Detail Letting Schedule for Bell County (FY 2013)
Bell County (FY 2013) |
CCSJ: 0015-14-091 | |||
District: | Waco | Let Date: | SEP 2012 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | NH 2012(691) | CSJ: | 0015-14-091 |
Description: | RECONSTRUCT AND WIDEN FROM FOUR TO EIGHT LANES | Handling Code: |
|
Limits From: | S LP 363 IN TEMPLE | Fund Cat: | 11 |
Limits To: | NUGENT AVE | Estimate: | $89,902,582 |
Length: | 2.2 Miles | Actual: | $98,379,773 |
District: | Waco | Let Date: | SEP 2012 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | NH 2012(691) | CSJ: | 0015-14-102 |
Description: | RECONSTRUCT AND WIDEN FROM FOUR TO EIGHT LANES | Handling Code: |
|
Limits From: | NUGENT AVE | Fund Cat: | 11 |
Limits To: | NORTH LP 363 | Estimate: | 109,418,665 |
Length: | 3.6 Miles | Actual: | 126,618,729 |
District: | Waco | Let Date: | SEP 2012 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | NH 2012(690) | CSJ: | 0015-14-123 |
Description: | RIGHT OF WAY ACQUISITION, UTILITIES ADJUSTMENTS AND | Handling Code: |
|
Limits From: | S LP 363 IN TEMPLE | Fund Cat: | ROW |
Limits To: | NUGENT AVE | Estimate: | |
Length: | 2.7 Miles | Actual: | $5,168,878 |
District: | Waco | Let Date: | SEP 2012 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | NH 2012(689) | CSJ: | 0015-14-124 |
Description: | RIGHT OF WAY ACQUISITION, UTILITIES ADJUSTMENTS AND | Handling Code: |
|
Limits From: | NUGENT AVE | Fund Cat: | ROW |
Limits To: | NORTH LP 363 | Estimate: | |
Length: | 2.5 Miles | Actual: | $3,820,264 |
District: | Waco | Let Date: | SEP 2012 |
Highway: | IH 35 | Let Status: | Actual |
Project ID: | NH 2012(691) | CSJ: | 0015-14-125 |
Description: | REVERSE ENTRANCE RAMP, EXIT RAMP AND CONSTRUCT AUXILIARY | Handling Code: |
|
Limits From: | MIDWAY DRIVE | Fund Cat: | 11 |
Limits To: | S LP 363 IN TEMPLE | Estimate: | $6,234,579 |
Length: | 1.8 Miles | Actual: | $7,309,292 |
Back... |
Totals for 0015-14-091 | ||
---|---|---|---|
Length: | 12.8 Miles | ||
Estimate: | 205,555,826 | ||
Actual: | 241,296,936 | ||
CCSJ: 0231-03-103 | |||
District: | Waco | Let Date: | MAR 2013 |
Highway: | US 190 | Let Status: | Actual |
Project ID: | NH 2013(407) | CSJ: | 0231-03-103 |
Description: | WIDEN FROM FOUR TO SIX LANES AND RESURFACE | Handling Code: |
|
Limits From: | WS YOUNG | Fund Cat: | 11 |
Limits To: | FM 2410 IN HARKER HEIGHTS | Estimate: | $10,442,113 |
Length: | 2.8 Miles | Actual: | $9,587,761 |
Back... |
Totals for 0231-03-103 | ||
Length: | 2.8 Miles | ||
Estimate: | $10,442,113 | ||
Actual: | $9,587,761 | ||
CCSJ: 0231-03-107 | |||
District: | Waco | Let Date: | OCT 2012 |
Highway: | US 190 | Let Status: | Actual |
Project ID: | NH 2012(638) | CSJ: | 0231-03-107 |
Description: | WIDEN FROM FOUR TO SIX LANES AND RESURFACE | Handling Code: |
|
Limits From: | SP 172 (FT HOOD MAIN GATE) | Fund Cat: | 3 |
Limits To: | WS YOUNG | Estimate: | $55,074,711 |
Length: | 5.9 Miles | Actual: | $55,361,501 |
Back... |
Totals for 0231-03-107 | ||
Length: | 5.9 Miles | ||
Estimate: | $55,074,711 | ||
Actual: | $55,361,501 | ||
CCSJ: 0231-03-129 | |||
District: | Waco | Let Date: | JAN 2013 |
Highway: | US 190 | Let Status: | Actual |
Project ID: | PTF 1102(054) | CSJ: | 0231-03-129 |
Description: | CONSTRUCT OVERPASS AT PROPOSED ROSEWOOD DRIVE | Handling Code: |
LC |
Limits From: | 0.20 MI E OF FM 3470 | Fund Cat: | 3 |
Limits To: | 0.30 MI W OF FM 2410 | Estimate: | $16,816,965 |
Length: | 1.3 Miles | Actual: | $17,025,036 |
District: | Waco | Let Date: | JAN 2013 |
Highway: | CS | Let Status: | Actual |
Project ID: | CC 909-36-143 | CSJ: | 0909-36-143 |
Description: | CONSTRUCT 4 - LANE CITY STREET ON NEW LOCATION | Handling Code: |
LC |
Limits From: | US 190 EASTBOUND FRTG RD | Fund Cat: | 3 |
Limits To: | ROSEWOOD DR | Estimate: | $2,654,181 |
Length: | 0.7 Miles | Actual: | $2,654,181 |
District: | Waco | Let Date: | JAN 2013 |
Highway: | FM 2410 | Let Status: | Actual |
Project ID: | PTF 1102(054) | CSJ: | 2304-02-035 |
Description: | WIDEN FROM TWO TO FOUR LANES WITH CONTINUOUS LEFT TURN LANE | Handling Code: |
LC |
Limits From: | FM 3470 | Fund Cat: | 3 |
Limits To: | ROY REYNOLDS DRIVE | Estimate: | $3,333,035 |
Length: | 0.9 Miles | Actual: | $2,273,558 |
Back... |
Totals for 0231-03-129 | ||
Length: | 2.9 Miles | ||
Estimate: | $22,804,181 | ||
Actual: | $21,952,775 | ||
CCSJ: 0398-04-072 | |||
District: | Waco | Let Date: | OCT 2012 |
Highway: | SH 317 | Let Status: | Actual |
Project ID: | HP 2012(776) | CSJ: | 0398-04-072 |
Description: | WIDEN FROM TWO TO FOUR LANES WITH RAISED MEDIAN | Handling Code: |
|
Limits From: | FM 439 | Fund Cat: | 1 |
Limits To: | 0.5 MI N OF FM 439 | Estimate: | $2,841,086 |
Length: | 0.8 Miles | Actual: | $3,649,335 |
Back... |
Totals for 0398-04-072 | ||
Length: | 0.8 Miles | ||
Estimate: | $2,841,086 | ||
Actual: | $3,649,335 | ||
CCSJ: 0752-03-021 | |||
District: | Waco | Let Date: | DEC 2012 |
Highway: | FM 935 | Let Status: | Actual |
Project ID: | STP 2013(275) | CSJ: | 0752-03-021 |
Description: | WIDEN PAVEMENT TO ADD SHOULDERS, PROVIDE SAFETY UPGRADES | Handling Code: |
|
Limits From: | IH 35 | Fund Cat: | 1 |
Limits To: | FALLS CO LINE | Estimate: | $2,184,550 |
Length: | 6.8 Miles | Actual: | $2,187,902 |
Official Notice Back... |
Totals for 0752-03-021 | ||
Length: | 6.8 Miles | ||
Estimate: | $2,184,550 | ||
Actual: | $2,187,902 | ||
CCSJ: 0752-07-013 | |||
District: | Waco | Let Date: | AUG 2013 |
Highway: | FM 1237 | Let Status: | Actual |
Project ID: | STP 2013(368)FRS | CSJ: | 0752-07-013 |
Description: | INSTALL RAILROAD SIGNAL | Handling Code: |
XX |
Limits From: | @ BNSF RR TRACKS | Fund Cat: | 8 |
Limits To: | ON FM 1237 NEAR PENDLETON | Estimate: | $161,180 |
Length: | 0.1 Miles | Actual: | $161,180 |
Back... |
Totals for 0752-07-013 | ||
Length: | 0.1 Miles | ||
Estimate: | $161,180 | ||
Actual: | $161,180 | ||
CCSJ: 0909-36-132 | |||
District: | Waco | Let Date: | OCT 2012 |
Highway: | CS | Let Status: | Actual |
Project ID: | STP 2011(645)SRS | CSJ: | 0909-36-132 |
Description: | CONSTRUCT ALTERNATE TRANSPORTATION ROUTE CONSISTING OF | Handling Code: |
LC |
Limits From: | IH 35 SB FRTG RD | Fund Cat: | 3 |
Limits To: | MAYS MIDDLE SCHOOL (TROY ISD) | Estimate: | $450,950 |
Length: | 0.1 Miles | Actual: | $429,445 |
Back... |
Totals for 0909-36-132 | ||
Length: | 0.1 Miles | ||
Estimate: | $450,950 | ||
Actual: | $429,445 | ||
CCSJ: 0909-36-133 | |||
District: | Waco | Let Date: | OCT 2012 |
Highway: | CS | Let Status: | Actual |
Project ID: | STP 2011(232)TE | CSJ: | 0909-36-133 |
Description: | PHASE II - CONSTRUCT ALTERNATE TRANSPORTATION ROUTE | Handling Code: |
LC |
Limits From: | SOUTH FIRST STREET | Fund Cat: | 3 |
Limits To: | SOUTH FIFTH STREET | Estimate: | $1,873,465 |
Length: | 0.1 Miles | Actual: | $2,110,600 |
Back... |
Totals for 0909-36-133 | ||
Length: | 0.1 Miles | ||
Estimate: | $1,873,465 | ||
Actual: | $2,110,600 | ||
CCSJ: 0909-36-141 | |||
District: | Waco | Let Date: | AUG 2013 |
Highway: | CR | Let Status: | Actual |
Project ID: | STP 2013(368)FRS | CSJ: | 0909-36-141 |
Description: | INSTALL RAILROAD SIGNAL | Handling Code: |
XX |
Limits From: | @ BNSF RR TRACKS | Fund Cat: | 8 |
Limits To: | ON GUYTON RD NEAR PENDLETON | Estimate: | $231,934 |
Length: | 0.1 Miles | Actual: | $231,934 |
Back... |
Totals for 0909-36-141 | ||
Length: | 0.1 Miles | ||
Estimate: | $231,934 | ||
Actual: | $231,934 | ||
CCSJ: 0909-36-142 | |||
District: | Waco | Let Date: | AUG 2013 |
Highway: | CR | Let Status: | Actual |
Project ID: | STP 2013(368)FRS | CSJ: | 0909-36-142 |
Description: | INSTALL RAILROAD SIGNAL | Handling Code: |
XX |
Limits From: | @ BNSF RR TRACKS | Fund Cat: | 8 |
Limits To: | ON LUTHER CURTIS RD NEAR PENDLETON | Estimate: | $219,394 |
Length: | 0.1 Miles | Actual: | $219,394 |
Back... |
Totals for 0909-36-142 | ||
Length: | 0.1 Miles | ||
Estimate: | $219,394 | ||
Actual: | $219,394 | ||
CCSJ: 1308-01-029 | |||
District: | Waco | Let Date: | SEP 2012 |
Highway: | FM 1123 | Let Status: | Actual |
Project ID: | STP 2013(016)HES | CSJ: | 1308-01-029 |
Description: | PROVIDE ADDITIONAL PAVED SURFACE WIDTH | Handling Code: |
|
Limits From: | FM 436 | Fund Cat: | 1 |
Limits To: | TOWERY DR IN HOLLAND | Estimate: | $4,172,634 |
Length: | 12.2 Miles | Actual: | $4,743,893 |
District: | Waco | Let Date: | SEP 2012 |
Highway: | FM 1123 | Let Status: | Actual |
Project ID: | STP 2013(017) | CSJ: | 1308-01-030 |
Description: | FARM - TO - MARKET PAVEMENT RESTORATION | Handling Code: |
|
Limits From: | TOWERY DR | Fund Cat: | 1 |
Limits To: | TRAVIS ST IN HOLLAND | Estimate: | $142,250 |
Length: | 0.3 Miles | Actual: | $194,354 |
Back... |
Totals for 1308-01-029 | ||
Length: | 12.5 Miles | ||
Estimate: | $4,314,884 | ||
Actual: | $4,938,247 |
|