | Fund Cat: | 8 |
Limits To: | 0.3 MI E OF CEDAR CLIFF | Estimate: | $860,299 |
Length: | 2.7 Miles | Actual: | $984,964 |
Back... |
Totals for 0829-04-031 | ||
Length: | 2.7 Miles | ||
Estimate: | $860,299 | ||
Actual: | $984,964 | ||
CCSJ: 0915-15-085 | |||
District: | San Antonio | Let Date: | JUL 2012 |
Highway: | CR | Let Status: | Actual |
Project ID: | BR 2008(112) | CSJ: | 0915-15-085 |
Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: |
|
Limits From: | LAZY VALLEY RD AT CYPRESS CREEK | Fund Cat: | 6 |
Limits To: | . | Estimate: | $334,001 |
Length: | 0.1 Miles | Actual: | $364,308 |
Bid Tabulations Back... |
Totals for 0915-15-085 | ||
Length: | 0.1 Miles | ||
Estimate: | $334,001 | ||
Actual: | $364,308 | ||
CCSJ: 1135-03-026 | |||
District: | San Antonio | Let Date: | MAR 2012 |
Highway: | FM 1341 | Let Status: | Actual |
Project ID: | STP 2012(422)HES | CSJ: | 1135-03-026 |
Description: | WIDEN NARROW ROADWAY TO ADD SHOULDERS | Handling Code: |
|
Limits From: | 1.5 MI E OF SP 534 | Fund Cat: | 8 |
Limits To: | 1.6 MI W OF RED ROSE | Estimate: | $313,751 |
Length: | 0.5 Miles | Actual: | $367,231 |
Back... |
Totals for 1135-03-026 | ||
Length: | 0.5 Miles | ||
Estimate: | $313,751 | ||
Actual: | $367,231 |
|
|