Van Zandt County (FY 2013)

CCSJ: 0095-06-066

District: Tyler Let Date: NOV 2012
Highway: US 80 Let Status: Actual
Project ID: STP 2013(165) CSJ: 0095-06-066
Description: SEAL COAT & PAVEMENT MARKINGS Handling
Code:
 
Limits From: .4 MI W OF FM1504(EDGWD W CTY LIM)E Fund Cat: 1
Limits To: SH 19 Estimate: $775,903
Length: 3.6 Miles Actual: $723,287
 
District: Tyler Let Date: NOV 2012
Highway: US 287 Let Status: Actual
Project ID: STP 2013(165) CSJ: 0109-01-059
Description: SEAL COAT & PAVEMENT MARKINGS Handling
Code:
 
Limits From: SL 256 IN PALESTINE, S Fund Cat: 1
Limits To: FM 2419 Estimate: $163,235
Length: 2.3 Miles Actual: $148,951
 
District: Tyler Let Date: NOV 2012
Highway: SH 21 Let Status: Actual
Project ID: STP 2013(165) CSJ: 0118-05-020
Description: SEAL COAT & PAVEMENT MARKINGS Handling
Code:
 
Limits From: 0.65 MI E OF US 69 IN ALTO, E Fund Cat: 1
Limits To: NACOGDOCHES C/L Estimate: $220,518
Length: 6.3 Miles Actual: $199,859
 
District: Tyler Let Date: NOV 2012
Highway: US 259 Let Status: Actual
Project ID: NH 2013(166) CSJ: 0138-02-035
Description: SEAL COAT & PAVEMENT MARKINGS Handling
Code:
 
Limits From: BU 259 (S END OF BYPASS), S Fund Cat: 1
Limits To: FM 850 Estimate: $397,098
Length: 4.8 Miles Actual: $364,076
 
District: Tyler Let Date: NOV 2012
Highway: US 175 Let Status: Actual
Project ID: NH 2013(166) CSJ: 0197-06-052
Description: SEAL COAT & PAVEMENT MARKINGS, NO SHOULDERS Handling
Code:
 
Limits From: 0.2 MI SE OF BU 175 IN MABANK, SE Fund Cat: 1
Limits To: 0.8 MI NW OF FM 316 IN EUSTACE Estimate: $376,342
Length: 4.4 Miles Actual: $345,710
 
District: Tyler Let Date: NOV 2012
Highway: US 175 Let Status: Actual
Project ID: NH 2013(166) CSJ: 0197-06-053
Description: SEAL COAT & PAVEMENT MARKINGS, NO SHOULDERS, WBL ONLY Handling
Code:
 
Limits From: 1.7 MI SE OF FM 316 (END C & G), SE Fund Cat: 1
Limits To: 0.8 MI NW OF SL7/SH 31 IN ATHENS Estimate: $376,288
Length: 6.1 Miles Actual: $348,097
 
District: Tyler Let Date: NOV 2012
Highway: US 175 Let Status: Actual
Project ID: NH 2013(166) CSJ: 0198-01-027
Description: SEAL COAT & PAVEMENT MARKINGS Handling
Code:
 
Limits From: SH 19/SL 7 IN ATHENS, SE Fund Cat: 1
Limits To: 0.5 MI SE OF FM 804 (BGN 4 LN) Estimate: $508,522
Length: 4.8 Miles Actual: $472,537
 
District: Tyler Let Date: NOV 2012
Highway: BU 175G Let Status: Actual
Project ID: NH 2013(166) CSJ: 0198-01-028
Description: SEAL COAT & PAVEMENT MARKINGS Handling
Code:
 
Limits From: 1.6 MI SE OF BS19(ATHENS CTY LIM),S Fund Cat: 1
Limits To: US 175/SL 7 Estimate: $103,394
Length: 1.1 Miles Actual: $96,351
 
District: Tyler Let Date: NOV 2012
Highway: FM 1799 Let Status: Actual
Project ID: STP 2013(165) CSJ: 0203-10-021
Description: SEAL COAT & PAVEMENT MARKINGS Handling
Code:
 
Limits From: FM 779 AT GOLDEN, S Fund Cat: 1
Limits To: US 80 W OF MINEOLA Estimate: $99,080
Length: 3.7 Miles Actual: $90,456
 
District: Tyler Let Date: NOV 2012
Highway: FM 1799 Let Status: Actual
Project ID: STP 2013(165) CSJ: 0203-11-006
Description: SEAL COAT & PAVEMENT MARKINGS Handling
Code:
 
Limits From: US 69, S Fund Cat: 1
Limits To: FM 779 AT GOLDEN, S Estimate: $13,390
Length: 0.7 Miles Actual: $12,203
 
District: Tyler Let Date: NOV 2012
Highway: SH 64 Let Status: Actual
Project ID: STP 2013(165) CSJ: 0245-01-031
Description: SEAL COAT & PAVEMENT MARKINGS Handling
Code:
 
Limits From: US 80 IN WILLS POINT, SE Fund Cat: 1
Limits To: IH 20 Estimate: $426,078
Length: 8.5 Miles Actual: $388,245
 
District: Tyler Let Date: NOV 2012
Highway: SH 110 Let Status: Actual
Project ID: STP 2013(165) CSJ: 0345-01-058
Description: SEAL COAT & PAVEMENT MARKINGS Handling
Code:
 
Limits From: 2.1 MI S OF FM 2964(NR NEW SL 49),S Fund Cat: 1
Limits To: 0.1 MI N OF FM 346 IN WHITEHOUSE Estimate: $295,966
Length: 3.1 Miles Actual: $273,107
 
District: Tyler Let Date: NOV 2012
Highway: SH 110 Let Status: Actual
Project ID: STP 2013(165) CSJ: 0345-02-051
Description: SEAL COAT & PAVEMENT MARKINGS Handling
Code:
 
Limits From: 0.7 MI S OF FM 346 (HAGAN RD), S Fund Cat: 1
Limits To: 0.1 MI S OF FM 1089 (CHEROKEE C/L) Estimate: $469,655
Length: 8.7 Miles Actual: $435,172
 
District: Tyler Let Date: NOV 2012
Highway: SH 110 Let Status: Actual
Project ID: STP 2013(165) CSJ: 0345-03-021
Description: SEAL COAT & PAVEMENT MARKINGS Handling
Code:
 
Limits From: 0.1 MI S OF FM 1089 (SMITH C/L), S Fund Cat: 1
Limits To: US 79 IN NEW SUMMERFIELD Estimate: $408,354
Length: 10.9 Miles Actual: $371,556
 
District: Tyler Let Date: NOV 2012
Highway: SH 135 Let Status: Actual
Project ID: STP 2013(165) CSJ: 0378-01-028
Description: SEAL COAT & PAVEMENT MARKINGS Handling
Code:
 
Limits From: SH 42 IN NEW LONDON, SW Fund Cat: 1
Limits To: SMITH C/L IN OVERTON Estimate: $199,082
Length: 4.5 Miles Actual: $181,343
 
District: Tyler Let Date: NOV 2012
Highway: FM 347 Let Status: Actual
Project ID: STP 2013(165) CSJ: 0378-07-027
Description: SEAL COAT & PAVEMENT MARKINGS Handling
Code:
 
Limits From: SL 456 IN JACSONVILLE, S Fund Cat: 1
Limits To: US 84 Estimate: $337,697
Length: 9.1 Miles Actual: $305,435
 
District: Tyler Let Date: NOV 2012
Highway: SH 182 Let Status: Actual
Project ID: STP 2013(165) CSJ: 0429-01-021
Description: SEAL COAT & PAVEMENT MARKINGS Handling
Code:
 
Limits From: US 69 IN ALBA, E Fund Cat: 1
Limits To: SH 154 W OF QUITMAN Estimate: $298,441
Length: 9.9 Miles Actual: $274,039
 
District: Tyler Let Date: NOV 2012
Highway: LP 256 Let Status: Actual
Project ID: STP 2013(165) CSJ: 0520-09-040
Description: SEAL COAT & PAVEMENT MARKINGS Handling
Code:
 
Limits From: US 84(E) IN PALESTINE, S & W Fund Cat: 1
Limits To: US 79(S) Estimate: $464,142
Length: 4.5 Miles Actual: $425,731
 
District: Tyler Let Date: NOV 2012
Highway: FM 16 Let Status: Actual
Project ID: STP 2013(165) CSJ: 0522-03-023
Description: SEAL COAT & PAVEMENT MARKINGS Handling
Code:
 
Limits From: FM 773, E. Fund Cat: 1
Limits To: FM 314 IN VAN Estimate: $133,750
Length: 3.5 Miles Actual: $122,087
 
District: Tyler Let Date: NOV 2012
Highway: FM 47 Let Status: Actual
Project ID: STP 2013(165) CSJ: 0646-01-030
Description: SEAL COAT & PAVEMENT MARKINGS Handling
Code:
 
Limits From: FM 2475, S Fund Cat: 1
Limits To: US 80 IN WILLS POINT Estimate: $240,843
Length: 5.7 Miles Actual: $218,186
 
District: Tyler Let Date: NOV 2012
Highway: FM 320 Let Status: Actual
Project ID: STP 2013(165) CSJ: 0891-01-013
Description: SEAL COAT & PAVEMENT MARKINGS Handling
Code:
 
Limits From: FM 645 AT JOHNSON, E Fund Cat: 1
Limits To: US 79 IN PALESTINE Estimate: $227,867
Length: 8.1 Miles Actual: $208,735
 
District: Tyler Let Date: NOV 2012
Highway: FM 782 Let Status: Actual
Project ID: STP 2013(165) CSJ: 1116-01-021
Description: SEAL COAT & PAVEMENT MARKINGS Handling
Code:
 
Limits From: FM 1716 AT OAK HILL, NE Fund Cat: 1
Limits To: SH 149 NEAR EASTON Estimate: $297,249
Length: 9.5 Miles Actual: $271,733
 
District: Tyler Let Date: NOV 2012
Highway: FM 848 Let Status: Actual
Project ID: STP 2013(165) CSJ: 1151-01-012
Description: SEAL COAT & PAVEMENT MARKINGS Handling
Code:
 
Limits From: SH 64 AT BASCOM, S Fund Cat: 1
Limits To: FM 346 IN WHITEHOUSE Estimate: $285,250
Length: 7.5 Miles Actual: $260,078
 
District: Tyler Let Date: NOV 2012
Highway: FM 859 Let Status: Actual
Project ID: STP 2013(165) CSJ: 1171-02-015
Description: SEAL COAT & PAVEMENT MARKINGS Handling
Code:
 
Limits From: IH 20, S Fund Cat: 1
Limits To: SH 64 IN CANTON Estimate: $60,981
Length: 1.7 Miles Actual: $55,063
 
District: Tyler Let Date: NOV 2012
Highway: FM 858 Let Status: Actual
Project ID: STP 2013(165) CSJ: 1172-03-007
Description: SEAL COAT & PAVEMENT MARKINGS Handling
Code:
 
Limits From: SH 64 IN BEN WHEELER, E Fund Cat: 1
Limits To: FM 314 Estimate: $149,631
Length: 4.8 Miles Actual: $136,961
 
District: Tyler Let Date: NOV 2012
Highway: FM 3053 Let Status: Actual
Project ID: STP 2013(165) CSJ: 1608-02-013
Description: SEAL COAT & PAVEMENT MARKINGS Handling
Code:
 
Limits From: RABBIT CREEK, S Fund Cat: 1
Limits To: FM 850 IN OVERTON Estimate: $134,338
Length: 3.6 Miles Actual: $121,878
 
District: Tyler Let Date: NOV 2012
Highway: FM 837 Let Status: Actual
Project ID: STP 2013(165) CSJ: 1666-02-008
Description: SEAL COAT & PAVEMENT MARKINGS Handling
Code:
 
Limits From: SH 19 AT BRADFORD, E Fund Cat: 1
Limits To: FM 315 AT BRUSHY CREEK Estimate: $367,441
Length: 11.4 Miles Actual: $333,193
 
District: Tyler Let Date: NOV 2012
Highway: FM 1804 Let Status: Actual
Project ID: STP 2013(165) CSJ: 1791-01-008
Description: SEAL COAT & PAVEMENT MARKINGS Handling
Code:
 
Limits From: WOOD C/L AT SABINE RIVER, S Fund Cat: 1
Limits To: US 69 IN LINDALE Estimate: $137,130
Length: 5.0 Miles Actual: $125,506
 
District: Tyler Let Date: NOV 2012
Highway: FM 1804 Let Status: Actual
Project ID: STP 2013(165) CSJ: 1791-02-005
Description: SEAL COAT & PAVEMENT MARKINGS Handling
Code:
 
Limits From: FM 2422, S Fund Cat: 1
Limits To: SMITH C/L AT SABINE RIVER Estimate: $65,721
Length: 2.0 Miles Actual: $60,031
 
District: Tyler Let Date: NOV 2012
Highway: FM 2138 Let Status: Actual
Project ID: STP 2013(165) CSJ: 2065-01-011
Description: SEAL COAT & PAVEMENT MARKINGS Handling
Code:
 
Limits From: US 79 IN JACKSONVILLE, S Fund Cat: 1
Limits To: US 84 Estimate: $386,266
Length: 10.7 Miles Actual: $350,486
 
District: Tyler Let Date: NOV 2012
Highway: FM 1804 Let Status: Actual
Project ID: STP 2013(165) CSJ: 2274-01-009
Description: SEAL COAT & PAVEMENT MARKINGS Handling
Code:
 
Limits From: US 80 AT HOARD, S Fund Cat: 1
Limits To: FM 2422 Estimate: $23,969
Length: 0.8 Miles Actual: $22,489
 
District: Tyler Let Date: NOV 2012
Highway: FM 2966 Let Status: Actual
Project ID: STP 2013(165) CSJ: 2409-01-010
Description: SEAL COAT & PAVEMENT MARKINGS Handling
Code:
 
Limits From: SH 154 IN YANTIS, E & S Fund Cat: 1
Limits To: FM 515 Estimate: $215,126
Length: 7.3 Miles Actual: $195,764
 
District: Tyler Let Date: NOV 2012
Highway: FM 2661 Let Status: Actual
Project ID: STP 2013(165) CSJ: 2654-01-020
Description: SEAL COAT & PAVEMENT MARKINGS Handling
Code:
 
Limits From: SH 64, S Fund Cat: 1
Limits To: 3.5 MI N OF SH 155(BIG EDDY/CR1261) Estimate: $370,709
Length: 9.5 Miles Actual: $336,743
 
District: Tyler Let Date: NOV 2012
Highway: FM 2966 Let Status: Actual
Project ID: STP 2013(165) CSJ: 3023-01-007
Description: SEAL COAT & PAVEMENT MARKINGS Handling
Code:
 
Limits From: FM 515, S Fund Cat: 1
Limits To: SL 173 IN QUITMAN Estimate: $263,314
Length: 8.9 Miles Actual: $240,753
 
Back...

Totals for 0095-06-066
Length: 197.0 Miles
Estimate: $9,292,770
Actual: $8,515,841


Handling Code Definition
XX Project not processed through statewide letting
TR Transfer of funds
LC Project let through local entity
NC Project not charged against district apportionment



Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract