Letting Schedule for Corpus Christi District (FY 2012)

 
 
Last Update: Monday, September 24, 2012
Corpus Christi District (FY 2012)
Aransas | Goliad | Jim Wells | Karnes | Kleberg | Live Oak | Nueces | Refugio | San Patricio

Aransas County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0916-38-004 VA Actual JAN 2012 $694,061 3 HIKE AND BIKE TRAIL

Goliad County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0088-02-060 US 59 Actual APR 2012 $223,390 8 CENTERLINE RUMBLE STRIP
0155-03-036 US 183 Actual DEC 2011 $2,460,601 1 REHABILITATE ROADWAY
0411-01-013 PR 27 Actual DEC 2011 $24,064 10 REPLANK RAILROAD CROSSING (2011 PROGRAM)

Jim Wells County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0087-01-100 SH 44 Actual DEC 2011 $211,200 10 REPLANK RAILROAD CROSSING (2010 PROGRAM PROJECT)
0087-01-101 SH 359 Actual DEC 2011 $4,120,322 1 UNDERSEAL AND OVERLAY
0254-07-003 US 281 Actual JUL 2012 $16,496,832 8 CONSTRUCT OVERPASS
1447-01-021 FM 1352 Actual MAY 2012 $617,097 1 MILL, SEAL & OVERLAY
1693-01-021 FM 1931 Actual MAY 2012 $79,200 10 REPLANK RAILROAD CROSSING

Karnes County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0100-05-071 US 181 Actual SEP 2011 $9,565,611 1 SEAL COAT ROADWAY (2012 LOW CONTROL SEAL COAT PROJECT)
0100-05-072 US 181 Actual SEP 2011 $643,627 1 MISCELLANEOUS ROADWAY WORK

Kleberg County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0102-04-095 US 77 Actual APR 2012 $14,562,422 11 CONSTRUCT MAINLANES AND OVERPASS AT CAESAR AVE.
0102-06-028 SH 285 Actual DEC 2011 $42,112 10 RAILROAD GRADE CROSSING REPLANKING
0992-01-020 RM 628 Actual MAY 2012 $1,354,854 6 WIDEN ROADWAY

Live Oak County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0447-01-060 BU 59-X Actual DEC 2011 $108,288 10 REPLANK RAILROAD CROSSING (2011 PROGRAM)
2373-04-013 FM 624 Actual AUG 2012 $4,199,613 1 REHAB ROADWAY

Nueces County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0074-06-216 IH 37 Actual DEC 2011 $42,112 10 REPLANK RAILROAD CROSSING (2010 PROGRAM PROJECT)
0102-01-103 SH 44 Actual DEC 2011 $61,600 10 REPLANK RAILROAD CROSSING (2010 PROGRAM PROJECT)
0102-01-104 SH 44 Actual DEC 2011 $88,000 10 REPLANK RAILROAD CROSSING (2010 PROGRAM PROJECT)
0102-02-095 US 77 Actual JUL 2012 $11,246,984 3 CONSTRUCT MAIN LANES
0102-14-104 SS 544 Actual DEC 2011 $193,600 10 REPLANK RAILROAD CROSSING (2010 PROGRAM PROJECT)
0373-01-099 US 77 Actual OCT 2011 $895,021 1 LEVEL - UP OF EXISTING ROADWAY
0617-01-182 SH 358 Actual DEC 2011 $36,096 10 REPLANK RAILROAD CROSSIN (2011 PROGRAM)
0916-00-063 VA Actual JUN 2012 $1,104,600 10 CONSTRUCT CURB RAMPS FOR ADA COMPLIANCE
0916-35-166 CS Actual OCT 2011 $1,017,532 3 YORKTOWN BLVD. / STAPLES TO CIMARRON LANDSCAPING IMPROVMENTS
1093-01-027 FM 763 Actual FEB 2012 $1,483,876 1 REHAB AND WIDEN
1556-01-024 FM 24 Actual FEB 2012 $2,296,239 1 REHAB ROADWAY
1558-02-033 FM 70 Actual DEC 2011 $36,096 10 REPLANK RAILROAD CROSSING (2011 PROGRAM)
1558-03-026 FM 70 Actual JAN 2012 $249,002 8 CENTERLINE RUMBLE STRIPS
1742-01-025 FM 1694 Actual MAY 2012 $44,000 10 REPLANK RAILROAD CROSSING
3364-01-010 FM 3386 Actual MAY 2012 $2,782,732 1 CONSTRUCT NEW FM ROAD

Refugio County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0447-05-064 FM 774 Actual DEC 2011 $54,144 10 RAILROAD GRADE CROSSING REPLANKING

San Patricio County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0101-03-082 US 181 Actual JAN 2012 $4,783,690 1 OVERLAY ROADWAY
0372-01-095 US 77 Actual NOV 2011 $719,210 1 MILL AND OVERLAY
0994-01-030 SH 188 Actual JUN 2012 $9,223,815 1 REHAB
3340-01-005 FM 3239 Actual AUG 2012 $4,770,791 3 CONSTRUCT 2 ADDITIONAL LANES WITH CONTINUOUS LEFT TURN LANE


Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract