Detail Letting Schedule for Goliad County (FY 2015)

Last Update: Wednesday, September 24, 2014
Goliad County (FY 2015)

CCSJ: 0155-03-037

District: Corpus Christi Let Date: AUG 2015
Highway: US 183 Let Status: Tentative
Project ID: BR ( ) CSJ: 0155-03-037
Description: BRIDGE REPLACEMENT Handling
Code:
 
Limits From: ON US 183 STR5 AT MANAHUILLA CREEK Fund Cat: 6
Limits To: 2.3 MI. N. OF US 59 Estimate: $3,220,000
Length: 0.1 Miles Actual:  
 
Back...

Totals for 0155-03-037
Length: 0.1 Miles
Estimate: $3,220,000
Actual:  

CCSJ: 1196-03-016

District: Corpus Christi Let Date: DEC 2014
Highway: FM 884 Let Status: Approved
Project ID: STP 2015(379)HES CSJ: 1196-03-016
Description: PROVIDE ADDITIONAL PAVED SURFACE WIDTH Handling
Code:
 
Limits From: FM 1726 Fund Cat: 8
Limits To: FM 81 Estimate: $2,332,815
Length: 6.7 Miles Actual:  
 
Back...

Totals for 1196-03-016
Length: 6.7 Miles
Estimate: $2,332,815
Actual:  


Handling Code Definition
XX Project not processed through statewide letting
TR Transfer of funds
LC Project let through local entity
NC Project not charged against district apportionment



Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract