Detail Letting Schedule for Liberty County (FY 2013)
Liberty County (FY 2013) |
CCSJ: 0028-05-042 | |||
District: | Beaumont | Let Date: | JUN 2013 |
Highway: | US 90 | Let Status: | Actual |
Project ID: | STP 2013(796)MM | CSJ: | 0028-05-042 |
Description: | ADD 2 LANES TO EXISTING 2 LANE HIGHWAY | Handling Code: |
|
Limits From: | SH 61 IN DEVERS | Fund Cat: | 7 |
Limits To: | 4.0 MI W OF JEFFERSON CO. LINE | Estimate: | $17,526,485 |
Length: | 5.4 Miles | Actual: | $20,677,586 |
Back... |
Totals for 0028-05-042 | ||
---|---|---|---|
Length: | 5.4 Miles | ||
Estimate: | $17,526,485 | ||
Actual: | $20,677,586 | ||
CCSJ: 0762-01-029 | |||
District: | Beaumont | Let Date: | NOV 2012 |
Highway: | FM 686 | Let Status: | Actual |
Project ID: | STP 2013(183) | CSJ: | 0762-01-029 |
Description: | RESTORE EXISTING ROADWAY | Handling Code: |
|
Limits From: | FM 1960, EAST | Fund Cat: | 1 |
Limits To: | 2.4 MI | Estimate: | $1,031,212 |
Length: | 2.4 Miles | Actual: | $824,500 |
Back... |
Totals for 0762-01-029 | ||
Length: | 2.4 Miles | ||
Estimate: | $1,031,212 | ||
Actual: | $824,500 | ||
CCSJ: 0762-01-031 | |||
District: | Beaumont | Let Date: | NOV 2012 |
Highway: | FM 1960 | Let Status: | Actual |
Project ID: | STP 2013(184) | CSJ: | 0762-01-031 |
Description: | ADD CONTINUOUS LEFT TURN LANE AND INSTALL PASSING LANES | Handling Code: |
|
Limits From: | FM 686, EAST | Fund Cat: | 12 |
Limits To: | SH 321 | Estimate: | $2,152,105 |
Length: | 6.1 Miles | Actual: | $2,286,546 |
District: | Beaumont | Let Date: | NOV 2012 |
Highway: | FM 1960 | Let Status: | Actual |
Project ID: | STP 2013(184) | CSJ: | 1685-04-022 |
Description: | INSTALL PASSING LANES | Handling Code: |
|
Limits From: | 1.2 MI W OF FM 686 | Fund Cat: | 12 |
Limits To: | FM 686 | Estimate: | $482,686 |
Length: | 1.1 Miles | Actual: | $518,864 |
Back... |
Totals for 0762-01-031 | ||
Length: | 7.2 Miles | ||
Estimate: | $2,634,791 | ||
Actual: | $2,805,410 | ||
CCSJ: 0813-01-096 | |||
District: | Beaumont | Let Date: | AUG 2013 |
Highway: | FM 787 | Let Status: | Actual |
Project ID: | BR 2013(921) | CSJ: | 0813-01-096 |
Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: |
|
Limits From: | AT TARKINGTON BAYOU | Fund Cat: | 6 |
Limits To: | (STR 081301009) | Estimate: | $1,486,476 |
Length: | 0.1 Miles | Actual: | $1,341,288 |
Back... |
Totals for 0813-01-096 | ||
Length: | 0.1 Miles | ||
Estimate: | $1,486,476 | ||
Actual: | $1,341,288 | ||
CCSJ: 0920-02-088 | |||
District: | Beaumont | Let Date: | AUG 2013 |
Highway: | CR | Let Status: | Actual |
Project ID: | STP 2013(368)FRS | CSJ: | 0920-02-088 |
Description: | UPGRADE RAILROAD SIGNAL | Handling Code: |
XX |
Limits From: | CR 2148 AT BNSF RR IN ROMAYOR | Fund Cat: | 8 |
Limits To: | (DOT 024411Y) | Estimate: | $183,611 |
Length: | 0.1 Miles | Actual: | $183,611 |
Back... |
Totals for 0920-02-088 | ||
Length: | 0.1 Miles | ||
Estimate: | $183,611 | ||
Actual: | $183,611 | ||
CCSJ: 1023-02-047 | |||
District: | Beaumont | Let Date: | OCT 2012 |
Highway: | FM 563 | Let Status: | Actual |
Project ID: | STP 2013(133)HES | CSJ: | 1023-02-047 |
Description: | PROVIDE ADDITIONAL PAVED SURFACE WIDTH | Handling Code: |
|
Limits From: | 1.309 MI S OF US 90, SOUTH | Fund Cat: | 8 |
Limits To: | 9.366 MI S OF US 90 | Estimate: | $2,779,021 |
Length: | 8.1 Miles | Actual: | $2,638,787 |
Back... |
Totals for 1023-02-047 | ||
Length: | 8.1 Miles | ||
Estimate: | $2,779,021 | ||
Actual: | $2,638,787 | ||
CCSJ: 1421-01-024 | |||
District: | Beaumont | Let Date: | AUG 2013 |
Highway: | FM 1413 | Let Status: | Actual |
Project ID: | STP 2013(923) | CSJ: | 1421-01-024 |
Description: | PROVIDE ADDITIONAL PAVED SURFACE WIDTH (WIDENING TO 28 FT.) | Handling Code: |
|
Limits From: | US 90 | Fund Cat: | 1 |
Limits To: | UP RR | Estimate: | $1,826,586 |
Length: | 4.6 Miles | Actual: | $2,173,548 |
Back... |
Totals for 1421-01-024 | ||
Length: | 4.6 Miles | ||
Estimate: | $1,826,586 | ||
Actual: | $2,173,548 | ||
CCSJ: 2381-01-009 | |||
District: | Beaumont | Let Date: | JAN 2013 |
Highway: | FM 2518 | Let Status: | Actual |
Project ID: | STP 2013(314)HES | CSJ: | 2381-01-009 |
Description: | PROVIDE ADDITIONAL PAVED SURFACE WIDTH | Handling Code: |
|
Limits From: | FM 787, SOUTH | Fund Cat: | 8 |
Limits To: | FM 163 | Estimate: | $2,397,638 |
Length: | 5.3 Miles | Actual: | $2,196,076 |
Back... |
Totals for 2381-01-009 | ||
Length: | 5.3 Miles | ||
Estimate: | $2,397,638 | ||
Actual: | $2,196,076 |
|