Detail Letting Schedule for Lavaca County (FY 2015)

Last Update: Monday, December 15, 2014
Lavaca County (FY 2015)

CCSJ: 0269-10-023

District: Yoakum Let Date: AUG 2015
Highway: FM 531 Let Status: Tentative
Project ID: BR ( ) CSJ: 0269-10-023
Description: REPLACE BRIDGE AND APPROACHES Handling
Code:
 
Limits From: AT YELLOW BANK CREEK Fund Cat: 6
Limits To: STR # 0269-10-027 Estimate: $761,000
Length: 0.1 Miles Actual:  
 
Back...

Totals for 0269-10-023
Length: 0.1 Miles
Estimate: $761,000
Actual:  

CCSJ: 0446-01-047

District: Yoakum Let Date: OCT 2014
Highway: US 90A Let Status: Actual
Project ID: BR 2015(245) CSJ: 0446-01-047
Description: REPLACE BRIDGE AND APPROACHES Handling
Code:
 
Limits From: @ BRUSHY CREEK Fund Cat: 6
Limits To: STR # 0446-01-016 Estimate: $3,409,153
Length: 0.6 Miles Actual: $3,321,678
 
Bid Tabulations
Back...

Totals for 0446-01-047
Length: 0.6 Miles
Estimate: $3,409,153
Actual: $3,321,678

CCSJ: 0913-29-033

District: Yoakum Let Date: AUG 2015
Highway: CR Let Status: Tentative
Project ID: BR 2007(372) CSJ: 0913-29-033
Description: REPLACE BRIDGE AND APPROACHES Handling
Code:
 
Limits From: AT SMOTHERS CREEK CR 183 Fund Cat: 6
Limits To: (CR 183) STR AA01-02-004 Estimate: $629,000
Length: 0.3 Miles Actual:  
 
Back...

Totals for 0913-29-033
Length: 0.3 Miles
Estimate: $629,000
Actual:  

CCSJ: 0913-29-045

District: Yoakum Let Date: NOV 2014
Highway: CR Let Status: Actual
Project ID: BR 2012(429) CSJ: 0913-29-045
Description: REPLACE BRIDGE AND APPROACHES Handling
Code:
 
Limits From: AT SUPPLEJACK CREEK CR 402 Fund Cat: 6
Limits To: (CR 402) STR # AA03-78-001 Estimate: $450,286
Length: 0.1 Miles Actual: $420,926
 
Award Status
Bid Tabulations
Back...

Totals for 0913-29-045
Length: 0.1 Miles
Estimate: $450,286
Actual: $420,926


Handling Code Definition
XX Project not processed through statewide letting
TR Transfer of funds
LC Project let through local entity
NC Project not charged against district apportionment



Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract