Collin County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0091-05-059 SH 289 Tentative JUL 2016 $3,153,023 5 WIDEN BRIDGE TO PROVIDE 2 LEFT TURN LANES FOR PGBT ENTRANCE
0918-24-184 VA Tentative AUG 2016 $2,500,000 7 WIDEN FRONTAGE ROADS FROM 2 TO 3 LANES AND INTERSECTION
0918-24-202 CS Tentative AUG 2016 $255,900 5 ADD 2 EASTBOUND DEDICATED LEFT TURN LANES ON MAIN STREET

Dallas County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0092-02-122 SH 310 Tentative AUG 2016 $167,007 8 IMPROVE GUARDRAIL TO DESIGN STANDARDS
0094-03-117 SS 482 Tentative AUG 2016 $68,634 8 INSTALL PROTECTION
0442-02-158 IH 35E Tentative AUG 2016 $144,000 8 IMPROVE TRAFFIC SIGNALS
0581-02-144 SL 12 Tentative AUG 2016 $244,000 8 IMPROVE TRAFFIC SIGNALS
0918-00-182 VA Tentative JUL 2016 $300,000 1 REFURBISH ITS EQUIPMENT
0918-00-215 VA Tentative JUL 2016 $3,500,000 7 PROVIDE ASSISTANCE TO STRANDED MOTORISTS OR NON INJURY
0918-00-216 VA Tentative JUL 2016 $280,000 7 DEPARTMENTAL STREAMLINING POLICIES AND PROCEDURES
0918-00-217 VA Tentative JUL 2016 $4,150,000 7 REGIONAL TRIP REDUCTION PROGRAM, VANPOOL PGM, BIKE / PEDESTRIAN
0918-00-254 VA Tentative AUG 2016 $2,500,000 5 IDLE REDUCTION & OTH EMISSIONS REDUCTION TECHNOLOGIES;INCEN -
0918-47-070 CS Tentative AUG 2016 $343,020 5 CONSTRUCT BICYCLE LINK FOR CARROLLTON TRANSIT DISTRICT
0918-47-120 CS Tentative AUG 2016 $518,000 8 IMPROVE TRAFFIC SIGNALS
0918-47-123 CS Tentative AUG 2016 $255,000 8 IMPROVE TRAFFIC SIGNALS
0918-47-124 CS Tentative AUG 2016 $245,000 8 IMPROVE TRAFFIC SIGNALS
0918-47-125 CS Tentative AUG 2016 $276,000 8 IMPROVE TRAFFIC SIGNALS
0918-47-127 CS Tentative AUG 2016 $258,000 8 IMPROVE TRAFFIC SIGNALS
1047-03-068 FM 1382 Tentative JUL 2016 $600,000 3 INTERSECTION IMPROVEMENTS - CONSTRUCT TURNING LANES
2374-01-178 IH 635 Tentative AUG 2016 $748,000 8 IMPROVE TRAFFIC SIGNALS
2374-04-049 IH 20 Tentative AUG 2016 $22,744,669 3 CONSTRUCT 0 TO 6 LANE FRONTAGE ROADS AND RAMP MODIFICATIONS

Denton County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0081-03-058 US 377 Tentative AUG 2016 $175,000 8 IMPROVE TRAFFIC SIGNALS
0081-03-059 US 377 Tentative AUG 2016 $200,000 8 INSTALL RAISED MEDIAN
0918-46-267 CS Tentative AUG 2016 $471,120 5 DENTON SCHOOL CONNECTION SIDEWALKS; NEW SIDEWALK SEGMENTS
0918-46-281 CS Tentative AUG 2016 $2,000,000 3 DESIGN AND CONSTRUCT ROUNDABOUT

Ellis County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
1051-01-037 FM 664 Tentative JUL 2016 $30,050,000 1 WIDEN FROM 2 LANES TO 6 LANES URBAN DIVIDED, INCLUDING


Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract