Detail Letting Schedule for Newton County (FY 2015)

Last Update: Wednesday, September 24, 2014
Newton County (FY 2015)

CCSJ: 0305-03-041

District: Beaumont Let Date: MAY 2015
Highway: SH 87 Let Status: Tentative
Project ID: STP ( )HES CSJ: 0305-03-041
Description: INCREASE SUPERELEVATION, CENTERLINE TEXTURING, AND TEXTURIZE Handling
Code:
 
Limits From: FM 1004, SOUTH Fund Cat: 8
Limits To: 7.5 MILES Estimate: $251,667
Length: 7.5 Miles Actual:  
 
Back...

Totals for 0305-03-041
Length: 7.5 Miles
Estimate: $251,667
Actual:  

CCSJ: 0920-06-032

District: Beaumont Let Date: FEB 2015
Highway: CR Let Status: Tentative
Project ID: BR 2014(568) CSJ: 0920-06-032
Description: REPLACE BRIDGE AND APPROACHES Handling
Code:
 
Limits From: CR 3024 AT CLEAR CRK Fund Cat: 6
Limits To: (STR AA3024001) Estimate: $332,452
Length: 0.1 Miles Actual:  
 
Back...

Totals for 0920-06-032
Length: 0.1 Miles
Estimate: $332,452
Actual:  


Handling Code Definition
XX Project not processed through statewide letting
TR Transfer of funds
LC Project let through local entity
NC Project not charged against district apportionment



Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract