0052-03-029 | Bailey/ Lubbock |
US 84 | Actual | $15,399,876 | 11 | REHABILITATION OF EXISTING ROAD |
0807-01-027 | Bastrop/ Austin |
FM 535 | Actual | $3,806,544 | 8 | PROVIDE ADDITIONAL PAVED SURFACE WIDTH |
0015-07-081 | Bell/ Waco |
IH 35 | Actual | $168,925 | 1 | LEVELUP AND PROVIDE PFC OVERLAY |
0017-10-253 | Bexar/ San Antonio |
IH 35 | Actual | $10,703,165 | 1 | SEGMENTAL STRUCTURES - DRAINAGE REPAIR, POST TENSIONING DUCT |
0915-00-171 | Bexar/ San Antonio |
VA | Actual | $3,000,000 | 1 | DISTRICTWIDE ITS OPERATION AND MAINTENANCE FY 2014 |
0179-05-002 | Brazoria/ Houston |
SH 35 | Actual | $3,985,333 | 1 | SEAL COAT, ASPHALT CONCRETE PAVEMENT OVERLAY AND PAVEMENT |
0331-01-040 | Cameron/ Pharr |
SH 100 | Actual | $2,737,444 | 1 | SEAL COAT |
2419-01-010 | Castro/ Lubbock |
FM 145 | Actual | $1,987,950 | 11 | REHABILITATION OF EXISTING ROAD |
1016-02-017 | Collin/ Dallas |
FM 1138 | Actual | $3,337,173 | 8 | PROVIDE ADDITIONAL PAVED SURFACE WIDTH |
0016-05-106 | Comal/ San Antonio |
IH 35 | Actual | $5,848,000 | 1 | SEAL COAT, PFC OVERLAY & PAVEMENT MARKINGS |
2459-01-021 | Cooke/ Wichita Falls |
FM 902 | Actual | $2,939,410 | 8 | PROVIDE ADDITIONAL PAVED SURFACE WIDTH |
0867-03-026 | Coryell/ Waco |
FM 183 | Actual | $4,552,211 | 1 | PROVIDE ADDITIONAL PAVED SURFACE WIDTH |
2374-03-076 | Dallas/ Dallas |
IH 20 | Actual | $1,858,920 | 1 | INSTALLATION OF FULL ITS SYSTEM |
1315-02-009 | Denton/ Dallas |
FM 423 | Actual | $29,826,070 | 3 | WIDEN 2 LANE RURAL UNDIVIDED TO 6 LANE DIVIDED URBAN |
0908-23-030 | Fisher/ Abilene |
CR | Actual | $714,924 | 6 | REPLACE BRIDGE |
0675-02-077 | Freestone/ Bryan |
IH 45 | Actual | $4,687,022 | 1 | OVERLAY CONSISTING OF AN HMA OVERLAY |
0017-07-132 | Frio/ San Antonio |
IH 35 | Actual | $593,552 | 1 | INSTALL TRAFFIC SIGNAL |
0748-01-029 | Frio/ San Antonio |
FM 140 | Actual | $1,394,946 | 1 | WIDENING OF NARROW ROADWAY AND SHOULDERS |
0978-02-071 | Galveston/ Houston |
FM 517 | Actual | $959,633 | 8 | IMPROVE TRAFFIC SIGNAL AND ADD LEFT TURN LANE |
0047-18-068 | Grayson/ Paris |
US 75 | Actual | $5,248,891 | 11 | WIDEN EXISTING BRIDGE OVERPASS |
0050-03-090 | Grimes/ Bryan |
SH 6 | Actual | $4,575,221 | 3 | UPGRADING OF A FREEWAY FACILITY CONSISTING OF GRADING, |
0251-01-056 | Hamilton/ Waco |
US 281 | Actual | $10,087,611 | 1 | ADD PASSING LANES |
0251-02-047 | Hamilton/ Waco |
US 281 | Actual | $9,687,837 | 1 | REHAB ROADWAY AND ADD PASSING LANES |
0508-01-276 | Harris/ Houston |
IH 10 | Actual | $34,623,242 | 3 | REPLACE BRIDGE AND APPROACHES |
0495-09-049 | Harrison/ Atlanta |
IH 20 | Actual | $7,961,243 | 1 | RESURFACE EXISTING INTERSTATE FACILITY |
0919-03-049 | Harrison/ Atlanta |
CR | Actual | $375,523 | 6 | REPLACE BRIDGE AND APPROACHES |
0458-01-022 | Henderson/ Tyler |
FM 59 | Actual | $6,987,662 | 1 | PROVIDE ADDITIONAL PAVED SURFACE WIDTH |
0621-01-099 | Hidalgo/ Pharr |
SH 336 | Actual | $80,950 | 3 | CORRIDOR SIGNAL RE - TIMING |
2094-01-051 | Hidalgo/ Pharr |
FM 2220 | Actual | $50,150 | 3 | COORIDOR SIGNAL RE - TIMING |
0109-03-032 | Houston/ Lufkin |
US 287 | Actual | $1,142,739 | 8 | TEXTURIZE SHOULDERS (ROLLED IN OR MILLED IN) |
0002-06-051 | Hudspeth/ El Paso |
IH 10 | Actual | $4,277,160 | 1 | INSTALL MEDIAN BARRIER |
1497-01-012 | Hunt/ Paris |
FM 1568 | Actual | $1,749,177 | 1 | REHABILITATION OF EXISTING ROAD |
0259-05-070 | Johnson/ Fort Worth |
US 67 | Actual | $2,820,911 | 1 | RESURFACE ROADWAY |
0259-06-001 | Johnson/ Fort Worth |
US 67 | Actual | $28,488,426 | 1 | WIDEN TO 4 LANE DIVIDED |
2213-01-013 | Johnson/ Fort Worth |
FM 2331 | Actual | $4,289,115 | 8 | GRADING, BASE AND PAVEMENT |
0327-02-051 | Kenedy/ Pharr |
US 77 | Actual | $8,073,400 | 1 | MILL & OVERLAY N.B. & S.B. ROADWAYS |
2329-02-015 | Kent/ Abilene |
FM 1081 | Actual | $5,496,256 | 1 | WIDENING AND REHAB |
0291-03-057 | Kerr/ San Antonio |
SH 16 | Actual | $2,504,539 | 1 | WIDEN ROADWAY TO PROVIDE CONTINUOUS LEFT TURN LANE |
0270-09-027 | Live Oak/ Corpus Christi |
SH 72 | Actual | $16,894,488 | 1 | CONSTRUCT PASSING LANES |
0700-04-045 | Llano/ Austin |
SH 71 | Actual | $4,402,628 | 1 | UPGRADE TO SUPER 2 & ADD LTL'S |
0130-05-077 | Lubbock/ Lubbock |
SH 114 | Actual | $997,062 | 1 | RESTORATION OF EXISTING ROAD |
0919-22-019 | Marion/ Atlanta |
CR | Actual | $304,787 | 6 | REPLACE BRIDGE AND APPROACHES |
0848-01-037 | Medina/ San Antonio |
FM 462 | Actual | $4,927,895 | 1 | REHAB & WIDEN NARROW ROADWAY TO ADD SHOULDERS |
0176-05-173 | Polk/ Lufkin |
US 59 | Actual | $738,985 | 8 | IMPROVE GUARDRAIL TO DESIGN STANDARDS |
0177-01-099 | Polk/ Lufkin |
US 59 | Actual | $1,577,675 | 1 | REMOVE CROSSOVERS AND CONSTRUCT TURN - AROUNDS WITH |
0904-00-152 | Potter/ Amarillo |
VA | Actual | $286,787 | 1 | CRACK SEAL |
0534-01-019 | Randall/ Amarillo |
PR 5 | Actual | $3,956,849 | 10 | REPLACE CONCRETE WATER CROSSINGS |
0772-01-027 | Red River/ Paris |
FM 410 | Actual | $2,516,693 | 1 | REHAB EXIST ROAD |
0424-01-045 | Smith/ Tyler |
SH 31 | Actual | $3,431,987 | 1 | WIDEN 2 LN ROADWAY TO SUPER - 2 (3 LANE) CRITERIA |
0910-00-093 | Smith/ Tyler |
VA | Actual | $98,697 | 1 | DISTRICT - WIDE THERMO PLASTIC PAVEMENT MARKINGS PROGRAM |
0039-01-079 | Starr/ Pharr |
US 83 | Actual | $8,089,840 | 1 | OVERLAY (ML BOTH DIRECTIONS) |
0034-01-124 | Taylor/ Abilene |
US 83 | Actual | $4,055,813 | 3 | RELOCATE RAMPS AND RECONSTRUCT FRONTAGE ROADS |
2398-01-047 | Taylor/ Abilene |
LP 322 | Actual | $4,222,065 | 3 | RELOCATE RAMPS AND RECONSTRUCT FRONTAGE ROADS |
0248-01-070 | Titus/ Atlanta |
US 271 | Actual | $779,081 | 1 | RESTORE SECTION & RESURFACE EXISTING 4 - LANE HIGHWAY |
0914-00-320 | Travis/ Austin |
VA | Actual | $452,779 | 1 | FY 2013 SIGNING |
3621-01-009 | Val Verde/ Laredo |
SL 79 | Actual | $5,720,530 | 4 | FOR THE CONSTRUCTION OF A 2 LANE UNDIVIDED HIGHWAY |
0842-02-021 | Victoria/ Yoakum |
FM 447 | Actual | $2,015,295 | 1 | REPAIR & WIDEN ROADWAY |
2350-01-053 | Victoria/ Yoakum |
US 77 | Actual | $1,585,484 | 1 | CONSTRUCT TURN LANE |
0110-01-037 | Walker/ Bryan |
SH 75 | Actual | $6,858,560 | 1 | SEAL COAT CONSISTING OF A ONE COURSE SURFACE TREATMENT |
0089-08-095 | Wharton/ Yoakum |
US 59 | Actual | $2,072,945 | 11 | ADDING ACCEL / DECEL LANES |
0030-08-033 | Wheeler/ Childress |
US 83 | Actual | $5,038,373 | 1 | SEAL COAT |
0544-01-020 | Wichita/ Wichita Falls |
SH 258 | Actual | $5,823,532 | 8 | WIDEN STRUCTURES AND ADD SHOULDERS |
0100-03-076 | Wilson/ San Antonio |
US 181 | Actual | $507,654 | 1 | INSTALL TRAFFIC SIGNAL |
|