Detail Letting Schedule for Archer County (FY 2016)
Archer County (FY 2016) |
CCSJ: 0156-05-056 | |||
District: | Wichita Falls | Let Date: | JAN 2016 |
Highway: | US 82 | Let Status: | Actual |
Project ID: | NH 2016(379) | CSJ: | 0156-05-056 |
Description: | 2" OVERLAY - REMAINING PAVEMENT STRUCT | Handling Code: |
|
Limits From: | 1.69 MI W OF FM 368 | Fund Cat: | 1 |
Limits To: | 0.795 MI E OF FERGUSON ROAD | Estimate: | $2,782,013 |
Length: | 9.2 Miles | Actual: | $2,475,815 |
District: | Wichita Falls | Let Date: | JAN 2016 |
Highway: | US 82 | Let Status: | Actual |
Project ID: | NH 2016(379) | CSJ: | 0156-06-054 |
Description: | REHABILITATION OF EXISTING ROADWAY | Handling Code: |
|
Limits From: | US 82 INTERCHANGE | Fund Cat: | 11 |
Limits To: | CR 621 (SIGNED 218) | Estimate: | $286,116 |
Length: | 1.7 Miles | Actual: | $276,807 |
District: | Wichita Falls | Let Date: | JAN 2016 |
Highway: | US 277 | Let Status: | Actual |
Project ID: | NH 2016(379) | CSJ: | 0157-01-072 |
Description: | REHABILITATION OF EXISTING ROADWAY | Handling Code: |
|
Limits From: | CR 718 (SIGNED 400) | Fund Cat: | 1 |
Limits To: | 0.16 MI N OF CR 718 (SIGNED 400) | Estimate: | $290,072 |
Length: | 0.9 Miles | Actual: | $281,789 |
District: | Wichita Falls | Let Date: | JAN 2016 |
Highway: | US 183 | Let Status: | Actual |
Project ID: | NH 2016(379) | CSJ: | 0562-08-001 |
Description: | REHABILITATION OF EXISTING ROADWAY | Handling Code: |
|
Limits From: | US 183 SOUTH OF SEYMOUR | Fund Cat: | 11 |
Limits To: | US 82 INTERCHANGE | Estimate: | $955,754 |
Length: | 4.0 Miles | Actual: | $926,766 |
District: | Wichita Falls | Let Date: | JAN 2016 |
Highway: | US 277 | Let Status: | Actual |
Project ID: | NH 2016(379) | CSJ: | 0562-08-002 |
Description: | REHABILITATION OF EXISTING ROADWAY | Handling Code: |
|
Limits From: | US 283 SOUTH OF SEYMOUR | Fund Cat: | 1 |
Limits To: | 1.6 MILES EAST OF FM 2395 | Estimate: | $266,892 |
Length: | 1.2 Miles | Actual: | $258,432 |
District: | Wichita Falls | Let Date: | JAN 2016 |
Highway: | RM 1919 | Let Status: | Actual |
Project ID: | STP 2016(380) | CSJ: | 1523-01-019 |
Description: | OVERLAY | Handling Code: |
|
Limits From: | FM 2582 | Fund Cat: | 1 |
Limits To: | US 82 INTERSECTION | Estimate: | $631,450 |
Length: | 3.4 Miles | Actual: | $591,917 |
Back... |
Totals for 0156-05-056 | ||
---|---|---|---|
Length: | 20.4 Miles | ||
Estimate: | $5,212,297 | ||
Actual: | $4,811,526 | ||
CCSJ: 0156-05-058 | |||
District: | Wichita Falls | Let Date: | JUN 2016 |
Highway: | US 82 | Let Status: | Actual |
Project ID: | NH 1602(200) | CSJ: | 0156-05-058 |
Description: | MILL AND INLAY | Handling Code: |
|
Limits From: | 0.54 MILES WEST OF BU 82F | Fund Cat: | 11 |
Limits To: | BU 82F | Estimate: | $331,517 |
Length: | 0.5 Miles | Actual: | $234,323 |
District: | Wichita Falls | Let Date: | JUN 2016 |
Highway: | US 82 | Let Status: | Actual |
Project ID: | NH 1602(200) | CSJ: | 0156-16-020 |
Description: | MILL AND INLAY | Handling Code: |
|
Limits From: | ARCHER COUNTY LINE | Fund Cat: | 11 |
Limits To: | 0.407 MILES EAST OF ARCHER CO. LINE | Estimate: | $254,908 |
Length: | 0.4 Miles | Actual: | $252,041 |
District: | Wichita Falls | Let Date: | JUN 2016 |
Highway: | US 82 | Let Status: | Actual |
Project ID: | NH 1602(200) | CSJ: | 0156-17-028 |
Description: | MILL AND INLAY | Handling Code: |
|
Limits From: | BU 82F WEST OF HOLLIDAY | Fund Cat: | 11 |
Limits To: | WICHITA COUNTY LINE | Estimate: | $1,274,808 |
Length: | 3.4 Miles | Actual: | $1,274,833 |
Back... |
Totals for 0156-05-058 | ||
Length: | 4.3 Miles | ||
Estimate: | $1,861,233 | ||
Actual: | $1,761,197 |
|