Detail Letting Schedule for Callahan County (FY 2016)

Last Update: Thursday, August 20, 2015
Callahan County (FY 2016)

CCSJ: 0006-07-076

District: Abilene Let Date: JAN 2016
Highway: IH 20 Let Status: Tentative
Project ID: BR ( ) CSJ: 0006-07-076
Description: REPLACE BRIDGE AND APPROACH RAILING OR Handling
Code:
 
Limits From: AT DRAW (IH 20 ML) Fund Cat: 6
Limits To: 1.00 MI E OF TAYLOR C/L Estimate: $53,040
Length: 0.1 Miles Actual:  
 
District: Abilene Let Date: JAN 2016
Highway: IH 20 Let Status: Tentative
Project ID: BR ( ) CSJ: 0006-07-077
Description: REPLACE BRIDGE AND APPROACH RAILING OR Handling
Code:
 
Limits From: AT DRAW (IH 20 ML & NFR) Fund Cat: 6
Limits To: 7.80 MI E OF TAYLOR CO/L Estimate: $43,996
Length: 0.1 Miles Actual:  
 
District: Abilene Let Date: JAN 2016
Highway: BI 20-R Let Status: Tentative
Project ID: BR ( ) CSJ: 0006-18-056
Description: REPLACE BRIDGE AND APPROACH RAILING OR Handling
Code:
 
Limits From: AT MOORE SLOUGH Fund Cat: 6
Limits To: 0.70 MI E OF US 83 Estimate: $60,656
Length: 0.1 Miles Actual:  
 
District: Abilene Let Date: JAN 2016
Highway: BI 20-R Let Status: Tentative
Project ID: BR ( ) CSJ: 0006-18-057
Description: REPLACE BRIDGE AND APPROACH RAILING OR Handling
Code:
 
Limits From: AT BIG ELM CREEK Fund Cat: 6
Limits To: 1.00 MI E OF US 83 Estimate: $86,836
Length: 0.1 Miles Actual:  
 
Back...

Totals for 0006-07-076
Length: 0.4 Miles
Estimate: $244,528
Actual:  


Handling Code Definition
XX Project not processed through statewide letting
TR Transfer of funds
LC Project let through local entity
NC Project not charged against district apportionment



Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract