Detail Letting Schedule for Panola County (FY 2014)
Panola County (FY 2014) |
CCSJ: 0063-03-059 | |||
District: | Atlanta | Let Date: | MAR 2014 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | STP 2014(489)HESG | CSJ: | 0063-03-059 |
Description: | TEXTURIZE SHOULDERS & CL TEXTURING | Handling Code: |
|
Limits From: | FM 2792 | Fund Cat: | 8 |
Limits To: | LP 436 | Estimate: | $447,391 |
Length: | 5.7 Miles | Actual: | $259,181 |
District: | Atlanta | Let Date: | MAR 2014 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | STP 2014(490)HESG | CSJ: | 0063-05-035 |
Description: | TEXTURIZE SHOULDERS & CL TEXTURING | Handling Code: |
|
Limits From: | 0.4 MI. N. OF CR 420 | Fund Cat: | 8 |
Limits To: | SHELBY C/L | Estimate: | $538,114 |
Length: | 7.1 Miles | Actual: | $312,138 |
District: | Atlanta | Let Date: | MAR 2014 |
Highway: | US 79 | Let Status: | Actual |
Project ID: | STP 2014(491)HESG | CSJ: | 0246-02-048 |
Description: | TEXTURIZE SHOULDERS & CL TEXTURING | Handling Code: |
|
Limits From: | SH 149 | Fund Cat: | 8 |
Limits To: | FM 124 | Estimate: | $732,867 |
Length: | 9.5 Miles | Actual: | $472,853 |
District: | Atlanta | Let Date: | MAR 2014 |
Highway: | SH 149 | Let Status: | Actual |
Project ID: | STP 2014(487)HESG | CSJ: | 0393-03-033 |
Description: | TEXTURIZE SHOULDERS & CL TEXTURING | Handling Code: |
|
Limits From: | RUSK C/L | Fund Cat: | 8 |
Limits To: | FM 959 | Estimate: | $484,136 |
Length: | 7.4 Miles | Actual: | $332,936 |
District: | Atlanta | Let Date: | MAR 2014 |
Highway: | SH 149 | Let Status: | Actual |
Project ID: | STP 2014(488)HESG | CSJ: | 0394-01-062 |
Description: | TEXTURIZE SHOULDERS & CL TEXTURING | Handling Code: |
|
Limits From: | FM 959 | Fund Cat: | 8 |
Limits To: | US 79 | Estimate: | $300,550 |
Length: | 5.1 Miles | Actual: | $199,170 |
District: | Atlanta | Let Date: | MAR 2014 |
Highway: | FM 10 | Let Status: | Actual |
Project ID: | STP 2014(482)HRRG | CSJ: | 1222-01-030 |
Description: | TEXTURIZE SHOULDERS & CL TEXTURING | Handling Code: |
|
Limits From: | COTTON STREET | Fund Cat: | 8 |
Limits To: | FM 2260 | Estimate: | $584,941 |
Length: | 9.5 Miles | Actual: | $447,648 |
Back... |
Totals for 0063-03-059 | ||
---|---|---|---|
Length: | 44.3 Miles | ||
Estimate: | $3,087,999 | ||
Actual: | $2,023,926 | ||
CCSJ: 0063-04-056 | |||
District: | Atlanta | Let Date: | FEB 2014 |
Highway: | US 59 | Let Status: | Actual |
Project ID: | STP 2014(450)HESG | CSJ: | 0063-04-056 |
Description: | TEXTURIZE SHOULDERS & CL TEXTURING | Handling Code: |
|
Limits From: | US 79 | Fund Cat: | 8 |
Limits To: | 0.4 MI. N. OF CR 420 | Estimate: | $1,827,100 |
Length: | 7.2 Miles | Actual: | $980,825 |
District: | Atlanta | Let Date: | FEB 2014 |
Highway: | US 79 | Let Status: | Actual |
Project ID: | STP 2014(456)HESG | CSJ: | 0247-01-050 |
Description: | TEXTURIZE SHOULDERS & CL TEXTURING | Handling Code: |
|
Limits From: | SABINE RIVER | Fund Cat: | 8 |
Limits To: | US 59/US 79 | Estimate: | $568,714 |
Length: | 7.2 Miles | Actual: | $351,234 |
District: | Atlanta | Let Date: | FEB 2014 |
Highway: | FM 31 | Let Status: | Actual |
Project ID: | STP 2014(406)HESG | CSJ: | 0640-02-028 |
Description: | TEXTURIZE SHOULDERS & CL TEXTURING | Handling Code: |
|
Limits From: | HARRISON C/L | Fund Cat: | 8 |
Limits To: | FM 123 | Estimate: | $505,046 |
Length: | 9.4 Miles | Actual: | $345,817 |
District: | Atlanta | Let Date: | FEB 2014 |
Highway: | FM 31 | Let Status: | Actual |
Project ID: | STP 2014(407)HESG | CSJ: | 0731-01-049 |
Description: | TEXTURIZE SHOULDERS & CL TEXTURING | Handling Code: |
|
Limits From: | FM 123 | Fund Cat: | 8 |
Limits To: | FM 2517 | Estimate: | $423,329 |
Length: | 7.7 Miles | Actual: | $292,124 |
Back... |
Totals for 0063-04-056 | ||
Length: | 31.5 Miles | ||
Estimate: | $3,324,189 | ||
Actual: | $1,970,000 | ||
CCSJ: 0063-11-056 | |||
District: | Atlanta | Let Date: | FEB 2014 |
Highway: | SH 149 | Let Status: | Actual |
Project ID: | STP 2014(408) | CSJ: | 0063-11-056 |
Description: | STRENGTHEN BASE AND RESURFACE EXISTING 2 - LANE HIGHWAY | Handling Code: |
|
Limits From: | 0.1 MI SOUTH OF SH 315 | Fund Cat: | 1 |
Limits To: | US 59 | Estimate: | $2,996,398 |
Length: | 2.2 Miles | Actual: | $2,437,501 |
Back... |
Totals for 0063-11-056 | ||
Length: | 2.2 Miles | ||
Estimate: | $2,996,398 | ||
Actual: | $2,437,501 | ||
CCSJ: 0207-04-035 | |||
District: | Atlanta | Let Date: | JUN 2014 |
Highway: | SH 43 | Let Status: | Actual |
Project ID: | STP 2014(801) | CSJ: | 0207-04-035 |
Description: | RESURFACE EXISTING HIGHWAY WITH ASPHALTIC CONCRETE | Handling Code: |
|
Limits From: | 0.4 MI S. OF FM 959 | Fund Cat: | 1 |
Limits To: | HARRISON C/L | Estimate: | $515,725 |
Length: | 1.2 Miles | Actual: | $494,227 |
District: | Atlanta | Let Date: | JUN 2014 |
Highway: | SH 43 | Let Status: | Actual |
Project ID: | STP 2014(801) | CSJ: | 0207-05-075 |
Description: | RESURFACE EXISTING HIGHWAY WITH ASPHALTIC CONCRETE | Handling Code: |
|
Limits From: | PANOLA C/L | Fund Cat: | 1 |
Limits To: | 0.7 MI N. OF SPRING CREEK | Estimate: | $725,350 |
Length: | 2.6 Miles | Actual: | $748,924 |
Back... |
Totals for 0207-04-035 | ||
Length: | 3.8 Miles | ||
Estimate: | $1,241,075 | ||
Actual: | $1,243,151 | ||
CCSJ: 0247-03-030 | |||
District: | Atlanta | Let Date: | DEC 2013 |
Highway: | US 79 | Let Status: | Actual |
Project ID: | STP 2014(294)HES | CSJ: | 0247-03-029 |
Description: | TEXTURIZE SHOULDERS & CL TEXTURING | Handling Code: |
|
Limits From: | LOUISIANA STATE LINE | Fund Cat: | 8 |
Limits To: | FM 31 | Estimate: | $688,525 |
Length: | 8.9 Miles | Actual: | $641,008 |
District: | Atlanta | Let Date: | DEC 2013 |
Highway: | US 79 | Let Status: | Actual |
Project ID: | NH 2014(293) | CSJ: | 0247-03-030 |
Description: | RESTORE SECTION AND RESURFACE EXISTING HIGHWAY | Handling Code: |
|
Limits From: | LOUISIANA STATE LINE | Fund Cat: | 1 |
Limits To: | 0.9 MI SOUTH OF FM 9 | Estimate: | $1,811,363 |
Length: | 4.0 Miles | Actual: | $1,761,698 |
Back... |
Totals for 0247-03-030 | ||
Length: | 12.9 Miles | ||
Estimate: | $2,499,888 | ||
Actual: | $2,402,706 | ||
CCSJ: 1894-01-020 | |||
District: | Atlanta | Let Date: | OCT 2013 |
Highway: | FM 1971 | Let Status: | Actual |
Project ID: | BR 2013(985) | CSJ: | 1894-01-020 |
Description: | REHABILITATE BRIDGE AND APPROACHES | Handling Code: |
|
Limits From: | AT MURVAUL CREEK | Fund Cat: | 6 |
Limits To: | AT MURVAUL LAKE | Estimate: | $388,355 |
Length: | 0.0 Miles | Actual: | $437,577 |
Back... |
Totals for 1894-01-020 | ||
Length: | 0.0 Miles | ||
Estimate: | $388,355 | ||
Actual: | $437,577 | ||
CCSJ: 1894-01-021 | |||
District: | Atlanta | Let Date: | FEB 2014 |
Highway: | FM 1971 | Let Status: | Actual |
Project ID: | STP 2014(447)HES | CSJ: | 1894-01-021 |
Description: | SAFETY TREAT FIXED OBJECTS | Handling Code: |
|
Limits From: | SH 315 | Fund Cat: | 8 |
Limits To: | RUSK COUNTY LINE | Estimate: | $650,560 |
Length: | 9.6 Miles | Actual: | $591,745 |
Back... |
Totals for 1894-01-021 | ||
Length: | 9.6 Miles | ||
Estimate: | $650,560 | ||
Actual: | $591,745 |
|