Detail Letting Schedule for Bosque County (FY 2015)
Last Update: Tuesday, September 29, 2015
CCSJ: 3228-02-013
|
District: |
Waco |
Let Date: |
APR 2015 |
Highway: |
FM 1713 |
Let Status: |
Actual |
Project ID: |
BR 2015(874) |
CSJ: |
3228-02-013 |
Description: |
REPAINT BRIDGE |
Handling Code: |
|
Limits From: |
@ LAKE WHITNEY |
Fund Cat: |
6 |
Limits To: |
. |
Estimate: |
$4,660,460 |
Length: |
0.6 Miles |
Actual: |
$2,623,030 |
|
Back...
|
Totals for 3228-02-013 |
Length: |
0.6 Miles |
Estimate: |
$4,660,460 |
Actual: |
$2,623,030 |
Handling Code |
Definition |
XX |
Project not processed through statewide letting |
TR |
Transfer of funds |
LC |
Project let through local entity |
NC |
Project not charged against district apportionment |
Let Status |
Definition |
Tentative |
Estimated letting date for this project |
Approved |
Project has administrative approval to be let |
Actual |
Project was let to contract |
|