Detail Letting Schedule for Goliad County (FY 2016)

Last Update: Tuesday, May 26, 2015
Goliad County (FY 2016)

CCSJ: 0155-03-037

District: Corpus Christi Let Date: MAY 2016
Highway: US 183 Let Status: Tentative
Project ID: BR 1502(573) CSJ: 0155-03-037
Description: BRIDGE REPLACEMENT Handling
Code:
 
Limits From: ON US 183 STR5 AT MANAHUILLA CREEK Fund Cat: 6
Limits To: 2.3 MI. N. OF US 59 Estimate: $3,220,000
Length: 0.1 Miles Actual:  
 
Back...

Totals for 0155-03-037
Length: 0.1 Miles
Estimate: $3,220,000
Actual:  

CCSJ: 0155-04-051

District: Corpus Christi Let Date: SEP 2015
Highway: US 183 Let Status: Approved
Project ID: STP 2015(887) CSJ: 0155-04-051
Description: MILL AND INLAY Handling
Code:
 
Limits From: FRANKLIN ST. Fund Cat: 1
Limits To: SH 239 Estimate: $2,169,516
Length: 2.3 Miles Actual:  
 
Back...

Totals for 0155-04-051
Length: 2.3 Miles
Estimate: $2,169,516
Actual:  

CCSJ: 0943-04-033

District: Corpus Christi Let Date: FEB 2016
Highway: FM 622 Let Status: Tentative
Project ID: STP ( )HES CSJ: 0943-04-033
Description: TEXTURIZE SHOULDERS (ROLL OR MILL IN) , CENTERLINE TEXTURING Handling
Code:
 
Limits From: US 183 Fund Cat: 8
Limits To: VICTORIA COUNTY LINE Estimate: $224,902
Length: 15.2 Miles Actual:  
 
Back...

Totals for 0943-04-033
Length: 15.2 Miles
Estimate: $224,902
Actual:  


Handling Code Definition
XX Project not processed through statewide letting
TR Transfer of funds
LC Project let through local entity
NC Project not charged against district apportionment



Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract