Detail Letting Schedule for Nolan County (FY 2014)
Nolan County (FY 2014) |
CCSJ: 0006-02-111 | |||
District: | Abilene | Let Date: | DEC 2013 |
Highway: | IH 20 | Let Status: | Actual |
Project ID: | NH 1302(041) | CSJ: | 0006-02-111 |
Description: | INSTALL SAFETY LIGHTING | Handling Code: |
|
Limits From: | AT US 84 | Fund Cat: | 1 |
Limits To: | . | Estimate: | $462,018 |
Length: | 3.0 Miles | Actual: | $423,645 |
Back... |
Totals for 0006-02-111 | ||
---|---|---|---|
Length: | 3.0 Miles | ||
Estimate: | $462,018 | ||
Actual: | $423,645 | ||
CCSJ: 0053-12-057 | |||
District: | Abilene | Let Date: | OCT 2013 |
Highway: | US 84 | Let Status: | Actual |
Project ID: | NH 2014(058) | CSJ: | 0053-12-057 |
Description: | RECONSTRUCTION, REALIGNMENT, WIDENING, STRUCTURES, SAFETY | Handling Code: |
|
Limits From: | APPROX 1 MI NORTHWEST OF ROSCOE | Fund Cat: | 1 |
Limits To: | 5 MI EAST OF MITCHELL C/L(EBL ONLY) | Estimate: | $6,772,927 |
Length: | 2.7 Miles | Actual: | $7,054,502 |
District: | Abilene | Let Date: | OCT 2013 |
Highway: | US 84 | Let Status: | Actual |
Project ID: | NH 2014(058) | CSJ: | 0053-12-062 |
Description: | 2" MILL & FILL DRIVING LN, 2" OVERLAY | Handling Code: |
|
Limits From: | NEAR FM 608 | Fund Cat: | 1 |
Limits To: | MITCHELL COUNTY LINE (WBL ONLY) | Estimate: | $4,011,148 |
Length: | 8.7 Miles | Actual: | $4,493,543 |
Back... |
Totals for 0053-12-057 | ||
Length: | 11.4 Miles | ||
Estimate: | $10,784,075 | ||
Actual: | $11,548,045 |
|