Detail Letting Schedule for Hemphill County (FY 2014)

Last Update: Monday, November 17, 2014
Hemphill County (FY 2014)

CCSJ: 0030-06-054

District: Amarillo Let Date: DEC 2013
Highway: US 83 Let Status: Actual
Project ID: STP 2014(267) CSJ: 0030-06-054
Description: REHAB EXISTING ROADWAY Handling
Code:
 
Limits From: US 60 Fund Cat: 1
Limits To: FM 277 Estimate: $3,084,638
Length: 7.7 Miles Actual: $3,013,001
 
District: Amarillo Let Date: DEC 2013
Highway: US 83 Let Status: Actual
Project ID: STP 2014(267) CSJ: 0030-07-018
Description: REHAB EXISTING ROADWAY Handling
Code:
 
Limits From: FM 277 Fund Cat: 1
Limits To: 1.66 MILES SOUTH OF FM 277 Estimate: $491,480
Length: 1.7 Miles Actual: $503,833
 
Back...

Totals for 0030-06-054
Length: 9.4 Miles
Estimate: $3,576,118
Actual: $3,516,834


Handling Code Definition
XX Project not processed through statewide letting
TR Transfer of funds
LC Project let through local entity
NC Project not charged against district apportionment



Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract