Letting Schedule for San Antonio District (FY 2014)
| San Antonio District (FY 2014) |
| Atascosa | Bexar | Comal | Frio | Guadalupe | Kendall | Kerr | Medina | Uvalde | ||||||
Atascosa County | ||||||
| CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
|---|---|---|---|---|---|---|
| 0915-13-025 | CR | Tentative | SEP 2013 | $150,000 | 8 | INSTALL RAILROAD WARNING SIGNS AND PAVEMENT MARKINGS TO |
Bexar County | ||||||
| CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
| 0017-10-253 | IH 35 | Tentative | SEP 2013 | $11,800,000 | 1 | SEGMENTAL STRUCTURES - DRAINAGE REPAIR, POST TENSIONING DUCT |
| 0521-05-139 | IH 410 | Tentative | DEC 2013 | $4,500,000 | 1 | SEAL COAT, OVERLAY AND PAVEMENT MARKINGS |
| 0849-01-046 | FM 471 | Tentative | JAN 2014 | $15,500,000 | 3 | EXPAND 2 TO 4 LANE DIVIDED WITH BIKE LANES |
| 0915-00-155 | VA | Tentative | APR 2014 | $1,500,000 | 1 | DISTRICTWIDE GUIDESIGNS FY14 |
| 0915-00-156 | VA | Tentative | FEB 2014 | $2,000,000 | 1 | DISTRICTWIDE NON - SITE SPECIFIC TRAFFIC SIGNALS - FY 2014 |
| 0915-12-218 | CS | Tentative | JAN 2014 | $1,500,000 | 6 | REPLACE BRIDGE & APPROACHES |
| 0915-12-254 | CS | Tentative | JUL 2014 | $726,000 | 7 | EXPAND 2 TO 4 LANES WITH CURBS AND SIDEWALK |
| 0915-12-459 | CS | Tentative | JUL 2014 | $9,367,263 | 7 | EXPAND 2 LANES TO 4 LANES WITH LEFT TURN LANES, BIKE LANES & |
| 0915-12-493 | VA | Tentative | AUG 2014 | $267,000 | 7 | ALAMO AREA COMMUTE SOLUTION PGM - FY 2014 |
| 0915-12-496 | VA | Tentative | APR 2014 | $5,900,000 | 3 | EXTEND 36TH ST ALONG EXISTING WAGNER / TINKER RD - EXPAND TO |
| 0915-12-509 | CR | Tentative | APR 2014 | $8,097,480 | 7 | RECONSTRUCT AND WIDEN TO 4 LANES WITH SHOULDER, PEDESTRIAN |
| 0915-12-511 | CS | Tentative | JAN 2014 | $4,595,400 | 7 | RECONSTRUCT ROADWAY AND REPLACE EXISTING SIDEWALKS, CURBS |
| 0915-12-514 | CS | Tentative | JAN 2014 | $933,000 | 7 | CONSTRUCTION OF A HIKE AND BIKE TRAIL ALONG HUEBNER CREEK |
| 0915-12-516 | CS | Tentative | JUL 2014 | $8,538,766 | 7 | WIDEN ROADWAY TO 4 LANES WITH LEFT TURN LANES AND SIDEWALKS |
| 0915-12-521 | VA | Tentative | MAY 2014 | $2,000,000 | 10 | CONSTRUCT CURB RAMPS FOR ADA COMPLIANCE |
| 2104-02-027 | FM 1957 | Tentative | OCT 2013 | $37,500,000 | 3 | EXPAND FROM 2 LANES TO 4 LANE DIVIDED |
| 2104-02-030 | FM 1957 | Tentative | OCT 2013 | $184,854 | 3 | RELOCATE FENCING AND CLEAR ROW |
| 2230-02-004 | SP 53 | Tentative | MAY 2014 | $8,300,000 | 7 | EXPAND 2 LANES TO 4 LANES WITH LEFT TURN LANES, BIKE LANES |
| 2230-02-006 | SP 53 | Tentative | MAY 2014 | ROW | ACQUISITION | |
| 2452-01-055 | LP 1604 | Tentative | NOV 2013 | $66,070,421 | 3 | EXPAND TO 4 LANE EXPRESSWAY (4 NON - TOLL LANES) |
| 2452-03-108 | LP 1604 | Tentative | OCT 2013 | $23,520,000 | 3 | EXPAND 2 LANES TO 4 LANE DIVIDED |
| 3544-04-002 | SH 211 | Tentative | APR 2014 | $18,100,002 | 3 | CONSTRUCT TWO LANE RURAL HIGHWAY ON NEW LOCATION |
Comal County | ||||||
| CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
| 0016-04-104 | IH 35 | Tentative | MAY 2014 | $2,500,000 | 1 | RECONSTRUCT ENTRANCE AND EXIT RAMPS |
| 0016-05-106 | IH 35 | Tentative | SEP 2013 | $8,523,249 | 1 | SEAL COAT, PFC OVERLAY & PAVEMENT MARKINGS |
| 0016-05-107 | IH 35 | Tentative | DEC 2013 | $1,300,000 | 1 | RECONFIGURE INTERSECTION |
| 1272-01-016 | FM 1101 | Tentative | FEB 2014 | $5,044,968 | 1 | WIDEN EXISTING ROADWAY TO PROVIDE A CONTINUOUS LEFT TURN |
Frio County | ||||||
| CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
| 0017-07-130 | IH 35 | Tentative | OCT 2013 | $3,065,605 | 1 | RECONSTRUCT & RECONFIGURE RAMPS AND FRONTAGE ROAD |
| 0748-01-029 | FM 140 | Tentative | SEP 2013 | $1,453,227 | 1 | WIDENING OF NARROW ROADWAY AND SHOULDERS |
| 0915-18-028 | CR | Tentative | JAN 2014 | $500,000 | 6 | REPLACE BRIDGE AND APPROACHES |
Guadalupe County | ||||||
| CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
| 0366-12-026 | BS 123B | Tentative | JUL 2014 | $3,760,000 | 1 | CONSTRUCT CLTL, BIKE LANES, SIDEWALK & DRAINAGE IMPROVEMENTS |
| 0366-12-027 | BS 123B | Tentative | JAN 2014 | ROW | ACQUISITION AND UTILITIES | |
| 0915-46-039 | VA | Tentative | DEC 2013 | $1,791,466 | 3 | SEGUIN WALNUT BRANCH LINEAR PARK HIKE AND BIKE TRAIL |
Kendall County | ||||||
| CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
| 0142-09-041 | RM 473 | Tentative | NOV 2013 | $5,792,000 | 1 | SEAL COAT & PAVEMENT MARKINGS |
| 0215-06-031 | SH 46 | Tentative | MAY 2014 | $1,500,000 | 1 | INTERSECTION IMPROVEMENTS |
Kerr County | ||||||
| CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
| 0291-03-057 | SH 16 | Tentative | SEP 2013 | $2,125,595 | 1 | WIDEN ROADWAY TO PROVIDE CONTINUOUS LEFT TURN LANE |
Medina County | ||||||
| CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
| 0017-05-093 | IH 35 | Tentative | DEC 2013 | $500,000 | 1 | WIDEN EXISTING FRONTAGE ROADS TO PROVIDE SHOULDERS |
| 0024-05-095 | US 90 | Tentative | DEC 2013 | $1,070,492 | 1 | OVERLAY & PAVEMENT MARKINGS |
| 0848-01-037 | FM 462 | Tentative | SEP 2013 | $2,645,755 | 1 | REHAB & WIDEN NARROW ROADWAY TO ADD SHOULDERS |
Uvalde County | ||||||
| CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
| 0369-01-033 | SH 127 | Tentative | JUN 2014 | $3,500,000 | 6 | REPLACE BRIDGE AND APPROACHES |
| 0915-20-015 | PW | Tentative | JAN 2014 | $890,291 | 10 | REPAIR & RESURFACE EXISITNG PAVED PARK ROADS, PARKING LOTS, |
| 0915-20-016 | CR | Tentative | SEP 2013 | $150,000 | 8 | INSTALL RAILROAD WARNING SIGNS AND PAVEMENT MARKINGS TO |
|