0006-07-072 IH 20 Actual DEC 2012 $443,024 1 SAFETY LIGHTING

Fisher County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0908-23-027 CR Actual AUG 2013 $248,230 6 REPLACE BRIDGE AND APPROACHES
0908-23-029 CR Actual AUG 2013 $292,218 6 REPLACE BRIDGE AND APPROACHES
0908-23-031 CR Actual MAY 2013 $211,698 6 REPLACE BRIDEG AND APPROACHES
0908-23-032 CR Actual APR 2013 $276,104 6 REPLACE BRIDGE
0908-23-033 CR Actual APR 2013 $254,269 6 REPLACE BRIDGE AND APPROACHES
2379-01-010 FM 608 Actual AUG 2013 $176,468 8 UPGRADE / INSTALL RR XING PROTECTION

Haskell County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0157-04-045 US 277 Actual FEB 2013 $3,020,842 1 MILLING, SPOT BASE REPAIR AND SURFACING

Howard County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0005-05-102 IH 20 Actual MAY 2013 $18,434,934 1 CONSTRUCT NEW INTERCHANGE
0005-10-016 BI 20-G Actual JAN 2013 $5,646,936 10 REHABILITATION, ACP, SIDEWALKS
0069-01-052 US 87 Actual JUL 2013 $2,216,751 1 SPOT REPAIR / SEAL / OVERLAY
1155-03-009 FM 1785 Actual APR 2013 $633,634 6 REPLACE BRIDGE AND APPROACHES

Mitchell County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0454-03-040 SH 208 Actual AUG 2013 $42,112 10 REPLANK RAILROAD GRADE CROSSING

Nolan County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0006-02-108 IH 20 Actual NOV 2012 $3,445,320 1 SEAL COAT
0006-02-109 IH 20 Actual APR 2013 $1,564,230 6 REPLACE BRIDGE
0006-02-110 IH 20 Actual MAY 2013 $158,645 6 DEMOLITION OF BRIDGE FOR EMERGENCY BRIDGE REPLACEMENT
0264-01-036 BS 70-G Actual FEB 2013 $6,493,251 1 REHABILITATION, ACP, SIDEWALKS
0264-02-026 SH 70 Actual FEB 2013 $2,989,281 1 ASPHALT CONCRETE PAVEMENT OVERLAY

Scurry County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0053-09-069 US 84 Actual MAR 2013 $2,338,232 1 DEEP MILL FILL DR LN, SEAL, OVERLAY
0053-09-071 US 84 Actual JUN 2013 $114,757 3 SAFETY LIGHTING
0053-09-072 US 84 Actual AUG 2013 $2,709,930 6 REPLACE BRIDGE & APPROACHES

Shackelford County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0107-03-013 FM 601 Actual APR 2013 $545,125 6 REHABILITATE BRIDGE

Taylor County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0006-18-051 BI 20-R Actual FEB 2013 $2,400,617 1 BRIDGE REPLACEMENT
0006-18-054 BI 20-R Actual AUG 2013 $1,242,845 3 LANDSCAPING, SIDEWALKS, CURB AND GUTTER, ILLUMINATION, AND
0699-03-017 FM 613 Actual AUG 2013 $2,058,773 8 REHAB & WIDEN
0908-00-078 VA Actual JAN 2013 $345,815 10 CURB RAMPS
0908-33-092 CR Actual AUG 2013 $172,121 8 UPGRADE / INSTALL RR XING PROTECTION
2398-01-046 LP 322 Actual FEB 2013 $3,787,565 1 SPOT BASE REPAIR; UNDERSEAL, OVERLAY, MBGF