Letting Schedule for Bryan District (FY 2014)
Bryan District (FY 2014) |
Brazos | Burleson | Freestone | Grimes | Leon | Madison | Milam | Walker | Washington | ||||||
Brazos County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
---|---|---|---|---|---|---|
0049-12-091 | SH 6 | Actual | FEB 2014 | $1,420,898 | 1 | OVERLAY CONSISTING OF MILLING, AN HMA OVERLAY AND PAVEMENT |
0315-05-026 | SH 105 | Actual | MAY 2014 | $23,601,410 | 11 | REPLACE EXISTING BRIDGE FACILITY CONSISTING OF GRADING, |
0917-00-040 | VA | Actual | JUL 2014 | $3,503,761 | 10 | MISCELLANEOUS CONSTRUCTION CONSISTING OF THE CONSTRUCTION OF |
Burleson County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0116-02-041 | SH 21 | Actual | APR 2014 | $5,811,634 | 1 | OVERLAY CONSISTING OF AN HMA LEVEL - UP, OVERLAY AND PAVEMENT |
0457-01-056 | FM 50 | Actual | JAN 2014 | $1,532,334 | 1 | REHABILITATE EXISTING ROAD CONSISTING OF GRADING, STRUCTURES |
0648-03-050 | FM 60 | Actual | DEC 2013 | $10,487,721 | 3 | NEW LOCATION NON - FREEWAY FACILITY CONSISTING OF GRADING, |
0648-03-065 | FM 60 | Actual | AUG 2014 | $27,670 | 10 | RAILROAD GRADE CROSSING REPLANKING, 2014 REPLANKING PROGRAM |
Freestone County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0456-01-046 | FM 27 | Actual | AUG 2014 | $30,080 | 10 | RAILROAD GRADE CROSSING REPLANKING, 2014 REPLANKING PROGRAM |
0675-02-077 | IH 45 | Actual | SEP 2013 | $4,687,022 | 1 | OVERLAY CONSISTING OF AN HMA OVERLAY |
0917-20-011 | CR | Actual | OCT 2013 | $448,407 | 6 | REPLACE BRIDGE AND APPROACHES |
0998-05-009 | FM 416 | Actual | MAY 2014 | $1,235,168 | 8 | SAFETY WORK CONSISTING OF SUBGRADE WIDENING, FLEXIBLE BASE, |
Grimes County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0050-03-090 | SH 6 | Actual | SEP 2013 | $4,575,221 | 3 | UPGRADING OF A FREEWAY FACILITY CONSISTING OF GRADING, |
0212-04-033 | SH 30 | Actual | JUL 2014 | $5,718,784 | 1 | SAFETY IMPROVEMENT WORK CONSISTING OF GRADING, STRUCTURES, |
0315-02-045 | SH 90 | Actual | AUG 2014 | $4,087,491 | 1 | REHABILITATE EXISTING ROAD CONSISTING OF SUBGRADE WIDENING, |
0315-02-049 | SH 90 | Actual | AUG 2014 | $3,129,293 | 1 | REHABILITATE EXISTING ROAD CONSISTING OF SUBGRADE WIDENING, |
0643-04-028 | FM 244 | Actual | AUG 2014 | $2,156,939 | 1 | SCARIFY BASE, CEMENT TREAT BASE AND SEAL SURFACE |
0917-17-043 | CR | Actual | MAR 2014 | $662,558 | 6 | REPLACEMENT OF AN EXISTING BRIDGE FACILITY CONSISTING OF |
Leon County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0335-04-009 | SL 208 | Actual | AUG 2014 | $72,192 | 10 | RAILROAD GRADE CROSSING REPLANKING, 2014 REPLANKING PROGRAM |
0426-03-039 | FM 542 | Actual | MAY 2014 | $1,887,338 | 8 | SAFETY WORK CONSISTING OF SUBGRADE WIDENING, FLEXIBLE BASE, |
Madison County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0117-04-038 | US 190 | Actual | AUG 2014 | $4,647,859 | 1 | REHABILITATE EXISTING ROAD CONSISTING OF PLANING, PAVEMENT |
0675-05-076 | IH 45 | Actual | NOV 2013 | $2,387,523 | 1 | OVERLAY CONSISTING OF MILL AND INLAY |
Milam County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0185-06-009 | FM 845 | Actual | AUG 2014 | $22,144 | 10 | RAILROAD GRADE CROSSING REPLANKING, 2014 REPLANKING PROGRAM |
2133-03-019 | FM 2269 | Actual | OCT 2013 | $3,309,495 | 8 | SAFETY WORK CONSISTING OF SUBGRADE WIDENING, FLEXIBLE BASE, |
Walker County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0110-01-037 | SH 75 | Actual | SEP 2013 | $6,858,560 | 1 | SEAL COAT CONSISTING OF A ONE COURSE SURFACE TREATMENT |
0675-06-099 | IH 45 | Actual | OCT 2013 | $5,387,237 | 1 | OVERLAY CONSISTING OF MILLING, HMA LEVEL - UP, SMA OVERLAY AND |
0675-07-089 | IH 45 | Actual | MAR 2014 | $3,355,021 | 8 | SAFETY WORK CONSISTING OF GRADING, STRUCTURES, FLEXIBLE BASE |
0917-27-043 | PW | Actual | APR 2014 | $262,457 | 10 | MISCELLANEOUS WORK CONSISTING OF THE RECONSTRUCTION OF |
1402-01-032 | FM 1375 | Actual | JUN 2014 | $2,371,297 | 8 | SAFETY WORK CONSISTING OF SUBGRADE WIDENING, FLEXIBLE BASE, |
1706-01-025 | FM 1791 | Actual | JUL 2014 | $3,187,516 | 8 | SAFETY WORK CONSISTING OF SUBGRADE WIDENING, FLEXIBLE BASE, |
1809-02-024 | FM 1696 | Actual | NOV 2013 | $4,305,080 | 8 | SAFETY WORK CONSISTING OF SUBGRADE WIDENING, FLEXIBLE BASE, |
Washington County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0186-06-078 | US 290 | Actual | JAN 2014 | $1,024,094 | 1 | OVERLAY CONSISTING OF MILL, OCST, PFC OVERLAY & PAVEMENT |
|