Detail Letting Schedule for Hopkins County (FY 2015)

Last Update: Wednesday, April 16, 2014
Hopkins County (FY 2015)

CCSJ: 0009-09-081

District: Paris Let Date: JAN 2015
Highway: IH 30 Let Status: Tentative
Project ID: STP 2000(825)TE CSJ: 0009-09-081
Description: CONSTRUCTION OF SAFETY REST AREA Handling
Code:
 
Limits From: ON IH 30, 1 MILE EAST OF CUMBY Fund Cat: 9
Limits To: . Estimate: $15,000,000
Length: 0.0 Miles Actual:  
 
Back...

Totals for 0009-09-081
Length: 0.0 Miles
Estimate: $15,000,000
Actual:  

CCSJ: 0009-09-099

District: Paris Let Date: SEP 2014
Highway: IH 30 Let Status: Tentative
Project ID: STP ( )HES CSJ: 0009-09-099
Description: TEXTURIZED SHOULDERS (ROLLED IN OR MILLED IN) Handling
Code:
 
Limits From: SH 19 Fund Cat: 8
Limits To: TEXAS AVE IN SULPHUR SPRINGS Estimate: $32,980
Length: 1.5 Miles Actual:  
 
District: Paris Let Date: SEP 2014
Highway: IH 30 Let Status: Tentative
Project ID: STP ( )HES CSJ: 0010-02-091
Description: TEXTURIZE SHOULDERS (ROLLED IN OR MILLED IN) Handling
Code:
 
Limits From: TEXAS AVE IN SULPHUR SPRINGS Fund Cat: 8
Limits To: SL 301 Estimate: $77,558
Length: 3.4 Miles Actual:  
 
District: Paris Let Date: SEP 2014
Highway: SH 56 Let Status: Tentative
Project ID: STP ( )HES CSJ: 0045-04-064
Description: TEXTURIZE SHOULDERS (ROLLED IN OR MILLED IN) , CENTERLINE Handling
Code:
 
Limits From: 0.376 MILES EAST OF US 75 Fund Cat: 8
Limits To: FANNIN COUNTY LINE Estimate: $90,458
Length: 13.8 Miles Actual:  
 
District: Paris Let Date: SEP 2014
Highway: US 82 Let Status: Tentative
Project ID: STP ( )HES CSJ: 0045-09-099
Description: TEXTURIZED SHOULDERS Handling
Code:
 
Limits From: MT OLIVE ROAD Fund Cat: 8
Limits To: DIVISION STREET Estimate: $223,096
Length: 2.8 Miles Actual:  
 
District: Paris Let Date: SEP 2014
Highway: US 82 Let Status: Tentative
Project ID: STP ( )HES CSJ: 0045-12-079
Description: TEXTURIZE SHOULDERS & CENTERLINE Handling
Code:
 
Limits From: LAMAR COUNTY LINE Fund Cat: 8
Limits To: SH 37 Estimate: $107,104
Length: 16.5 Miles Actual:  
 
District: Paris Let Date: SEP 2014
Highway: US 82 Let Status: Tentative
Project ID: STP ( )HES CSJ: 0045-18-034
Description: TEXTURIZE SHOULDERS (ROLLED IN OR MILLED IN) , CENTERLINE Handling
Code:
 
Limits From: COOKE COUNTY LINE Fund Cat: 8
Limits To: FM 1417 Estimate: $115,035
Length: 17.4 Miles Actual:  
 
District: Paris Let Date: SEP 2014
Highway: US 82 Let Status: Tentative
Project ID: STP ( )HES CSJ: 0045-21-013
Description: TEXTURIZE SHOULDERS (ROLLED IN OR MILLED IN) , CENTERLINE Handling
Code:
 
Limits From: SH 78 Fund Cat: 8
Limits To: LAMAR COUNTY LINE Estimate: $120,395
Length: 18.6 Miles Actual:  
 
District: Paris Let Date: SEP 2014
Highway: US 82 Let Status: Tentative
Project ID: STP ( )HES CSJ: 0046-01-060
Description: TEXTURIZE SHOULDERS & CENTERLINE_TEXTURIZING Handling
Code:
 
Limits From: FM 114 Fund Cat: 8
Limits To: BOWIE COUNTY LINE Estimate: $110,577
Length: 16.9 Miles Actual:  
 
District: Paris Let Date: SEP 2014
Highway: US 377 Let Status: Tentative
Project ID: STP ( )HES CSJ: 0081-07-022
Description: CENTERLINE TEXTURING Handling
Code:
 
Limits From: FM 902 Fund Cat: 8
Limits To: DENTON COUNTY LINE Estimate: $88,871
Length: 10.0 Miles Actual:  
 
District: Paris Let Date: SEP 2014
Highway: SH 289 Let Status: Tentative
Project ID: STP ( )HES CSJ: 0091-01-047
Description: TEXTURIZE SHOULDERS (ROLLED IN OR MILLED IN) , CENTERLINE Handling
Code:
 
Limits From: RM 196+0.596 Fund Cat: 8
Limits To: COLLIN COUNTY LINE Estimate: $174,218
Length: 29.3 Miles Actual:  
 
District: Paris Let Date: SEP 2014
Highway: US 69 Let Status: Tentative
Project ID: STP ( )HES CSJ: 0202-03-039
Description: TEXTURIZE SHOULDERS (ROLLED IN OR MILLED IN) , CENTERLINE Handling
Code:
 
Limits From: SH 121 Fund Cat: 8
Limits To: HUNT COUNTY LINE Estimate: $58,500
Length: 8.2 Miles Actual:  
 
District: Paris Let Date: SEP 2014
Highway: FM 79 Let Status: Tentative
Project ID: STP ( )HES CSJ: 0688-02-056
Description: TEXTURIZE SHOULDERS AND CENTERLINE Handling
Code:
 
Limits From: FANNIN COUNTY LINE Fund Cat: 8
Limits To: US 82 Estimate: $145,713
Length: 21.0 Miles Actual:  
 
Back...

Totals for 0009-09-099
Length: 159.4 Miles
Estimate: $1,344,505
Actual:  

CCSJ: 0083-02-048

District: Paris Let Date: AUG 2015
Highway: SH 11 Let Status: Tentative
Project ID: STP ( )HES CSJ: 0083-02-048
Description: WIDEN ROADWAY Handling
Code:
 
Limits From: 0.419 MI SE OF COUNTY LINE Fund Cat: 1
Limits To: COUNTY ROAD 4737 Estimate: $4,733,622
Length: 3.2 Miles Actual:  
 
Back...

Totals for 0083-02-048
Length: 3.2 Miles
Estimate: $4,733,622
Actual:  

CCSJ: 0546-06-017

District: Paris Let Date: OCT 2014
Highway: FM 71 Let Status: Tentative
Project ID: STP ( ) CSJ: 0546-06-017
Description: REHAB EXIST ROAD Handling
Code:
 
Limits From: SH 19 Fund Cat: 1
Limits To: FM 3236 Estimate: $2,461,090
Length: 4.1 Miles Actual:  
 
Back...

Totals for 0546-06-017
Length: 4.1 Miles
Estimate: $2,461,090
Actual:  

CCSJ: 0680-05-008

District: Paris Let Date: MAR 2015
Highway: FM 900 Let Status: Tentative
Project ID: BR 90(264) CSJ: 0680-05-008
Description: REHABILITATE BRIDGE & APPROACHES Handling
Code:
 
Limits From: AT W GREENWOOD CREEK Fund Cat: 6
Limits To: . Estimate: $489,600
Length: 0.1 Miles Actual:  
 
District: Paris Let Date: MAR 2015
Highway: FM 69 Let Status: Tentative
Project ID: BR ( ) CSJ: 0766-01-021
Description: REPLACE BRIDGE & APPROACHES Handling
Code:
 
Limits From: AT LITTLE CANEY CREEK Fund Cat: 6
Limits To: . Estimate: $489,600
Length: 0.2 Miles Actual:  
 
District: Paris Let Date: MAR 2015
Highway: CR Let Status: Tentative
Project ID: BR 2014(190) CSJ: 0901-28-061
Description: REPLACE BRIDGE AND APPROACHES Handling
Code:
 
Limits From: CR 528-1 Fund Cat: 6
Limits To: AT SULPHUR RIVER TRIBUTARY Estimate: $198,900
Length: 0.0 Miles Actual:  
 
Back...

Totals for 0680-05-008
Length: 0.3 Miles
Estimate: $1,178,100
Actual:  


Handling Code Definition
XX Project not processed through statewide letting
TR Transfer of funds
LC Project let through local entity
NC Project not charged against district apportionment



Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract