Detail Letting Schedule for Atascosa County (FY 2015)
Atascosa County (FY 2015) |
CCSJ: 0073-03-063 | |||
District: | San Antonio | Let Date: | SEP 2014 |
Highway: | US 281 | Let Status: | Actual |
Project ID: | STP 2015(021)HESG | CSJ: | 0073-03-063 |
Description: | SAFETY TREAT FIXED OBJECTS | Handling Code: |
|
Limits From: | BEXAR COUNTY LINE | Fund Cat: | 8 |
Limits To: | 0.443 MI N OF FM 3006 | Estimate: | $238,430 |
Length: | 8.7 Miles | Actual: | $167,948 |
District: | San Antonio | Let Date: | SEP 2014 |
Highway: | SS 122 | Let Status: | Actual |
Project ID: | STP 2015(022)HESG | CSJ: | 0100-02-061 |
Description: | SAFETY TREAT FIXED OBJECTS, SIGNS & DELINEATION | Handling Code: |
|
Limits From: | LP 13 | Fund Cat: | 8 |
Limits To: | IH 410 | Estimate: | $328,257 |
Length: | 3.0 Miles | Actual: | $310,981 |
Back... |
Totals for 0073-03-063 | ||
---|---|---|---|
Length: | 11.7 Miles | ||
Estimate: | $566,687 | ||
Actual: | $478,929 | ||
CCSJ: 0073-05-068 | |||
District: | San Antonio | Let Date: | MAR 2015 |
Highway: | IH 37 | Let Status: | Actual |
Project ID: | STP 2015(733)HES | CSJ: | 0073-05-068 |
Description: | WIDEN ROADWAY TO ADD SHOULDERS | Handling Code: |
|
Limits From: | 0.4 MI SOUTH OF US 281 | Fund Cat: | 8 |
Limits To: | 0.2 MI SOUTH OF FM 541 | Estimate: | $2,661,056 |
Length: | 6.1 Miles | Actual: | $2,293,599 |
District: | San Antonio | Let Date: | MAR 2015 |
Highway: | IH 37 | Let Status: | Actual |
Project ID: | STP 2015(734)HES | CSJ: | 0073-10-051 |
Description: | INSTALL PROTECTION AND WIDEN PAVED SHOULDERS | Handling Code: |
|
Limits From: | 1.1 MI SOUTH OF US 281 | Fund Cat: | 8 |
Limits To: | 0.2 MI NORTH OF SP 199 | Estimate: | $1,280,054 |
Length: | 1.8 Miles | Actual: | $1,352,504 |
Back... |
Totals for 0073-05-068 | ||
Length: | 7.9 Miles | ||
Estimate: | $3,941,110 | ||
Actual: | $3,646,103 | ||
CCSJ: 0073-13-009 | |||
District: | San Antonio | Let Date: | DEC 2014 |
Highway: | US 281A | Let Status: | Actual |
Project ID: | STP 2015(368) | CSJ: | 0073-13-009 |
Description: | RESTORE EXISTING ROADWAY AND OPERATIONAL IMPROVEMENTS AT | Handling Code: |
|
Limits From: | 0.246 MILES N. OF FM 140 | Fund Cat: | 1 |
Limits To: | 0.170 MILES S. OF FM 1099 | Estimate: | $1,889,406 |
Length: | 2.6 Miles | Actual: | $1,478,559 |
Back... |
Totals for 0073-13-009 | ||
Length: | 2.6 Miles | ||
Estimate: | $1,889,406 | ||
Actual: | $1,478,559 | ||
CCSJ: 0328-03-032 | |||
District: | San Antonio | Let Date: | MAY 2015 |
Highway: | SH 97 | Let Status: | Actual |
Project ID: | STP 1502(165) | CSJ: | 0328-03-032 |
Description: | REHAB AND WIDEN ROADWAY TO PROVIDE PASSING LANES AND | Handling Code: |
|
Limits From: | WILSON COUNTY LINE | Fund Cat: | 1 |
Limits To: | IH 37 | Estimate: | $13,475,064 |
Length: | 6.7 Miles | Actual: | $11,864,972 |
Back... |
Totals for 0328-03-032 | ||
Length: | 6.7 Miles | ||
Estimate: | $13,475,064 | ||
Actual: | $11,864,972 | ||
CCSJ: 0328-05-037 | |||
District: | San Antonio | Let Date: | MAY 2015 |
Highway: | SH 97 | Let Status: | Actual |
Project ID: | STP 1502(166) | CSJ: | 0328-05-037 |
Description: | REHAB AND WIDEN ROADWAY TO PROVIDE PASSING LANES AND | Handling Code: |
|
Limits From: | 0.6 MILES EAST OF BURNETT AVE | Fund Cat: | 1 |
Limits To: | SH 16 | Estimate: | $19,315,926 |
Length: | 9.8 Miles | Actual: | $17,494,208 |
Back... |
Totals for 0328-05-037 | ||
Length: | 9.8 Miles | ||
Estimate: | $19,315,926 | ||
Actual: | $17,494,208 | ||
CCSJ: 0328-05-044 | |||
District: | San Antonio | Let Date: | AUG 2015 |
Highway: | SH 97 | Let Status: | Actual |
Project ID: | STP 1502(612) | CSJ: | 0328-05-044 |
Description: | REHAB AND WIDEN ROADWAY TO PROVIDE PASSING LANES AND | Handling Code: |
|
Limits From: | FM 140 | Fund Cat: | 1 |
Limits To: | 0.6 MILES EAST OF BURNETT AVE | Estimate: | $1,969,714 |
Length: | 1.0 Miles | Actual: | $1,760,592 |
District: | San Antonio | Let Date: | AUG 2015 |
Highway: | SH 97 | Let Status: | Actual |
Project ID: | STP 1502(612) | CSJ: | 0328-06-027 |
Description: | REHAB AND WIDEN ROADWAY TO PROVIDE PASSING LANES | Handling Code: |
|
Limits From: | 9.0 MI NORTH OF MCMULLEN C/L | Fund Cat: | 1 |
Limits To: | FM 140 | Estimate: | $11,946,923 |
Length: | 6.8 Miles | Actual: | $10,776,873 |
Back... |
Totals for 0328-05-044 | ||
Length: | 7.8 Miles | ||
Estimate: | $13,916,637 | ||
Actual: | $12,537,465 | ||
CCSJ: 0613-02-058 | |||
District: | San Antonio | Let Date: | JUN 2015 |
Highway: | SH 16 | Let Status: | Actual |
Project ID: | STP 1502(276)HES | CSJ: | 0613-02-057 |
Description: | PLACE INVERTED PROFILE PAVEMENT MARKINGS ALONG EDGELINES | Handling Code: |
|
Limits From: | 0.937 MI S OF FM 3350 | Fund Cat: | 8 |
Limits To: | 0.951 MI N OF CR 306 | Estimate: | $53,360 |
Length: | 4.0 Miles | Actual: | $35,128 |
District: | San Antonio | Let Date: | JUN 2015 |
Highway: | SH 16 | Let Status: | Actual |
Project ID: | STP 1502(275) | CSJ: | 0613-02-058 |
Description: | RESTORE EXISTING ROADWAY | Handling Code: |
|
Limits From: | SH 97 | Fund Cat: | 1 |
Limits To: | 0.2 MI SOUTH OF SP 282 | Estimate: | $13,657,441 |
Length: | 7.8 Miles | Actual: | $13,453,086 |
Back... |
Totals for 0613-02-058 | ||
Length: | 11.8 Miles | ||
Estimate: | $13,710,801 | ||
Actual: | $13,488,214 |
|