Detail Letting Schedule for Nueces County (FY 2013)
Nueces County (FY 2013) |
CCSJ: 0074-06-217 | |||
District: | Corpus Christi | Let Date: | OCT 2012 |
Highway: | IH 37 | Let Status: | Actual |
Project ID: | IM 0371(134) | CSJ: | 0074-06-217 |
Description: | FY 13 LOW CONTROL SEAL COAT PROJECT (FRTG LANES ONLY) | Handling Code: |
|
Limits From: | CORN PRODUCTS ROAD | Fund Cat: | 1 |
Limits To: | NUECES RIVER BRIDGE | Estimate: | $1,200,522 |
Length: | 11.5 Miles | Actual: | $1,302,880 |
District: | Corpus Christi | Let Date: | OCT 2012 |
Highway: | US 181 | Let Status: | Actual |
Project ID: | NH 2013(107) | CSJ: | 0074-06-218 |
Description: | FY 2013 SEAL COAT PROJECT (FRONTAGE LANES ONLY) | Handling Code: |
|
Limits From: | 0.068 MILES N. OF PALO ALTO ST. | Fund Cat: | 1 |
Limits To: | BELDEN ST. | Estimate: | $5,926 |
Length: | 0.2 Miles | Actual: | $5,713 |
District: | Corpus Christi | Let Date: | OCT 2012 |
Highway: | FM 665 | Let Status: | Actual |
Project ID: | STP 2013(108) | CSJ: | 0086-19-029 |
Description: | FY 2013 SEAL COAT PROJECT | Handling Code: |
|
Limits From: | FM 1352 | Fund Cat: | 1 |
Limits To: | NUECES/JIM WELLS COUNTY LINE | Estimate: | $305,561 |
Length: | 8.3 Miles | Actual: | $297,862 |
District: | Corpus Christi | Let Date: | OCT 2012 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | NH 2013(107) | CSJ: | 0088-01-065 |
Description: | FY 2013 SEAL COAT PROJECT | Handling Code: |
|
Limits From: | GOLIAD COUNTY LINE | Fund Cat: | 1 |
Limits To: | US 181 BY PASS | Estimate: | $758,834 |
Length: | 11.2 Miles | Actual: | $735,518 |
District: | Corpus Christi | Let Date: | OCT 2012 |
Highway: | US 181 | Let Status: | Actual |
Project ID: | STP 2013(108) | CSJ: | 0101-06-107 |
Description: | FY 2013 SEAL COAT PROJECT_ (FRONTAGE LANES ONLY) | Handling Code: |
|
Limits From: | 1706 FT. N. OF FITZGERALD ST. | Fund Cat: | 1 |
Limits To: | FITZGERALD ST. | Estimate: | $10,746 |
Length: | 0.3 Miles | Actual: | $10,391 |
District: | Corpus Christi | Let Date: | OCT 2012 |
Highway: | US 183 | Let Status: | Actual |
Project ID: | STP 2013(108) | CSJ: | 0155-04-050 |
Description: | FY 2013 SEAL COAT PROJECT | Handling Code: |
|
Limits From: | 4.8 MILES N. OF REFUGIO CO. LINE | Fund Cat: | 1 |
Limits To: | REFUGIO COUNTY LINE | Estimate: | $225,806 |
Length: | 4.8 Miles | Actual: | $220,594 |
District: | Corpus Christi | Let Date: | OCT 2012 |
Highway: | US 183 | Let Status: | Actual |
Project ID: | STP 2013(108) | CSJ: | 0155-05-037 |
Description: | FY 2013 SEAL COAT PROJECT | Handling Code: |
|
Limits From: | GOLIAD COUNTY LINE | Fund Cat: | 1 |
Limits To: | U.S. 77 | Estimate: | $425,348 |
Length: | 8.6 Miles | Actual: | $416,976 |
District: | Corpus Christi | Let Date: | OCT 2012 |
Highway: | BU 281R | Let Status: | Actual |
Project ID: | STP 2013(108) | CSJ: | 0254-03-075 |
Description: | SEAL COAT PROJECT (2013 SEAL COAT PROJECT) | Handling Code: |
|
Limits From: | OAN DIEGO CR. | Fund Cat: | 1 |
Limits To: | N. OF STAPLES ST. (CONTROL BRK.) | Estimate: | $182,237 |
Length: | 2.3 Miles | Actual: | $179,221 |
District: | Corpus Christi | Let Date: | OCT 2012 |
Highway: | US 281 | Let Status: | Actual |
Project ID: | NH 2013(107) | CSJ: | 0255-01-078 |
Description: | FY 2013 SEAL COAT PROJECT | Handling Code: |
|
Limits From: | SH 141 | Fund Cat: | 1 |
Limits To: | APPROX. 5.6 MI SO OF SH141 (CONT BK | Estimate: | $505,721 |
Length: | 5.6 Miles | Actual: | $526,356 |
District: | Corpus Christi | Let Date: | OCT 2012 |
Highway: | BU 281R | Let Status: | Actual |
Project ID: | STP 2013(108) | CSJ: | 0255-01-079 |
Description: | SEAL COAT PROJECT (2013 SEAL COAT PROJECT) | Handling Code: |
|
Limits From: | N. OF STAPLES ST. (CONTROL BRK.) | Fund Cat: | 1 |
Limits To: | FM 1352 | Estimate: | $15,997 |
Length: | 0.2 Miles | Actual: | $15,617 |
District: | Corpus Christi | Let Date: | OCT 2012 |
Highway: | US 281 | Let Status: | Actual |
Project ID: | NH 2013(107) | CSJ: | 0255-02-052 |
Description: | FY 2013 SEAL COAT PROJECT | Handling Code: |
|
Limits From: | APPROX. 5.6 MI S OF SH141 (CONT BK | Fund Cat: | 1 |
Limits To: | BROOKS/JIM WELL COUNTY LINE | Estimate: | $1,308,339 |
Length: | 14.4 Miles | Actual: | $1,350,380 |
District: | Corpus Christi | Let Date: | OCT 2012 |
Highway: | SH 72 | Let Status: | Actual |
Project ID: | STP 2013(108) | CSJ: | 0270-07-028 |
Description: | FY 2013 SEAL COAT PROJECT | Handling Code: |
|
Limits From: | BEE COUNTY LINE | Fund Cat: | 1 |
Limits To: | US 181 | Estimate: | $579,860 |
Length: | 12.0 Miles | Actual: | $563,343 |
District: | Corpus Christi | Let Date: | OCT 2012 |
Highway: | SH 286 | Let Status: | Actual |
Project ID: | STP 2013(108) | CSJ: | 0326-01-057 |
Description: | FY 2013 SEAL COAT PROJECT (FRONTAGE LANES ONLY) | Handling Code: |
|
Limits From: | SH 358 | Fund Cat: | 1 |
Limits To: | SH 357 | Estimate: | $217,809 |
Length: | 1.7 Miles | Actual: | $212,918 |
District: | Corpus Christi | Let Date: | OCT 2012 |
Highway: | SH 286 | Let Status: | Actual |
Project ID: | STP 2013(108) | CSJ: | 0326-03-093 |
Description: | FY 2013 SEAL COAT PROJECT_ (FRTG LANES ONLY) | Handling Code: |
|
Limits From: | GOLLIHAR RD. | Fund Cat: | 1 |
Limits To: | SH 358 | Estimate: | $72,626 |
Length: | 0.8 Miles | Actual: | $70,859 |
District: | Corpus Christi | Let Date: | OCT 2012 |
Highway: | FM 2040 | Let Status: | Actual |
Project ID: | STP 2013(108) | CSJ: | 0350-03-014 |
Description: | FY 2013 SEAL COAT PROJECT | Handling Code: |
|
Limits From: | FM 774 | Fund Cat: | 1 |
Limits To: | ARANSAS COUNTY LINE | Estimate: | $136,619 |
Length: | 5.5 Miles | Actual: | $127,922 |
District: | Corpus Christi | Let Date: | OCT 2012 |
Highway: | FM 2040 | Let Status: | Actual |
Project ID: | STP 2013(108) | CSJ: | 0350-04-010 |
Description: | FY 2013 SEAL COAT PROJECT | Handling Code: |
|
Limits From: | REFUGIO COUNTY LINE | Fund Cat: | 1 |
Limits To: | END OF MAINTENACE | Estimate: | $21,529 |
Length: | 0.8 Miles | Actual: | $20,179 |
District: | Corpus Christi | Let Date: | OCT 2012 |
Highway: | SH 123 | Let Status: | Actual |
Project ID: | STP 2013(108) | CSJ: | 0366-06-040 |
Description: | FY 2013 SEAL COAT PROJECT | Handling Code: |
|
Limits From: | CIBOLO CREEK BRIDGE | Fund Cat: | 1 |
Limits To: | HMAC JOINT NORTH OF SH 80 | Estimate: | $392,680 |
Length: | 8.6 Miles | Actual: | $384,147 |
District: | Corpus Christi | Let Date: | OCT 2012 |
Highway: | SP 22 | Let Status: | Actual |
Project ID: | STP 2013(108) | CSJ: | 0373-01-101 |
Description: | FY 2013 SEAL COAT PROJECT | Handling Code: |
|
Limits From: | SH 44 | Fund Cat: | 1 |
Limits To: | BU 77-U | Estimate: | $27,769 |
Length: | 0.3 Miles | Actual: | $27,105 |
District: | Corpus Christi | Let Date: | OCT 2012 |
Highway: | FM 774 | Let Status: | Actual |
Project ID: | STP 2013(108) | CSJ: | 0447-05-066 |
Description: | FY 2013 SEAL COAT PROJECT | Handling Code: |
|
Limits From: | US 77 | Fund Cat: | 1 |
Limits To: | FM 2040 | Estimate: | $763,201 |
Length: | 30.2 Miles | Actual: | $746,378 |
District: | Corpus Christi | Let Date: | OCT 2012 |
Highway: | FM 631 | Let Status: | Actual |
Project ID: | STP 2013(108) | CSJ: | 0507-02-051 |
Description: | FY 2013 SEAL COAT PROJECT | Handling Code: |
|
Limits From: | FM 2512 | Fund Cat: | 1 |
Limits To: | US 181 | Estimate: | $143,879 |
Length: | 3.7 Miles | Actual: | $140,793 |
District: | Corpus Christi | Let Date: | OCT 2012 |
Highway: | SH 188 | Let Status: | Actual |
Project ID: | STP 2013(108) | CSJ: | 0507-03-041 |
Description: | FY 2013 SEAL COAT PROJECT | Handling Code: |
|
Limits From: | FM 136 | Fund Cat: | 1 |
Limits To: | ARANSAS COUNTY LINE | Estimate: | $41,359 |
Length: | 0.9 Miles | Actual: | $40,628 |
District: | Corpus Christi | Let Date: | OCT 2012 |
Highway: | SH 188 | Let Status: | Actual |
Project ID: | STP 2013(108) | CSJ: | 0507-04-040 |
Description: | FY 2013 SEAL COAT PROJECT | Handling Code: |
|
Limits From: | SAN PATRICIO COUNTY LINE | Fund Cat: | 1 |
Limits To: | .156 MI. W OF FM 1069 | Estimate: | $298,936 |
Length: | 6.2 Miles | Actual: | $292,251 |
District: | Corpus Christi | Let Date: | OCT 2012 |
Highway: | SH 358 | Let Status: | Actual |
Project ID: | STP 2013(108) | CSJ: | 0617-01-184 |
Description: | FY 2013 SEAL COAT PROJECT_ (FRONTAGE LANES ONLY) | Handling Code: |
|
Limits From: | AGNES | Fund Cat: | 1 |
Limits To: | GREENWOOD | Estimate: | $449,570 |
Length: | 3.7 Miles | Actual: | $436,794 |
District: | Corpus Christi | Let Date: | OCT 2012 |
Highway: | FM 665 | Let Status: | Actual |
Project ID: | STP 2013(108) | CSJ: | 1052-02-079 |
Description: | FY 2013 SEAL COAT PROJECT | Handling Code: |
|
Limits From: | SH 357 | Fund Cat: | 1 |
Limits To: | SS 544 (AGNES) | Estimate: | $332,848 |
Length: | 4.9 Miles | Actual: | $325,476 |
District: | Corpus Christi | Let Date: | OCT 2012 |
Highway: | SH 357 | Let Status: | Actual |
Project ID: | STP 2013(108) | CSJ: | 1069-01-034 |
Description: | FY 2013 SEAL COAT PROJECT | Handling Code: |
|
Limits From: | RODD FIELD RD. | Fund Cat: | 1 |
Limits To: | SH 358 | Estimate: | $140,382 |
Length: | 1.7 Miles | Actual: | $138,032 |
District: | Corpus Christi | Let Date: | OCT 2012 |
Highway: | FM 1069 | Let Status: | Actual |
Project ID: | STP 2013(108) | CSJ: | 1549-04-028 |
Description: | FY 2013 SEAL COAT PROJECT | Handling Code: |
|
Limits From: | FM 2725 | Fund Cat: | 1 |
Limits To: | END OF MAINTENANCE | Estimate: | $47,086 |
Length: | 1.2 Miles | Actual: | $46,220 |
District: | Corpus Christi | Let Date: | OCT 2012 |
Highway: | FM 1931 | Let Status: | Actual |
Project ID: | STP 2013(108) | CSJ: | 1693-01-022 |
Description: | FY 2013 SEAL COAT PROJECT | Handling Code: |
|
Limits From: | SH 44 | Fund Cat: | 1 |
Limits To: | FM 665 | Estimate: | $111,199 |
Length: | 2.3 Miles | Actual: | $108,356 |
District: | Corpus Christi | Let Date: | OCT 2012 |
Highway: | FM 1961 | Let Status: | Actual |
Project ID: | STP 2013(108) | CSJ: | 1843-01-021 |
Description: | FY 2013 SEAL COAT PROJECT | Handling Code: |
|
Limits From: | CR 172 (HENCERLING RD) | Fund Cat: | 1 |
Limits To: | FM 622 | Estimate: | $369,836 |
Length: | 1.2 Miles | Actual: | $347,289 |
District: | Corpus Christi | Let Date: | OCT 2012 |
Highway: | FM 2292 | Let Status: | Actual |
Project ID: | NH 2013(107) | CSJ: | 2142-01-025 |
Description: | FY 2013 SEAL COAT PROJECT | Handling Code: |
|
Limits From: | 500' S. OF MCNORTON | Fund Cat: | 1 |
Limits To: | BS 44-D | Estimate: | $73,903 |
Length: | 1.9 Miles | Actual: | $71,280 |
District: | Corpus Christi | Let Date: | OCT 2012 |
Highway: | FM 2292 | Let Status: | Actual |
Project ID: | STP 2013(108) | CSJ: | 2142-02-014 |
Description: | FY 2013 SEAL COAT PROJECT | Handling Code: |
|
Limits From: | BS 44-D | Fund Cat: | 1 |
Limits To: | SH 44 (BY PASS) | Estimate: | $20,947 |
Length: | 0.3 Miles | Actual: | $20,889 |
District: | Corpus Christi | Let Date: | OCT 2012 |
Highway: | SH 188 | Let Status: | Actual |
Project ID: | STP 2013(108) | CSJ: | 2607-01-010 |
Description: | FY 2013 SEAL COAT PROJECT | Handling Code: |
|
Limits From: | .156 MI W OF FM 1069 | Fund Cat: | 1 |
Limits To: | BS 35-L | Estimate: | $136,011 |
Length: | 2.6 Miles | Actual: | $133,577 |
District: | Corpus Christi | Let Date: | OCT 2012 |
Highway: | FM 2725 | Let Status: | Actual |
Project ID: | STP 2013(108) | CSJ: | 2756-01-013 |
Description: | FY 2013 SEAL COAT PROJECT | Handling Code: |
|
Limits From: | SH 361 | Fund Cat: | 1 |
Limits To: | FM 1069 | Estimate: | $118,386 |
Length: | 3.5 Miles | Actual: | $116,582 |
District: | Corpus Christi | Let Date: | OCT 2012 |
Highway: | FM 3036 | Let Status: | Actual |
Project ID: | STP 2013(108) | CSJ: | 3116-01-007 |
Description: | FY 2013 SEAL COAT PROJECT | Handling Code: |
|
Limits From: | FM 1781 | Fund Cat: | 1 |
Limits To: | SH 35 (BY PASS) | Estimate: | $36,031 |
Length: | 0.6 Miles | Actual: | $35,233 |
District: | Corpus Christi | Let Date: | OCT 2012 |
Highway: | FM 3386 | Let Status: | Actual |
Project ID: | STP 2013(108) | CSJ: | 3364-01-018 |
Description: | FY 2013 SEAL COAT PROJECT | Handling Code: |
|
Limits From: | CONSTRUCTION 1.266 MI. N. OF SH 44 | Fund Cat: | 1 |
Limits To: | SH 44 | Estimate: | $48,122 |
Length: | 1.3 Miles | Actual: | $46,590 |
Back... |
Totals for 0074-06-217 | ||
---|---|---|---|
Length: | 163.3 Miles | ||
Estimate: | $9,525,625 | ||
Actual: | $9,514,349 | ||
CCSJ: 0102-02-096 | |||
District: | Corpus Christi | Let Date: | JUL 2013 |
Highway: | US 77 | Let Status: | Actual |
Project ID: | C 102-2-96 | CSJ: | 0102-02-096 |
Description: | CONSTRUCT MAIN LANES AND OVERPASSES | Handling Code: |
|
Limits From: | FM 892 | Fund Cat: | 3 |
Limits To: | S OF CR 28 | Estimate: | $36,107,859 |
Length: | 4.0 Miles | Actual: | $38,721,708 |
Back... |
Totals for 0102-02-096 | ||
Length: | 4.0 Miles | ||
Estimate: | $36,107,859 | ||
Actual: | $38,721,708 | ||
CCSJ: 0102-02-099 | |||
District: | Corpus Christi | Let Date: | MAY 2013 |
Highway: | SH 44 | Let Status: | Actual |
Project ID: | NH 2013(656) | CSJ: | 0102-02-099 |
Description: | CONSTRUCT OVERPASS | Handling Code: |
|
Limits From: | AT FM 1694/SH 44 INTERSECTION | Fund Cat: | 12 |
Limits To: | . | Estimate: | $12,587,021 |
Length: | 0.8 Miles | Actual: | $12,713,098 |
Back... |
Totals for 0102-02-099 | ||
Length: | 0.8 Miles | ||
Estimate: | $12,587,021 | ||
Actual: | $12,713,098 | ||
CCSJ: 0102-03-081 | |||
District: | Corpus Christi | Let Date: | AUG 2013 |
Highway: | US 77 | Let Status: | Actual |
Project ID: | NH 2013(287) | CSJ: | 0102-03-081 |
Description: | CONSTRUCT MAIN LANES AND OVERPASSES | Handling Code: |
DB |
Limits From: | FM 3354 | Fund Cat: | 12 |
Limits To: | KLEBERG CO. LINE | Estimate: | $60,000,000 |
Length: | 4.8 Miles | Actual: | $56,500,697 |
District: | Corpus Christi | Let Date: | AUG 2013 |
Highway: | US 77 | Let Status: | Actual |
Project ID: | NH 2013(287) | CSJ: | 0102-04-096 |
Description: | CONSTRUCT MAINLANES AND PARTIAL FRONTAGE ROADS | Handling Code: |
DB |
Limits From: | NUECES CO. LINE | Fund Cat: | 12 |
Limits To: | FM 1898 | Estimate: | $9,000,000 |
Length: | 3.1 Miles | Actual: | $22,419,081 |
Back... |
Totals for 0102-03-081 | ||
Length: | 7.9 Miles | ||
Estimate: | $69,000,000 | ||
Actual: | $78,919,778 | ||
CCSJ: 0326-01-052 | |||
District: | Corpus Christi | Let Date: | JUN 2013 |
Highway: | SH 286 | Let Status: | Actual |
Project ID: | NH 2013(795) | CSJ: | 0326-01-052 |
Description: | COMPLETE FREEWAY SECTION | Handling Code: |
|
Limits From: | SH 357 | Fund Cat: | 11 |
Limits To: | 1 MI S OF FM 43 | Estimate: | $31,272,495 |
Length: | 2.8 Miles | Actual: | $45,818,725 |
Back... |
Totals for 0326-01-052 | ||
Length: | 2.8 Miles | ||
Estimate: | $31,272,495 | ||
Actual: | $45,818,725 | ||
CCSJ: 0373-05-033 | |||
District: | Corpus Christi | Let Date: | AUG 2013 |
Highway: | BS 44-C | Let Status: | Actual |
Project ID: | CRX 373-5-33 | CSJ: | 0373-05-033 |
Description: | REPLANK RAILROAD CROSSING | Handling Code: |
XX |
Limits From: | AT UPRR IN ROBSTOWN | Fund Cat: | 10 |
Limits To: | DOT #427598L | Estimate: | $84,224 |
Length: | 0.2 Miles | Actual: | $84,224 |
Back... |
Totals for 0373-05-033 | ||
Length: | 0.2 Miles | ||
Estimate: | $84,224 | ||
Actual: | $84,224 | ||
CCSJ: 0617-01-180 | |||
District: | Corpus Christi | Let Date: | MAR 2013 |
Highway: | SH 358 | Let Status: | Actual |
Project ID: | NH 2013(446) | CSJ: | 0617-01-180 |
Description: | MILL AND OVERLAY ROADWAY | Handling Code: |
|
Limits From: | IH 37 | Fund Cat: | 1 |
Limits To: | WEST POINT ROAD | Estimate: | $2,196,739 |
Length: | 4.1 Miles | Actual: | $2,878,357 |
Back... |
Totals for 0617-01-180 | ||
Length: | 4.1 Miles | ||
Estimate: | $2,196,739 | ||
Actual: | $2,878,357 | ||
CCSJ: 0617-01-183 | |||
District: | Corpus Christi | Let Date: | JAN 2013 |
Highway: | SH 358 | Let Status: | Actual |
Project ID: | STP 2013(343) | CSJ: | 0617-01-183 |
Description: | NOVACHIP (FRTG LANES ONLY) | Handling Code: |
|
Limits From: | AYERS ST. | Fund Cat: | 1 |
Limits To: | PAUL JONES AVE. | Estimate: | $2,987,596 |
Length: | 5.8 Miles | Actual: | $3,492,994 |
District: | Corpus Christi | Let Date: | JAN 2013 |
Highway: | SP 3 | Let Status: | Actual |
Project ID: | NH 2013(342) | CSJ: | 3596-01-004 |
Description: | NOVACHIP ON SP 3 | Handling Code: |
|
Limits From: | BEGIN OF RD AT TEXAS A&M CC | Fund Cat: | 1 |
Limits To: | SH 358 | Estimate: | $1,093,257 |
Length: | 3.4 Miles | Actual: | $1,245,758 |
Back... |
Totals for 0617-01-183 | ||
Length: | 9.2 Miles | ||
Estimate: | $4,080,853 | ||
Actual: | $4,738,752 | ||
CCSJ: 0617-02-063 | |||
District: | Corpus Christi | Let Date: | MAR 2013 |
Highway: | PR 22 | Let Status: | Actual |
Project ID: | NH 2013(447) | CSJ: | 0617-02-063 |
Description: | MILL AND OVERLAY ROADWAY | Handling Code: |
|
Limits From: | SH 358 INTERS. | Fund Cat: | 1 |
Limits To: | SH 361 INTERS. | Estimate: | $2,506,626 |
Length: | 6.0 Miles | Actual: | $2,212,952 |
Back... |
Totals for 0617-02-063 | ||
Length: | 6.0 Miles | ||
Estimate: | $2,506,626 | ||
Actual: | $2,212,952 | ||
CCSJ: 0916-00-069 | |||
District: | Corpus Christi | Let Date: | MAY 2013 |
Highway: | VA | Let Status: | Actual |
Project ID: | ITS 99(714) | CSJ: | 0916-00-069 |
Description: | INSTALL FIBER OPTIC LINE TO INTERGRATE WITH CORPUS CHRISTI | Handling Code: |
|
Limits From: | AT VARIOUS LOCATIONS IN NUECES CO. | Fund Cat: | 10 |
Limits To: | . | Estimate: | $906,784 |
Length: | 0.1 Miles | Actual: | $946,694 |
Back... |
Totals for 0916-00-069 | ||
Length: | 0.1 Miles | ||
Estimate: | $906,784 | ||
Actual: | $946,694 | ||
CCSJ: 0916-00-071 | |||
District: | Corpus Christi | Let Date: | AUG 2013 |
Highway: | VA | Let Status: | Actual |
Project ID: | STP 2013(976) | CSJ: | 0916-00-071 |
Description: | INTERSECTION IMPROVEMENTS | Handling Code: |
|
Limits From: | AT VARIOUS LOCATIONS IN KARNES CO. | Fund Cat: | 1 |
Limits To: | . | Estimate: | $6,253,026 |
Length: | 0.1 Miles | Actual: | $5,181,782 |
District: | Corpus Christi | Let Date: | AUG 2013 |
Highway: | VA | Let Status: | Actual |
Project ID: | STP 2013(976) | CSJ: | 0916-00-072 |
Description: | INTERSECTION IMPROVEMTNTS | Handling Code: |
|
Limits From: | AT VARIOUS LOCATIONS IN GOLIAD CO. | Fund Cat: | 1 |
Limits To: | . | Estimate: | $2,843,827 |
Length: | 0.1 Miles | Actual: | $2,611,107 |
Back... |
Totals for 0916-00-071 | ||
Length: | 0.2 Miles | ||
Estimate: | $9,096,853 | ||
Actual: | $7,792,889 | ||
CCSJ: 0916-00-073 | |||
District: | Corpus Christi | Let Date: | AUG 2013 |
Highway: | VA | Let Status: | Actual |
Project ID: | NH 2013(977) | CSJ: | 0916-00-073 |
Description: | INTERSECTION IMPROVEMENTS | Handling Code: |
|
Limits From: | AT VARIOUS LOCATIONS IN LIVE OAK CO | Fund Cat: | 1 |
Limits To: | . | Estimate: | $1,621,884 |
Length: | 0.1 Miles | Actual: | $1,596,653 |
Back... |
Totals for 0916-00-073 | ||
Length: | 0.1 Miles | ||
Estimate: | $1,621,884 | ||
Actual: | $1,596,653 | ||
CCSJ: 0916-35-173 | |||
District: | Corpus Christi | Let Date: | AUG 2013 |
Highway: | VA | Let Status: | Actual |
Project ID: | STP 2013(880)MM | CSJ: | 0916-35-173 |
Description: | FEASIBILITY STUDY FOR PEDESTRIAN IMPROVEMENTS | Handling Code: |
XX |
Limits From: | VARIOUS LOCATIONS IN CORPUS CHRISTI | Fund Cat: | 7 |
Limits To: | . | Estimate: | $200,000 |
Length: | 0.1 Miles | Actual: | $200,000 |
Back... |
Totals for 0916-35-173 | ||
Length: | 0.1 Miles | ||
Estimate: | $200,000 | ||
Actual: | $200,000 | ||
CCSJ: 1557-01-037 | |||
District: | Corpus Christi | Let Date: | APR 2013 |
Highway: | FM 43 | Let Status: | Actual |
Project ID: | STP 2013(556)MM | CSJ: | 1557-01-037 |
Description: | CONSTRUCT ADDITIONAL TRAVEL LANES | Handling Code: |
|
Limits From: | SH 286 | Fund Cat: | 11 |
Limits To: | YORKTOWN BLVD. | Estimate: | $9,630,978 |
Length: | 1.9 Miles | Actual: | $9,863,126 |
Back... |
Totals for 1557-01-037 | ||
Length: | 1.9 Miles | ||
Estimate: | $9,630,978 | ||
Actual: | $9,863,126 | ||
CCSJ: 2263-02-090 | |||
District: | Corpus Christi | Let Date: | MAY 2013 |
Highway: | SH 361 | Let Status: | Actual |
Project ID: | FBD 2012(170) | CSJ: | 2263-02-090 |
Description: | INSTALLATION OF PILINGS | Handling Code: |
NC |
Limits From: | AT FERRY BOAT LANDINGS | Fund Cat: | 10 |
Limits To: | . | Estimate: | $897,600 |
Length: | 0.3 Miles | Actual: | $893,650 |
District: | Corpus Christi | Let Date: | MAY 2013 |
Highway: | SH 361 | Let Status: | Actual |
Project ID: | FBD 2012(170) | CSJ: | 2263-02-093 |
Description: | INSTALLATION OF MOORING & DOCKING SYSTEM | Handling Code: |
NC |
Limits From: | AT THE FERRY BOAT OPERATIONS | Fund Cat: | 10 |
Limits To: | . | Estimate: | $2,214,800 |
Length: | 0.3 Miles | Actual: | $2,262,530 |
Back... |
Totals for 2263-02-090 | ||
Length: | 0.6 Miles | ||
Estimate: | $3,112,400 | ||
Actual: | $3,156,180 | ||
CCSJ: 2263-02-091 | |||
District: | Corpus Christi | Let Date: | SEP 2012 |
Highway: | SH 361 | Let Status: | Actual |
Project ID: | FBD 2012(227) | CSJ: | 2263-02-091 |
Description: | BULKHEAD REPAIRS | Handling Code: |
NC |
Limits From: | AT FERRY BOAT LANDINGS | Fund Cat: | 10 |
Limits To: | . | Estimate: | $431,974 |
Length: | 0.3 Miles | Actual: | $508,752 |
Back... |
Totals for 2263-02-091 | ||
Length: | 0.3 Miles | ||
Estimate: | $431,974 | ||
Actual: | $508,752 | ||
CCSJ: 2343-01-036 | |||
District: | Corpus Christi | Let Date: | AUG 2013 |
Highway: | FM 2444 | Let Status: | Actual |
Project ID: | STP 2013(936)MM | CSJ: | 2343-01-036 |
Description: | CONSTRUCT ADDITIONAL LANES AND ACCESS MANAGEMENT | Handling Code: |
|
Limits From: | SH 286 | Fund Cat: | 3 |
Limits To: | OSO PARKWAY INTERSECTION | Estimate: | $23,976,832 |
Length: | 4.1 Miles | Actual: | $24,447,531 |
Back... |
Totals for 2343-01-036 | ||
Length: | 4.1 Miles | ||
Estimate: | $23,976,832 | ||
Actual: | $24,447,531 |
|