Detail Letting Schedule for Guadalupe County (FY 2015)

Last Update: Monday, March 23, 2015
Guadalupe County (FY 2015)

CCSJ: 0535-01-072

District: San Antonio Let Date: MAY 2015
Highway: IH 10 Let Status: Approved
Project ID: C 535-1-72 CSJ: 0535-01-072
Description: CONSTRUCT FRONTAGE ROADS AND OPERATIONAL IMPROVEMENTS Handling
Code:
 
Limits From: SH 46 Fund Cat: 3
Limits To: SH 123 B Estimate: $28,565,789
Length: 2.0 Miles Actual:  
 
Back...

Totals for 0535-01-072
Length: 2.0 Miles
Estimate: $28,565,789
Actual:  

CCSJ: 0915-46-040

District: San Antonio Let Date: MAY 2015
Highway: VA Let Status: Approved
Project ID: STP 2014(099)TE CSJ: 0915-46-040
Description: COLLEGE STREET / CEDAR STREET SIDEWALK NETWORK EXPANSION Handling
Code:
 
Limits From: IN THE CITY OF SEGUIN Fund Cat: 3
Limits To: . Estimate: $478,541
Length: 0.0 Miles Actual:  
 
District: San Antonio Let Date: MAY 2015
Highway: VA Let Status: Approved
Project ID: STP 2014(106)TE CSJ: 0915-46-041
Description: JEFFERSON STREET SIDEWALK NETWORK EXPANSION Handling
Code:
 
Limits From: IN THE CITY OF SEGUIN Fund Cat: 3
Limits To: . Estimate: $310,873
Length: 0.0 Miles Actual:  
 
Back...

Totals for 0915-46-040
Length: 0.0 Miles
Estimate: $789,414
Actual:  

CCSJ: 0915-46-043

District: San Antonio Let Date: AUG 2015
Highway: VA Let Status: Tentative
Project ID: STP ( )TP CSJ: 0915-46-043
Description: CONSTRUCT SIDEWALKS ALONGSIDE AND WITHIN THE NEW COMMUNITY Handling
Code:
 
Limits From: IN SEGUIN FROM N. VAUGHAN AND Fund Cat: 3
Limits To: SAN ANTONIO AVE TO GUADALUPE/COURT Estimate: $1,206,888
Length: 0.0 Miles Actual:  
 
Back...

Totals for 0915-46-043
Length: 0.0 Miles
Estimate: $1,206,888
Actual:  

CCSJ: 3107-02-034

District: San Antonio Let Date: JUL 2015
Highway: FM 3009 Let Status: Approved
Project ID: STP ( )MM CSJ: 3107-02-034
Description: CONSTRUCT SIDEWALKS Handling
Code:
 
Limits From: IH 35 Fund Cat: 7
Limits To: FM 78 Estimate: $2,825,000
Length: 3.1 Miles Actual:  
 
Back...

Totals for 3107-02-034
Length: 3.1 Miles
Estimate: $2,825,000
Actual:  


Handling Code Definition
XX Project not processed through statewide letting
TR Transfer of funds
LC Project let through local entity
NC Project not charged against district apportionment



Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract