Detail Letting Schedule for Taylor County (FY 2015)
Taylor County (FY 2015) |
CCSJ: 0006-04-071 | |||
District: | Abilene | Let Date: | JAN 2015 |
Highway: | IH 20 | Let Status: | Actual |
Project ID: | NH 2015(633) | CSJ: | 0006-04-071 |
Description: | PLANING EXISTING SURFACE, FLEXIBLE PAVEMENT STRUCTURE REPAIR | Handling Code: |
|
Limits From: | NOLAN COUNTY LINE | Fund Cat: | 1 |
Limits To: | NEAR WELLS LANE | Estimate: | $4,280,317 |
Length: | 13.4 Miles | Actual: | $4,088,129 |
Back... |
Totals for 0006-04-071 | ||
---|---|---|---|
Length: | 13.4 Miles | ||
Estimate: | $4,280,317 | ||
Actual: | $4,088,129 | ||
CCSJ: 0006-06-098 | |||
District: | Abilene | Let Date: | MAR 2015 |
Highway: | IH 20 | Let Status: | Actual |
Project ID: | NH 2015(648) | CSJ: | 0006-06-098 |
Description: | PLANE AND REPAIR EXISTING PAVEMENT STRUCTURE, OVERLAY | Handling Code: |
|
Limits From: | LP 322 | Fund Cat: | 1 |
Limits To: | BI 20-R (E US HWY 80 SFR ONLY) | Estimate: | $1,032,270 |
Length: | 2.3 Miles | Actual: | $1,059,120 |
Back... |
Totals for 0006-06-098 | ||
Length: | 2.3 Miles | ||
Estimate: | $1,032,270 | ||
Actual: | $1,059,120 | ||
CCSJ: 0006-18-050 | |||
District: | Abilene | Let Date: | FEB 2015 |
Highway: | US 84 | Let Status: | Actual |
Project ID: | BR 2014(849) | CSJ: | 0006-18-050 |
Description: | REPLACE BRIDGE & APPROACHES | Handling Code: |
|
Limits From: | US 84_(PSN 67) | Fund Cat: | 1 |
Limits To: | AT UPRR & OLD HIGHWAY 80 | Estimate: | $8,371,790 |
Length: | 1.5 Miles | Actual: | $8,999,252 |
Back... |
Totals for 0006-18-050 | ||
Length: | 1.5 Miles | ||
Estimate: | $8,371,790 | ||
Actual: | $8,999,252 | ||
CCSJ: 0011-01-030 | |||
District: | Abilene | Let Date: | MAR 2015 |
Highway: | SH 351 | Let Status: | Actual |
Project ID: | STP 1302(056) | CSJ: | 0011-01-030 |
Description: | CURB & GUTTER, MEDIAN, STORM SEWER, DRIVEWAYS, SIDEWALKS, | Handling Code: |
|
Limits From: | IH 20 | Fund Cat: | 1 |
Limits To: | ABILENE EAST CITY LIMIT | Estimate: | $5,909,901 |
Length: | 1.8 Miles | Actual: | $6,920,470 |
Back... |
Totals for 0011-01-030 | ||
Length: | 1.8 Miles | ||
Estimate: | $5,909,901 | ||
Actual: | $6,920,470 | ||
CCSJ: 0011-01-033 | |||
District: | Abilene | Let Date: | FEB 2015 |
Highway: | SH 351 | Let Status: | Actual |
Project ID: | STP 2015(585)HES | CSJ: | 0011-01-033 |
Description: | INSTALL TRAFFIC SIGNAL | Handling Code: |
|
Limits From: | AT FM 2833 | Fund Cat: | 8 |
Limits To: | . | Estimate: | $201,723 |
Length: | 0.2 Miles | Actual: | $173,646 |
Back... |
Totals for 0011-01-033 | ||
Length: | 0.2 Miles | ||
Estimate: | $201,723 | ||
Actual: | $173,646 | ||
CCSJ: 0033-06-106 | |||
District: | Abilene | Let Date: | MAY 2015 |
Highway: | US 83 | Let Status: | Actual |
Project ID: | NH 1502(290) | CSJ: | 0033-06-106 |
Description: | SPOT REPAIR, SEAL & ASPHALT CONCRETE OVERLAY | Handling Code: |
|
Limits From: | NEAR NORTH 3RD STREET IN ABILENE | Fund Cat: | 1 |
Limits To: | US 277 (S 14TH) (FTG RDS ONLY) | Estimate: | $2,210,302 |
Length: | 2.1 Miles | Actual: | $2,435,990 |
Back... |
Totals for 0033-06-106 | ||
Length: | 2.1 Miles | ||
Estimate: | $2,210,302 | ||
Actual: | $2,435,990 | ||
CCSJ: 0034-02-042 | |||
District: | Abilene | Let Date: | SEP 2014 |
Highway: | US 83 | Let Status: | Actual |
Project ID: | STP 2015(043)HESG | CSJ: | 0034-02-042 |
Description: | TEXTURIZE SHOULDERS (ROLLED IN OR MILLED IN) , CENTERLINE | Handling Code: |
|
Limits From: | Y" NORTHEAST OF TUSCOLA | Fund Cat: | 8 |
Limits To: | RUNNELS COUNTY LINE | Estimate: | $140,035 |
Length: | 14.9 Miles | Actual: | $54,923 |
District: | Abilene | Let Date: | SEP 2014 |
Highway: | SH 36 | Let Status: | Actual |
Project ID: | STP 2015(044)HESG | CSJ: | 0181-02-028 |
Description: | TEXTURIZE SHOULDERS (ROLLED IN OR MILLED IN) | Handling Code: |
|
Limits From: | TAYLOR CL | Fund Cat: | 8 |
Limits To: | US 283 | Estimate: | $113,891 |
Length: | 16.4 Miles | Actual: | $87,091 |
District: | Abilene | Let Date: | SEP 2014 |
Highway: | US 380 | Let Status: | Actual |
Project ID: | STP 2015(045)HESG | CSJ: | 0360-02-028 |
Description: | TEXTURIZE SHOULDERS (ROLLED IN OR MILLED IN) , CENTERLINE | Handling Code: |
|
Limits From: | STONEWALL COUNTY LINE | Fund Cat: | 8 |
Limits To: | SH 6 IN RULE | Estimate: | $32,121 |
Length: | 5.9 Miles | Actual: | $21,840 |
District: | Abilene | Let Date: | SEP 2014 |
Highway: | SH 153 | Let Status: | Actual |
Project ID: | STP 2015(046)HESG | CSJ: | 0650-01-030 |
Description: | TEXTURIZE SHOULDERS (ROLLED IN OR MILLED IN) | Handling Code: |
|
Limits From: | SH 70 | Fund Cat: | 8 |
Limits To: | TAYLOR CL | Estimate: | $112,748 |
Length: | 17.7 Miles | Actual: | $83,938 |
District: | Abilene | Let Date: | SEP 2014 |
Highway: | SH 350 | Let Status: | Actual |
Project ID: | STP 2015(047)HESG | CSJ: | 0693-01-032 |
Description: | TEXTURIZE SHOULDERS (ROLLED IN OR MILLED IN) , CENTERLINE | Handling Code: |
|
Limits From: | 3RD STR IN BIG SPRING | Fund Cat: | 8 |
Limits To: | MITCHELL CL | Estimate: | $182,480 |
Length: | 25.1 Miles | Actual: | $138,182 |
District: | Abilene | Let Date: | SEP 2014 |
Highway: | SH 350 | Let Status: | Actual |
Project ID: | STP 2015(048)HESG | CSJ: | 0693-02-013 |
Description: | TEXTURIZE SHOULDERS (ROLLED IN OR MILLED IN) , CENTERLINE | Handling Code: |
|
Limits From: | HOWARD COUNTY LINE | Fund Cat: | 8 |
Limits To: | SCURRY COUNTY LINE | Estimate: | $50,839 |
Length: | 6.6 Miles | Actual: | $38,492 |
Back... |
Totals for 0034-02-042 | ||
Length: | 86.6 Miles | ||
Estimate: | $632,114 | ||
Actual: | $424,466 | ||
CCSJ: 0054-01-030 | |||
District: | Abilene | Let Date: | SEP 2014 |
Highway: | US 84 | Let Status: | Actual |
Project ID: | STP 2015(049)HESG | CSJ: | 0054-01-030 |
Description: | TEXTURIZE SHOULDERS (PROFILE PAVEMENT MARKINGS) | Handling Code: |
|
Limits From: | Y" NORTHEAST OF TUSCOLA | Fund Cat: | 8 |
Limits To: | COLEMAN COUNTY LINE | Estimate: | $178,784 |
Length: | 11.3 Miles | Actual: | $64,753 |
District: | Abilene | Let Date: | SEP 2014 |
Highway: | FM 89 | Let Status: | Actual |
Project ID: | STP 2015(050)HRRG | CSJ: | 0699-01-048 |
Description: | TEXTURIZE SHOULDERS, CENTERLINE | Handling Code: |
|
Limits From: | US 277 | Fund Cat: | 8 |
Limits To: | FM 707 | Estimate: | $244,585 |
Length: | 21.5 Miles | Actual: | $165,178 |
District: | Abilene | Let Date: | SEP 2014 |
Highway: | FM 604 | Let Status: | Actual |
Project ID: | STP 2015(051)HESG | CSJ: | 0974-01-027 |
Description: | TEXTURIZE SHOULDERS (PROFILE PAVEMENT MARKERS) | Handling Code: |
|
Limits From: | S FRTG RD OF IH 20 | Fund Cat: | 8 |
Limits To: | SH 36 | Estimate: | $104,520 |
Length: | 12.4 Miles | Actual: | $72,549 |
District: | Abilene | Let Date: | SEP 2014 |
Highway: | FM 821 | Let Status: | Actual |
Project ID: | STP 2015(052)HESG | CSJ: | 1156-02-020 |
Description: | TEXTURIZE SHOULDERS, CENTERLINE | Handling Code: |
|
Limits From: | GLASSCOCK CL | Fund Cat: | 8 |
Limits To: | S FRTG RD IH 20 | Estimate: | $367,190 |
Length: | 22.6 Miles | Actual: | $247,943 |
District: | Abilene | Let Date: | SEP 2014 |
Highway: | FM 600 | Let Status: | Actual |
Project ID: | STP 2015(053)HESG | CSJ: | 2032-02-012 |
Description: | TEXTURIZE SHOULDERS (PROFILE PAVEMENT MARKERS) | Handling Code: |
|
Limits From: | US 180 | Fund Cat: | 8 |
Limits To: | FM 1082E | Estimate: | $98,695 |
Length: | 11.2 Miles | Actual: | $68,506 |
Back... |
Totals for 0054-01-030 | ||
Length: | 79.0 Miles | ||
Estimate: | $993,774 | ||
Actual: | $618,929 | ||
CCSJ: 0407-06-040 | |||
District: | Abilene | Let Date: | JUN 2015 |
Highway: | US 277 | Let Status: | Actual |
Project ID: | STP 1502(291) | CSJ: | 0407-06-040 |
Description: | MILLING, SPOT BASE REPAIR, ASPHALT CONCRETE PAVEMENT OVERLAY | Handling Code: |
|
Limits From: | FM 3438 | Fund Cat: | 1 |
Limits To: | FM 707 | Estimate: | $3,728,561 |
Length: | 3.3 Miles | Actual: | $3,555,975 |
District: | Abilene | Let Date: | JUN 2015 |
Highway: | US 277 | Let Status: | Actual |
Project ID: | STP 1502(292) | CSJ: | 0407-06-042 |
Description: | MILLING, SPOT BASE REPAIR, ASPHALT CONCRETE PAVEMENT OVERLAY | Handling Code: |
|
Limits From: | FM 707 | Fund Cat: | 1 |
Limits To: | 0.2 MILES NORTH OF FM 1235 | Estimate: | $3,238,367 |
Length: | 3.3 Miles | Actual: | $2,954,613 |
Back... |
Totals for 0407-06-040 | ||
Length: | 6.6 Miles | ||
Estimate: | $6,966,928 | ||
Actual: | $6,510,588 | ||
CCSJ: 0663-03-027 | |||
District: | Abilene | Let Date: | APR 2015 |
Highway: | FM 1235 | Let Status: | Actual |
Project ID: | STP 2015(789)HES | CSJ: | 0663-03-027 |
Description: | REHABILITATE AND WIDEN EXISTING ROADWAY, INSTALL CORRUGATED | Handling Code: |
|
Limits From: | MERKEL CITY LIMIT | Fund Cat: | 8 |
Limits To: | CR 392 | Estimate: | $722,155 |
Length: | 2.3 Miles | Actual: | $926,787 |
District: | Abilene | Let Date: | APR 2015 |
Highway: | FM 1235 | Let Status: | Actual |
Project ID: | STP 2015(790)HES | CSJ: | 0663-03-029 |
Description: | EXTEND EXISTING STRUCTURES, WIDEN ROADWAY, ADD FLEX BASE, | Handling Code: |
|
Limits From: | 11.428 MILES NORTH OF US 277 | Fund Cat: | 8 |
Limits To: | 7.419 MILES NORTH OF US 277 | Estimate: | $1,397,077 |
Length: | 3.9 Miles | Actual: | $2,012,038 |
District: | Abilene | Let Date: | APR 2015 |
Highway: | FM 126 | Let Status: | Actual |
Project ID: | STP 2015(791)HES | CSJ: | 0733-03-053 |
Description: | EXTEND EXISTING STRUCTURES, WIDEN ROADWAY, ADD FLEX BASE, | Handling Code: |
|
Limits From: | 4.778 MILES NORTH OF FM 1085 | Fund Cat: | 8 |
Limits To: | 2.478 MILES NORTH OF FM 1085 | Estimate: | $552,514 |
Length: | 2.1 Miles | Actual: | $671,965 |
District: | Abilene | Let Date: | APR 2015 |
Highway: | FM 605 | Let Status: | Actual |
Project ID: | STP 2015(792)HES | CSJ: | 0975-01-020 |
Description: | EXTEND EXISTING STRUCTURES, WIDEN ROADWAY, ADD FLEX BASE, | Handling Code: |
|
Limits From: | FM 1235 | Fund Cat: | 8 |
Limits To: | FM 707 | Estimate: | $744,934 |
Length: | 2.7 Miles | Actual: | $941,310 |
Back... |
Totals for 0663-03-027 | ||
Length: | 11.0 Miles | ||
Estimate: | $3,416,680 | ||
Actual: | $4,552,100 | ||
CCSJ: 0908-00-079 | |||
District: | Abilene | Let Date: | APR 2015 |
Highway: | VA | Let Status: | Actual |
Project ID: | NH 2015(793) | CSJ: | 0908-00-079 |
Description: | INSTL NEW SFT LIGHT AT B120 - M / FM 1544;REM & REPLC SFT LIGHT | Handling Code: |
|
Limits From: | BI 20-M IN NOLAN COUNTY | Fund Cat: | 1 |
Limits To: | FM 700, AND SH 350 IN HOWARD COUNTY | Estimate: | $382,935 |
Length: | 1.0 Miles | Actual: | $402,152 |
Back... |
Totals for 0908-00-079 | ||
Length: | 1.0 Miles | ||
Estimate: | $382,935 | ||
Actual: | $402,152 | ||
CCSJ: 1655-01-026 | |||
District: | Abilene | Let Date: | APR 2015 |
Highway: | FM 1750 | Let Status: | Actual |
Project ID: | STP 2015(795) | CSJ: | 1655-01-026 |
Description: | SPOT REPAIR, SPOT LEVEL - UP, SEAL & 0VERLAY | Handling Code: |
|
Limits From: | NEAR LP 322 IN ABILENE | Fund Cat: | 1 |
Limits To: | NEAR MARIAH STREET IN POTOSI | Estimate: | $2,447,165 |
Length: | 5.0 Miles | Actual: | $2,294,680 |
District: | Abilene | Let Date: | APR 2015 |
Highway: | FM 1750 | Let Status: | Actual |
Project ID: | STP 2015(796)HES | CSJ: | 1655-01-027 |
Description: | INSTALL TRAFFIC SIGNAL | Handling Code: |
|
Limits From: | AT FM 707 | Fund Cat: | 8 |
Limits To: | . | Estimate: | $287,731 |
Length: | 0.2 Miles | Actual: | $377,510 |
Back... |
Totals for 1655-01-026 | ||
Length: | 5.2 Miles | ||
Estimate: | $2,734,896 | ||
Actual: | $2,672,190 |
|