Letting Schedule for March, 2016 (FY 2016)

Last Update: Thursday, February 11, 2016
March, 2016 (FY 2016) (see Links)
SEP 2015 | OCT 2015 | NOV 2015 | DEC 2015 | JAN 2016 | FEB 2016 | MAR 2016 | APR 2016 | MAY 2016 | JUN 2016 | JUL 2016 | AUG 2016
CCSJ County/
District
Highway Let Status Contract
Cost
Fund
Cat
Description
0910-08-063 Anderson/
Tyler
PW Approved $374,993 10 REPAIR BRIDGES & REPLACE VARIOUS DRAINAGE CULVERTS
0176-13-006 Angelina/
Lufkin
FM 3439 Approved $458,825 1 RECONSTRUCT AND WIDEN PAVEMENT
0265-03-040 Bastrop/
Austin
SH 71 Approved $552,288 6 UPGRADE BRIDGE AND APPROACH RAILING
1117-01-015 Bee/
Corpus Christi
FM 798 Approved $4,694,348 1 WIDEN ROADWAY
0017-10-270 Bexar/
San Antonio
IH 35 Approved $7,089,630 1 MILL, SEAL COAT, OVERLAY AND PAVEMENT MARKINGS
0976-02-091 Brazoria/
Houston
FM 518 Approved $6,688,463 1 PAVEMENT REPAIR AND 1.5" ACP OVERLAY
0054-07-082 Brown/
Brownwood
US 67 Approved $955,178 1 SEAL COAT
0471-04-029 Caldwell/
Austin
SH 21 Approved $2,498,524 1 WIDEN AND REHABILITATE ROADWAY
0331-01-044 Cameron/
Pharr
SH 100 Approved $6,133,726 1 INSTALL WILDLIFE CROSSINGS
0925-00-064 Childress/
Childress
VA Approved $982,935 1 DISTRICT WIDE STRIPING
0044-02-096 Clay/
Wichita Falls
US 82 Approved $468,280 1 ILLUMINATION UPGRADE
0047-04-024 Collin/
Dallas
SH 5 Approved $4,118,617 1 MILL, BASE REPAIR, OVERLAY
1013-01-026 Collin/
Dallas
FM 546 Approved $20,205,619 3 REALIGN HIGHWAY - CONSTRUCT FOUR LANE DIVIDED FACILITY
0845-03-060 Cooke/
Wichita Falls
FM 922 Approved $246,830 1 REALIGN INTERSECTION
0231-02-058 Coryell/
Waco
US 190 Approved $3,061,869 3 MILL / INLAY
0141-01-053 Crockett/
San Angelo
IH 10 Approved $6,400,000 1 OVERLAY
0095-02-119 Dallas/
Dallas
US 80 Approved $2,990,825 1 DEPRESS ROADWAY
0237-04-013 Duval/
Laredo
SH 44 Approved $4,691,379 1 REHABILITATION OF EXISTING HIGHWAY
0906-00-153 Ector/
Odessa
VA Approved $956,578 1 PAVEMENT MARKINGS
0906-00-171 Ector/
Odessa
VA Approved $637,911 1 PAVEMENT MARKINGS
0057-05-028 Freestone/
Bryan
US 84 Approved $3,981,304 1 OVERLAY CONSISTING OF PLANING, HMA OVERLAY AND PAVEMENT
0917-17-062 Grimes/
Bryan
CR Approved $487,271 6 REPLACE EXISTING BRIDGE FACILITY CONSISTING OF GRADING,
0500-03-580 Harris/
Houston
IH 45 Approved $6,153,347 1 FAST TRACK CONCRETE PAVEMENT, CONCRETE CURB AND SIDEWALK
0528-01-100 Hidalgo/
Pharr
SH 107 Approved $2,119,217 1 REHABILITATE EXISTING ROADWAY
0921-02-325 Hidalgo/
Pharr
CS Approved $1,020,265 3 CONSTRUCT BENSTSEN ROAD HIKE & BIKE TRAIL
0080-03-054 Hood/
Fort Worth
US 377 Approved $4,682,149 1 BASE REPAIR, SEAL COAT AND HMAC OVERLAY
0009-09-101 Hopkins/
Paris
IH 30 Approved $2,448,229 1 OVERLAY
0495-01-070 Kaufman/
Dallas
IH 20 Approved $3,433,864 6 INSTALL CABLE BARRIER SYSTEM IN MEDIAN
2003-01-008 Lamar/
Paris
FM 2122 Approved $774,049 1 PROVIDE ADDITIONAL PAVED SURFACE WIDTH
0211-03-036 Lee/
Austin
US 77 Approved $951,177 1 LEVEL - UP SEAL COAT & OVERLAY
0783-01-100 Lubbock/
Lubbock
SL 289 Approved $209,468 1 REHABILITATION OF EXISTING ROAD
0258-09-139 McLennan/
Waco
SH 6 Approved $12,599,037 6 MILL, SEAL AND INLAY
1259-01-041 Montgomery/
Houston
FM 1097 Approved $206,154 8 INSTALL LED FLASHING CHEVRONS (CURVE)
0617-01-190 Nueces/
Corpus Christi
SH 358 Approved $4,796,641 1 NOVACHIP
0916-00-082 Nueces/
Corpus Christi
VA Approved $1,045,045 1 DISTRICT WIDE SMALL SIGN REPLACEMENT - PLANNING CSJ
2263-03-041 Nueces/
Corpus Christi
SH 361 Approved $5,947,667 4 CONSTRUCT 4 LANE ROADWAY WITH RAISED MEDIAN, HIKE / BIKE PATH
0009-04-061 Rockwall/
Dallas
SH 66 Approved $18,924,147 1 PROVIDE ADDITIONAL PAVED SURFACE WIDTH
0372-01-096 San Patricio/
Corpus Christi
US 77 Approved $2,971,268 1 MILL, SEAL AND OVERLAY NB & SB LANES
0810-02-019 Shelby/
Lufkin
FM 417 Approved $5,360,286 1 RECONSTRUCT AND WIDEN PAVEMENT
0165-01-101 Smith/
Tyler
US 271 Approved $4,507,976 1 PLANE, REPAIR, RESURF RDWY & BRIDGE, REPAIR & SEAL BRG JOINTS
0495-05-049 Smith/
Tyler
IH 20 Approved $1,840,103 1 RESURFACE ROADWAY - OMIT CONCRETE PVMT
0910-16-131 Smith/
Tyler
CR Approved $950,003 6 REPLACE BRIDGE AND APPROACHES
0038-07-058 Starr/
Pharr
US 83 Approved $1,720,127 11 CONSTRUCT DRAINAGE OUTFALL FOR US 83 PHASE I TRUNK SYSTEM
0008-06-050 Tarrant/
Fort Worth
SH 180 Approved $4,485,952 1 MILL, BASE REPAIR, HMAC OVERLAY
0908-33-093 Taylor/
Abilene
CS Approved $1,182,775 3 PROVIDES CORRIDOR ENHANCEMENT FOR WALKING / BIKING BY
0152-01-078 Travis/
Austin
US 183 Approved $344,175 3 WIDEN BRIDGE AND INSTALL LEFT TURN LANE
0914-00-369 Travis/
Austin
VA Approved $1,697,373 1 FY 2016 NON - SITE SPECIFIC SIGNALS
1186-01-089 Travis/
Austin
FM 969 Approved $2,665,580 1 MILL, SEAL & TY D OVERLAY
3277-01-022 Travis/
Austin
FM 3177 Approved $2,141,816 3 CONSTRUCT SIDEWALKS
0036-07-032 Uvalde/
San Antonio
US 83 Approved $1,227,710 8 PLACE INVERTED PROFILE PAVEMENT MARKINGS ALONG EDGELINES
0910-12-034 Van Zandt/
Tyler
CR Approved $1,316,286 6 REPLACE BRIDGE AND APPROACHES
0913-27-065 Victoria/
Yoakum
CR Approved $380,819 6 REPLACE BRIDGE AND APPROACHES
0044-01-103 Wichita/
Wichita Falls
US 82 Approved $1,494,849 1 UPGRADE ROADWAY ILLUMINATION
0320-03-093 Williamson/
Austin
SH 95 Approved $1,499,078 3 CONSTRUCT PEDESTRIAN AND BIKE PATH
1378-02-048 Williamson/
Austin
RM 1431 Approved $311,483 3 CONSTRUCT SIDEWALK & PEDESTRIAN BRIDGE
1566-01-014 Williamson/
Austin
FM 1660 Approved $1,252,350 3 CONSTRUCT PEDESTRIAN AND BIKE PATH
0312-03-030 Wise/
Fort Worth
FM 51 Approved $6,930,761 1 2" HMAC OVERLAY - LANES AND SHOULDERS_W / RUMBLE STRIPS


Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract