Detail Letting Schedule for Titus County (FY 2013)
Titus County (FY 2013) |
CCSJ: 0010-09-007 | |||
District: | Atlanta | Let Date: | AUG 2013 |
Highway: | SP 185 | Let Status: | Actual |
Project ID: | CRX 10-9-7 | CSJ: | 0010-09-007 |
Description: | RAILROAD REPLANKING | Handling Code: |
XX |
Limits From: | AT U.P.RAILROAD | Fund Cat: | 10 |
Limits To: | DOT.NO. 789159B | Estimate: | $25,600 |
Length: | 0.1 Miles | Actual: | $25,600 |
Back... |
Totals for 0010-09-007 | ||
---|---|---|---|
Length: | 0.1 Miles | ||
Estimate: | $25,600 | ||
Actual: | $25,600 | ||
CCSJ: 0083-09-030 | |||
District: | Atlanta | Let Date: | JUN 2013 |
Highway: | SH 11 | Let Status: | Actual |
Project ID: | C 83-9-30 | CSJ: | 0083-09-030 |
Description: | CONSTRUCT LEFT TURN LANE | Handling Code: |
|
Limits From: | AT FM 1735 INTERSECTION | Fund Cat: | 3 |
Limits To: | . | Estimate: | $202,693 |
Length: | 0.3 Miles | Actual: | $205,526 |
Back... |
Totals for 0083-09-030 | ||
Length: | 0.3 Miles | ||
Estimate: | $202,693 | ||
Actual: | $205,526 | ||
CCSJ: 1226-04-001 | |||
District: | Atlanta | Let Date: | FEB 2013 |
Highway: | FM 1000 | Let Status: | Actual |
Project ID: | PTF 2012(720) | CSJ: | 1226-04-001 |
Description: | CONSTRUCT 2 - LANE HIGHWAY ON NEW LOCATION FROM US 271 RELIEF | Handling Code: |
LC |
Limits From: | US 271 | Fund Cat: | 3 |
Limits To: | FM 1735 | Estimate: | $19,800,000 |
Length: | 5.0 Miles | Actual: | $18,846,843 |
Back... |
Totals for 1226-04-001 | ||
Length: | 5.0 Miles | ||
Estimate: | $19,800,000 | ||
Actual: | $18,846,843 |
|