Detail Letting Schedule for Kerr County (FY 2015)

Last Update: Tuesday, September 2, 2014
Kerr County (FY 2015)

CCSJ: 0193-02-038

District: San Antonio Let Date: SEP 2014
Highway: SH 39 Let Status: Approved
Project ID: BR 2013(715) CSJ: 0193-02-038
Description: REPLACE NARROW BRIDGE & APPROACHES Handling
Code:
 
Limits From: AT HUNT CROSSING Fund Cat: 6
Limits To: . Estimate: $1,945,917
Length: 0.2 Miles Actual:  
 
List Showing Order
Proposal Req Form
Bidders List
Project Addenda
Back...

Totals for 0193-02-038
Length: 0.2 Miles
Estimate: $1,945,917
Actual:  

CCSJ: 0193-02-043

District: San Antonio Let Date: FEB 2015
Highway: SH 39 Let Status: Tentative
Project ID: STP ( )HES CSJ: 0193-02-043
Description: INSTALL ADVANCED WARNING SIGNALS, & PLACE INVERTED PROFILE Handling
Code:
 
Limits From: 2.9 MI EAST OF FM 1340 Fund Cat: 8
Limits To: 3.6 MI EAST OF FM 1340 Estimate: $54,972
Length: 0.7 Miles Actual:  
 
District: San Antonio Let Date: FEB 2015
Highway: SH 16 Let Status: Tentative
Project ID: STP ( )HES CSJ: 0291-03-065
Description: WIDEN NARROW RDWY TO PROVIDE SHLDRS, SAFETY TREAT FIXED OBJ Handling
Code:
 
Limits From: FM 1273 Fund Cat: 8
Limits To: 4 MI S OF FM 1273 Estimate: $1,359,856
Length: 4.0 Miles Actual:  
 
Back...

Totals for 0193-02-043
Length: 4.7 Miles
Estimate: $1,414,828
Actual:  


Handling Code Definition
XX Project not processed through statewide letting
TR Transfer of funds
LC Project let through local entity
NC Project not charged against district apportionment



Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract