Detail Letting Schedule for Smith County (FY 2016)

Last Update: Tuesday, September 2, 2014
Smith County (FY 2016)

CCSJ: 0191-01-084

District: Tyler Let Date: FEB 2016
Highway: US 69 Let Status: Tentative
Project ID: STP ( ) CSJ: 0191-01-084
Description: CONSTRUCT RIGHT TURN LANE ON SB LANES Handling
Code:
 
Limits From: 1.05 MI N OF FM 344, S Fund Cat: 1
Limits To: .5 MI N OF FM 344(LYNCH),IN BULLARD Estimate: $466,000
Length: 0.5 Miles Actual:  
 
Back...

Totals for 0191-01-084
Length: 0.5 Miles
Estimate: $466,000
Actual:  

CCSJ: 0910-16-120

District: Tyler Let Date: JAN 2016
Highway: PW Let Status: Tentative
Project ID: C 910-16-120 CSJ: 0910-16-120
Description: CONSTRUCT NEW ENTRANCE ROAD & PARKING Handling
Code:
 
Limits From: WITHIN TYLER STATE PARK Fund Cat: 10
Limits To: . Estimate: $905,036
Length: 1.0 Miles Actual:  
 
Back...

Totals for 0910-16-120
Length: 1.0 Miles
Estimate: $905,036
Actual:  


Handling Code Definition
XX Project not processed through statewide letting
TR Transfer of funds
LC Project let through local entity
NC Project not charged against district apportionment



Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract