Detail Letting Schedule for Bastrop County (FY 2014)
Bastrop County (FY 2014) |
CCSJ: 0114-06-030 | |||
District: | Austin | Let Date: | NOV 2013 |
Highway: | US 290 | Let Status: | Actual |
Project ID: | C 114-6-30 | CSJ: | 0114-06-030 |
Description: | WIDEN TO 4 LANE DIVIDED | Handling Code: |
|
Limits From: | 8.864 MI E OF FM 696 | Fund Cat: | 3 |
Limits To: | FM 2104 | Estimate: | $22,245,545 |
Length: | 5.6 Miles | Actual: | $19,049,777 |
Back... |
Totals for 0114-06-030 | ||
---|---|---|---|
Length: | 5.6 Miles | ||
Estimate: | $22,245,545 | ||
Actual: | $19,049,777 | ||
CCSJ: 0573-01-031 | |||
District: | Austin | Let Date: | JUN 2014 |
Highway: | FM 86 | Let Status: | Actual |
Project ID: | STP 2014(722)HRR | CSJ: | 0571-02-034 |
Description: | IMPROVE GUARDRAIL TO DESIGN STANDARDS & SAFETY TREAT FIXED | Handling Code: |
|
Limits From: | FM 713 | Fund Cat: | 8 |
Limits To: | FM 1322 | Estimate: | $234,310 |
Length: | 7.5 Miles | Actual: | $354,297 |
District: | Austin | Let Date: | JUN 2014 |
Highway: | SH 304 | Let Status: | Actual |
Project ID: | STP 2014(721)HES | CSJ: | 0573-01-031 |
Description: | IMPROVE GUARDRAIL TO DESIGN STANDARDS & SAFETY TREAT FIXED | Handling Code: |
|
Limits From: | FM 2571 | Fund Cat: | 8 |
Limits To: | CALDWELL COUNTY LINE | Estimate: | $651,087 |
Length: | 14.7 Miles | Actual: | $805,833 |
Back... |
Totals for 0573-01-031 | ||
Length: | 22.2 Miles | ||
Estimate: | $885,397 | ||
Actual: | $1,160,130 | ||
CCSJ: 0807-01-027 | |||
District: | Austin | Let Date: | SEP 2013 |
Highway: | FM 535 | Let Status: | Actual |
Project ID: | STP 2014(014)HES | CSJ: | 0807-01-027 |
Description: | PROVIDE ADDITIONAL PAVED SURFACE WIDTH | Handling Code: |
|
Limits From: | FM 20 | Fund Cat: | 8 |
Limits To: | MAIN ST | Estimate: | $3,955,868 |
Length: | 10.5 Miles | Actual: | $3,806,544 |
Back... |
Totals for 0807-01-027 | ||
Length: | 10.5 Miles | ||
Estimate: | $3,955,868 | ||
Actual: | $3,806,544 | ||
CCSJ: 0914-18-094 | |||
District: | Austin | Let Date: | DEC 2013 |
Highway: | VA | Let Status: | Actual |
Project ID: | STP 2013(305)MM | CSJ: | 0914-18-094 |
Description: | DOWNTOWN TRANSIT STOP & BIKE / PED CONNS | Handling Code: |
LC |
Limits From: | VARIOUS LOCATIONS IN ELGIN AREA | Fund Cat: | 3 |
Limits To: | TRANSIT CONNECTS IN ELGIN REGION | Estimate: | $2,393,241 |
Length: | 0.1 Miles | Actual: | $2,020,306 |
Back... |
Totals for 0914-18-094 | ||
Length: | 0.1 Miles | ||
Estimate: | $2,393,241 | ||
Actual: | $2,020,306 | ||
CCSJ: 0914-18-095 | |||
District: | Austin | Let Date: | AUG 2014 |
Highway: | VA | Let Status: | Actual |
Project ID: | STP 1402(242)MM | CSJ: | 0914-18-095 |
Description: | UPDATE BASTROP THOROUGHFARE & TRANSPORTATION PLAN | Handling Code: |
XX |
Limits From: | VARIOUS IN BASTROP AREA | Fund Cat: | 3 |
Limits To: | UPDATE TO CITY'S TRANSP. PLAN | Estimate: | $200,000 |
Length: | 0.1 Miles | Actual: | $201,000 |
Back... |
Totals for 0914-18-095 | ||
Length: | 0.1 Miles | ||
Estimate: | $200,000 | ||
Actual: | $201,000 | ||
CCSJ: 0914-18-096 | |||
District: | Austin | Let Date: | AUG 2014 |
Highway: | VA | Let Status: | Actual |
Project ID: | STP 1402(224)MM | CSJ: | 0914-18-096 |
Description: | BASTROP COUNTY COMPREHENSIVE TRANSPORTATION PLAN, PHASE II | Handling Code: |
XX |
Limits From: | VARIOUS LOCATIONS IN BASTROP COUNTY | Fund Cat: | 3 |
Limits To: | DEVELOP PH 2 TRANSPORTATION PLAN | Estimate: | $650,991 |
Length: | 0.1 Miles | Actual: | $651,991 |
Back... |
Totals for 0914-18-096 | ||
Length: | 0.1 Miles | ||
Estimate: | $650,991 | ||
Actual: | $651,991 |
|