Letting Schedule for Abilene District (FY 2016)
Abilene District (FY 2016) |
Callahan | Howard | Jones | Mitchell | Nolan | Scurry | Shackelford | Stonewall | Taylor | ||||||
Callahan County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
---|---|---|---|---|---|---|
0006-07-076 | IH 20 | Actual | JAN 2016 | $249,107 | 6 | REPAIR CULVERT SAFETY END TREATMENTS |
0181-02-029 | SH 36 | Actual | FEB 2016 | $5,388,974 | 1 | SPOT BASE REPAIR, ASPHALT CONCRETE PAVEMENT LEVEL UP & |
Howard County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0005-10-021 | BI 20-G | Actual | OCT 2015 | $3,396,196 | 1 | SEAL COAT |
0558-04-021 | FM 669 | Actual | SEP 2015 | $130,267 | 8 | TEXTURIZE SHOULDERS (PROFILE PAVEMENT MARKERS) |
Jones County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0033-04-065 | US 83 | Actual | OCT 2015 | $4,425,889 | 1 | PLANE EXISTING SURFACE, PAVEMENT REPAIR, UNDERSEAL AND |
0107-01-036 | SH 6 | Actual | NOV 2015 | $5,991,843 | 1 | SEAL COAT |
2721-02-013 | FM 3116 | Actual | AUG 2016 | $1,045,833 | 1 | REPLACE BRIDGE AND APPROACHES |
Mitchell County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0454-03-041 | SH 208 | Actual | OCT 2015 | $2,654,057 | 1 | SPOT REPAIR, UNDERSEAL & OVERLAY |
2331-01-014 | FM 2836 | Actual | DEC 2015 | $1,445,915 | 6 | REPLACE BRIDGE AND APPROACHES |
Nolan County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0006-02-112 | IH 20 | Actual | APR 2016 | $3,498,755 | 8 | HIGH FRICTION COURSE SURFACE TREATMENT, PLANE AND |
Scurry County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
1526-03-015 | FM 1606 | Actual | FEB 2016 | $6,876,410 | 1 | REHABILITATION AND WIDENING OF EXISTING ROADWAY |
1531-02-012 | FM 1610 | Actual | FEB 2016 | $5,397,846 | 1 | RESTORATION AND WIDEN EXISTING ROADWAY |
Shackelford County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0011-06-045 | US 180 | Actual | AUG 2016 | $467,416 | 8 | INSTALL INTERSECTION FLASHING BEACON. |
Stonewall County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0106-04-034 | US 380 | Actual | FEB 2016 | $695,243 | 8 | HIGH FRICTION SURFACE TREATMENT AND |
Taylor County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0006-05-114 | IH 20 | Actual | AUG 2016 | $258,629 | 8 | INSTALL ADVANCE WARNING SIGNS (CURVE) , AND CHEVRONS (CURVE) |
0006-18-055 | US 84 | Actual | APR 2016 | $2,371,863 | 1 | SPOT REPAIR, MILL & OVERLAY |
0033-08-038 | BU 83-D | Actual | APR 2016 | $9,806,711 | 1 | PLANING, PAVEMENT STRUCTURE REPAIR, UNDERESEAL, ASPHALT |
0054-01-031 | US 84 | Actual | APR 2016 | $7,380,051 | 1 | SPOT REPAIR, SEAL & OVERLAY |
0407-05-025 | US 277 | Actual | SEP 2015 | $192,277 | 8 | TEXTURIZE SHOULDERS (ROLLED IN OR MILLED IN) , CENTERLINE |
0908-00-080 | VA | Actual | FEB 2016 | $448,261 | 1 | INSTALL HIGH MAST ILLUMINATION AT US84 / US380, KENT;US84 / ENNIS |
0908-33-093 | CS | Actual | MAY 2016 | $901,259 | 3 | PROVIDES CORRIDOR ENHANCEMENT FOR WALKING / BIKING BY |
|