Letting Schedule for El Paso District (FY 2016)

Last Update: Tuesday, September 2, 2014
El Paso District (FY 2016)
El Paso | Hudspeth

El Paso County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0001-01-056 SH 20 Tentative MAR 2016 $1,241,154 8 INSTALL RAISED MEDIAN
0002-01-093 SH 20 Tentative AUG 2016 $1,250,000 3 PEDESTRIAN ENHANCEMENTS TO INCLUDE INSTALLATION OF SIDEWALKS
0002-14-039 FM 258 Tentative MAR 2016 $1,837,418 8 INSTALL CONTINUOUS TURN LANE, WIDEN PAVED SHOULDERS (>5)
0924-00-089 VA Tentative FEB 2016 $750,000 1 FY 2016 STRIPING PROJECT
0924-00-091 VA Tentative FEB 2016 $750,000 1 FY 2016 BRIDGE MAINTENANCE PROGRAM
0924-00-096 VA Tentative FEB 2016 $750,000 1 METAL BEAM GUARD FENCE AND SGT UPGRADES
0924-06-111 CS Tentative JUN 2016 $12,000,000 3 CONSTRUCT NEW 4 LANE RAISED MEDIAN DIVIDED URBAN COLLECTOR
0924-06-450 VA Tentative JUN 2016 $1,500,000 10 CONSTRUCT CURB RAMPS AT VARIOUS LOCATIONS IN CLINT, EL PASO,
0924-06-457 CS Tentative AUG 2016 $5,316,808 3 WIDEN ROADWAY TO 4 LANE
0924-06-473 CS Tentative MAY 2016 $765,873 3 PEDESTRAIN BRIDGE AT RR XING
0924-06-491 VA Tentative AUG 2016 $539,000 11 REGIONAL BIKE IMPROVEMENTS (ON STATE)
0924-06-499 VA Tentative JUN 2016 $4,000,000 3 WIDEN FROM 4 TO 6 LANES DIVIDED
0924-06-500 VA Tentative AUG 2016 $22,850,000 3 WIDEN FROM 4 TO 6 LANES DIVIDED
0924-06-501 VA Tentative JUN 2016 $5,650,000 3 CONSTRUC AND UPGRADE TO 4 LANE DIVIDED ARTERIAL
2121-02-157 IH 10 Tentative JUN 2016 $2,500,000 11 OVERHEAD SIGN BRIDGES
2121-03-131 IH 10 Tentative AUG 2016 $25,000,000 7 INTERCHANGE IMPROVEMENTS

Hudspeth County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0002-05-044 IH 10 Tentative JAN 2016 $2,863,071 8 TEXTURIZE SHOULDERS (PROFILE PAVEMENT MARKERS)


Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract