Bastrop County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0114-04-064 US 290 Actual DEC 2012 $107,797 3 EXTEND LEFT TURN LANE AT MEDIAN
0265-03-038 SH 71 Actual JAN 2013 $3,366,603 1 MILL, SEAL & INLAY MAINLANES
0573-01-029 SH 304 Actual MAY 2013 $6,181,474 12 UPGRADE TO 3 - LANE SECTION WITH SHOULDERS
0807-01-024 FM 535 Actual JAN 2013 $1,167,863 6 REPLACE BRIDGE AND APPROACHES
0807-05-019 FM 535 Actual SEP 2012 $4,348,947 8 PROVIDE ADDITIONAL PAVED SURFACE WIDTH
0914-18-089 VA Actual JUL 2013 $170,483 3 PED PATH, CROSSWALKS & SCHOOLZONE SIGNS
0914-18-093 VA Actual APR 2013 $552,250 7 EROSION CNTRL, TREE REMOVAL & GRINDING
0914-18-097 VA Actual OCT 2012 $1,598,452 10 DEBRIS REMOVAL DUE TO WILDFIRE
1234-02-012 FM 1100 Actual OCT 2012 $365,625 7 ENGINEERING STUDY

Blanco County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0252-03-047 US 281 Actual DEC 2012 $4,692,433 1 MILL, SEAL & OVERLAY
0253-02-030 US 281 Actual AUG 2013 $6,301,497 3 UPGRADE TO SUPER 2 (ADD PASSING LANE)
0914-23-008 VA Actual MAY 2013 $380,852 8 INSTALL SIDEWALKS & CROSSWALKS

Burnet County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0700-01-037 SH 71 Actual OCT 2012 $711,727 1 CONSTR CONTINUOUS LEFT TURN LANE

Caldwell County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0029-03-054 US 90 Actual MAR 2013 $3,543,869 1 FULL DEPTH REPAIR, MILL, SEAL & THIN OVERLAY MIXTURE
0115-02-017 FM 20 Actual MAR 2013 $1,097,372 1 FULL DEPTH REPAIR, LEVEL - UP & SEAL
0152-03-053 US 183 Actual APR 2013 $7,526,710 1 PAVEMENT REPAIR, MILL, SEAL & OVERLAY
1434-03-010 FM 1977 Actual DEC 2012 $1,254,725 6 REPLACE BRIDGE & APPROACHES
1850-01-013 FM 1966 Actual AUG 2013 $48,128 10 2013 RAILROAD GRADE CROSSING REPLANKING PROGRAM

Gillespie County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0113-02-060 US 290 Actual JUN 2013 $3,199,722 3 ADD CENTER TURN LANE & 4 - LANE DIVIDED SECTION WITH SHOULDERS
1135-01-026 RM 783 Actual FEB 2013 $5,106,864 8 PROVIDE ADDITIONAL PAVED SURFACE WIDTH
2719-01-008 RM 2721 Actual SEP 2012 $2,899,581 8 PROVIDE ADDITIONAL PAVED SURFACE WIDTH

Hays County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0016-02-133 IH 35 Actual AUG 2013 $11,422,054 3 WIDEN EXISTING BRIDGE & ADD TURNAROUND BRDG @ CEMENT PLANT
0285-03-053 RM 12 Actual AUG 2013 $1,923,900 3 INSTALL CENTER TURN LANE & SHLDRS
0286-01-053 SH 80 Actual AUG 2013 $4,699,339 3 INTERSECTION IMPROVEMENTS
0366-01-068 SH 123 Actual JUL 2013 $791,190 8 ADD LEFT TURN LANE
0683-03-032 RM 12 Actual DEC 2012 $659,191 3 ADD TURN LANES, DRAINAGE & PLANTING AREAS
0805-01-019 RM 150 Actual MAR 2013 $814,226 1 REPAIR & THIN OVERLAY
0914-33-033 CS Actual AUG 2013 $6,518,625 3 INTERSECTION, SIGNAL AND BICYCLE PEDESTRIAN IMPROVEMENTS
0914-33-062 VA Actual APR 2013 $458,262 8 SIDEWALKS, BIKEPATH & PEDESTRIAN BRIDGE
0914-33-065 VA Actual AUG 2013 $595,570 3 CONSTRUCT 2650 LF OF ADA SIDEWALK, CROSSWALKS, BICYCLE &
1776-01-030 RM 967 Actual OCT 2012 $437,358 3 CONSTRUCT TURN LANES
2293-01-023 FM 2439 Actual AUG 2013 $2,961,890 ROW ADD CENTER TURN LANE & 2 - LANE DIVIDED SECTION WITH SHOULDERS

Lee County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0116-01-028 SH 21 Actual NOV 2012 $7,525,070 1 ADD SHLDRS., PAV REPAIR, SEAL COAT
0334-05-030 FM 141 Actual SEP 2012 $2,191,993 8 PROVIDE ADDITIONAL PAVED SURFACE WIDTH
0473-02-035 SH 21 Actual SEP 2012 $2,789,600 1 WIDEN BRIDGE & MODIFY APPROACHES
0914-21-027 PW Actual FEB 2013 $725,104 10 PAVE VARIOUS ROADS / PARK AREAS & UPGRADE VARIOUS AREAS FOR AD
0914-21-029 CR Actual MAY 2013 $570,000 6 REPLACE BRIDGE & APPROACHES

Llano County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0150-04-043 SH 29 Actual DEC 2012 $1,485,595 1 LEVEL - UP & SEAL COAT
0700-04-046 SH 71 Actual MAY 2013 $6,036,480 1 UPGRADE TO SUPER 2 & ADD LTL'S

Travis County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0015-10-061 IH 35 Actual AUG 2013 $238,426 10 LANDSCAPING AND IRRIGATION
0015-11-062 LP 275 Actual MAR 2013 $1,249,602 1 MILL, SEAL & THIN OVERLAY
0015-13-362 IH 35 Actual AUG 2013 $2,412,039 3 CONSTRUCT NB COLLECTOR - DISTRIBUTOR
0015-13-375 IH 35 Actual AUG 2013 $140,036 10 LANDSCAPING & IRRIGATION
0015-13-376 IH 35 Actual AUG 2013 $184,835 10 LANDSCAPING & IRRIGATION
0113-08-075 US 290 Actual OCT 2012 $4,638,871 ROW PROVIDE SIGNALIZED INTERSECTIONS
0113-08-076 US 290 Actual FEB 2013 $6,523,372 1 INNOVATIVE INTERSECTION IMPROVEMENT
0114-02-096 US 290 Actual AUG 2013 $2,844,477 ROW EXTENSION OF GREGG MANOR ROAD AND RECONFIGURE SIGNALS
0114-02-098 US 290 Actual APR 2013 $769,882 3 ADD EASTBOUND RIGHT TURN AND EASTBOUND & WESTBOUND LEFT TURN
0114-20-009 LP 212 Actual JUL 2013 $587,548 1 PAVEMENT REPAIR, MILL, SEAL & OVERLAY
0683-02-056 RM 620 Actual DEC 2012 $781,981 11 RESTRIPE, ADD DUAL RTL & REPL SIGNALS
0700-03-123 SH 71 Actual AUG 2013 $8,246,005 ROW ADD LEFT TURN LANE & SHOULDERS
0700-03-129 SH 71 Actual DEC 2012 $416,704 1 LEVEL & SEAL COAT
0914-00-291 VA Actual SEP 2012 $357,643 1 FY 2012 SIGNING
0914-00-314 VA Actual SEP 2012 $2,958,819 1 FY 2013 NON - SITE SPECIFIC ITS MAINTENANCE CONTRACT
0914-00-322 VA Actual MAR 2013 $865,508 1 FY 2013 NON - SITE SPECIFIC SIGNALS
0914-00-324 VA Actual APR 2013 $870,432 1 FY 2013 SITE - SPECIFIC SIGNALS
0914-00-326 VA Actual FEB 2013 $397,507 3 CONSTRUCT SIDEWALKS
0914-00-328 VA Actual MAR 2013 $792,010 3 CONSTRUCT SIDEWALKS
0914-00-337 VA Actual AUG 2013 $959,586 7 DTA MODELING
0914-00-349 VA Actual JUN 2013 $1,269,801 10 STATEWIDE CURB RAMP PROGRAM__PROJECT 14 - 02
0914-00-357 VA Actual AUG 2013 $3,607,000 3 ADVANCED TRAFFIC MANAGEMENT SYSTEM
0914-00-358 VA Actual OCT 2012 $1,931,250 7 HERO PROGRAM
0914-00-359 VA Actual FEB 2013 $71,654 7 DOWNTOWN AUSTIN TRANSP.MGMT.ASSOC.
0914-00-361 VA Actual AUG 2013 $2,704,750 3 HERO PROGRAM
0914-00-362 VA Actual FEB 2013 $71,654 7 DOWNTOWN AUSTIN TRANSP.MGMT.ASSOC.
0914-00-363 VA Actual AUG 2013 $4,181,429 3 FREIGHT RAIL BYPASS STUDY FOR LONE STAR RAIL DISTRICT TO
0914-00-364 VA Actual AUG 2013 $5,818,771 3 FREIGHT RAIL BYPASS STUDY FOR LONE STAR RAIL DISTRICT TO
0914-00-374 VA Actual AUG 2013 $583,871 1 IMPROVE TRAFFIC SIGNALS_ (SH 16, SH 29, RM 2244, RM 152 ETC.)
0914-04-095 VA Actual JUN 2013 $683,340 3 CONST BIKE TRAIL ALONG WALNUT CREEK
0914-04-191 VA Actual APR 2013 $5,643,326 3 CONSTRUCT TRAIL
0914-04-224 VA Actual JAN 2013 $1,983,974 3 DESIGN & CONST OF BIKE TRAIL
0914-04-242 CS Actual AUG 2013 $6,599,215 3 DESIGN AND CONST UPGRADE OF EXISTING 2 LANE RURAL ROADWAY
0914-04-277 VA Actual JUL 2013 $1,920,000 3 BIKE SHARE / BIKE SAFETY PROGRAM GRANT & BICYCLE SAFETY
1200-05-017 FM 973 Actual MAR 2013 $742,733 1 PVMT REPAIR, SEAL & THIN OVERLAY
1200-06-007 SH 45 Actual AUG 2013 $540,497 1 INSTALL LTL & PAVED SHOULDERS
1376-02-039 FM 1325 Actual MAR 2013 $2,027,037 1 MILL, SEAL & THIN OVERLAY
1378-01-032 RM 1431 Actual FEB 2013 $494,228 3 ADD LEFT TURN LANE
3136-01-107 LP 1 Actual JUL 2013 197,600,001 3 PHASE 1: CONSTRUCT NB AND SB MANAGED LANES_ (TOLL)
3136-01-175 LP 1 Actual JUN 2013 $200,735 11 EXTEND JOHNSON CREEK BIKE / PED TRAIL
3136-01-179 LP 1 Actual JAN 2013 $1,466,461 1 REPAIR, LEVEL & THIN OVERLAY
3277-01-013 FM 3177 Actual AUG 2013 $3,616,127 1 REALIGN RDWY
3417-01-027 FM 734 Actual MAY 2013 $335,191 1 OVERLAY & RESTRIPE FOR BICYCLE LANE
3417-03-017 FM 734 Actual APR 2013 $1,481,100 3 ADD LEFT AND RIGHT TURN LANES
3417-03-019 FM 734 Actual MAR 2013 $118,692 3 ADD EASTBOUND LEFT TURN LANE

Williamson County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0015-08-128 IH 35 Actual FEB 2013 $18,690,162 3 CONSTRUCT A THREE LANE FRONTAGE ROAD AND ASSOCIATED RAMPS
0151-03-039 SH 29 Actual JAN 2013 $727,122 1 MILL, SEAL & OVERLAY
0151-04-067 US 183 Actual MAR 2013 $867,875 1 PAVEMENT REPAIR, UNDERSEAL & OVERLAY
0151-05-097 US 183 Actual AUG 2013 $529,532 3 CONSTRUCT DECELERATION LANE
0151-05-101 US 183 Actual OCT 2012 $5,000,000 7 MANAGED LANES STUDY
0151-05-102 US 183 Actual AUG 2013 $1,908,325 3 MANAGED LANES STUDY
0151-05-103 US 183 Actual AUG 2013 $344,399 3 ADD RTL & DUAL LTL LANES
0334-01-030 FM 112 Actual JUL 2013 $1,409,491 6 REPLACE BRIDGE & APPROACHES
0440-01-039 SH 195 Actual JUN 2013 $33,311,110 3 WIDEN TO FOUR LANE DIVIDED HIGHWAY
0440-02-010 SH 195 Actual SEP 2012 $18,778,888 1 WIDEN TO FOUR LANE DIVIDED HIGHWAY
0683-01-079 RM 620 Actual JAN 2013 $11,281,113 3 WIDEN TO 4 - LANE DIVIDED ROADWAY
0914-05-161 VA Actual AUG 2013 $1,972,744 3 CONST TRAIL
0914-05-170 VA Actual JUL 2013 $398,538 3 CONSTRUCT SIDEWALKS & CROSSWALKS
0914-05-175 CS Actual AUG 2013 $3,876,529 3 WIDEN, ADD LTLS, SIDEWALKS & LIGHTING
1202-01-016 FM 972 Actual AUG 2013 $535,693 6 REPLACE BRIDGE AND APPROACHES
1378-02-039 RM 1431 Actual AUG 2013 $3,965,955 3 INNOVATIVE INTERSECTION IMPROVEMENTS
1378-02-044 RM 1431 Actual AUG 2013 $121,900 10 2013 RAILROAD GRADE CROSSING REPLANKING PROGRAM
2690-01-033 FM 971 Actual MAR 2013 $1,487,610 1 SPOT PAVEMENT REPAIRS AND ONE COURSE SURFACE TREATMENT


Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract