Detail Letting Schedule for Live Oak County (FY 2017)

Last Update: Monday, October 16, 2017
Live Oak County (FY 2017)

CCSJ: 0073-07-063

District:CORPUS CHRISTILet Date:Jan 2017
Highway:IH 37Let Status:Actual
Project ID:STP 1602(446)HESCSJ:0073-07-063
Description:INSTALL MEDIAN BARRIERHandling
Code:
 
Limits From:3.022 MI S OF ATASCOSA CO LINEFund Cat:8
Limits To:ATASCOSA CO LINEESTIMATE:$599,985
Length:3.0Actual$421,488
 
District:CORPUS CHRISTILet Date:Jan 2017
Highway:IH 37Let Status:Actual
Project ID:STP 1602(447)CSJ:0074-01-053
Description:INSTALL MEDIAN BARRIERHandling
Code:
 
Limits From:.883 MI N. OF US 59Fund Cat:11
Limits To:2.198 MI N. OF US 59ESTIMATE:$251,677
Length:1.3Actual$192,664
 
District:CORPUS CHRISTILet Date:Jan 2017
Highway:IH 37Let Status:Actual
Project ID:STP 1602(447)CSJ:0074-02-077
Description:INSTALL MEDIAN BARRIERHandling
Code:
 
Limits From:US 59Fund Cat:11
Limits To:.883 MI N. OF US 59ESTIMATE:$148,398
Length:0.9Actual$114,010
 
Bid Tabulations
Back...
Totals for 0073-07-063
Length:5.2
Estimate:$1,000,060
Actual:$728,163

CCSJ: 0074-02-079

District:CORPUS CHRISTILet Date:Oct 2016
Highway:IH 37Let Status:Actual
Project ID:NH 2017(219)CSJ:0074-02-079
Description:2017 DISTRICT WIDE SEAL COAT PROJECT LOW CONTROL CSJHandling
Code:
 
Limits From:LIVE OAK COUNTY LINEFund Cat:1
Limits To:FM 888ESTIMATE:$168,069
Length:0.8Actual$17,593
 
District:CORPUS CHRISTILet Date:Oct 2016
Highway:IH 37Let Status:Actual
Project ID:NH 2017(219)CSJ:0074-03-045
Description:2017 DISTRICT WIDE SEAL COAT PROJECT (FTGR)Handling
Code:
 
Limits From:SH 359Fund Cat:1
Limits To:LIVE OAK COUNTY LINEESTIMATE:$86,317
Length:3.4Actual$69,852
 
District:CORPUS CHRISTILet Date:Oct 2016
Highway:IH 37Let Status:Actual
Project ID:NH 2017(219)CSJ:0074-03-046
Description:2017 DISTRICT WIDE SEAL COAT PROJECT (FTGR)Handling
Code:
 
Limits From:CONTROL BREAKFund Cat:1
Limits To:CR 803ESTIMATE:$18,007
Length:0.6Actual$14,395
 
District:CORPUS CHRISTILet Date:Oct 2016
Highway:IH 37Let Status:Actual
Project ID:NH 2017(219)CSJ:0074-04-044
Description:2017 DISTRICT WIDE SEAL COAT PROJECT (FTGR)Handling
Code:
 
Limits From:SH 188Fund Cat:1
Limits To:CONTROL BREAKESTIMATE:$79,448
Length:3.0Actual$64,453
 
District:CORPUS CHRISTILet Date:Oct 2016
Highway:FM 665Let Status:Actual
Project ID:STP 2017(220)CSJ:0086-19-032
Description:2017 DISTRICT WIDE SEAL COAT PROJECTHandling
Code:
 
Limits From:FM 1931Fund Cat:1
Limits To:NUECES COUNTY LINEESTIMATE:$223,567
Length:6.6Actual$181,848
 
District:CORPUS CHRISTILet Date:Oct 2016
Highway:SH 359Let Status:Actual
Project ID:NH 2017(219)CSJ:0087-01-108
Description:2017 DISTRICT WIDE SEAL COAT ROADWAY PROJECTHandling
Code:
 
Limits From:SH 44Fund Cat:1
Limits To:CR 324ESTIMATE:$258,031
Length:5.6Actual$226,598
 
District:CORPUS CHRISTILet Date:Oct 2016
Highway:US 181Let Status:Actual
Project ID:NH 2017(219)CSJ:0100-08-096
Description:2017 DISTRICT WIDE SEAL COAT PROJECTHandling
Code:
 
Limits From:1372.8' N OF FM3355Fund Cat:1
Limits To:BU 181-JESTIMATE:$523,015
Length:6.1Actual$414,685
 
District:CORPUS CHRISTILet Date:Oct 2016
Highway:BU 181JLet Status:Actual
Project ID:STP 2017(220)CSJ:0100-13-025
Description:2017 DISTRICT WIDE SEAL COAT ROADAWAYHandling
Code:
 
Limits From:US 181 (NORTH BYPASS)Fund Cat:1
Limits To:ENCINO LOMAS ST.ESTIMATE:$89,939
Length:1.8Actual$78,503
 
District:CORPUS CHRISTILet Date:Oct 2016
Highway:SH 72Let Status:Actual
Project ID:STP 2017(220)CSJ:0270-03-077
Description:2017 DISTRICT WIDE SEAL COAT PROJECTHandling
Code:
 
Limits From:SH 239Fund Cat:1
Limits To:DEWITT COUNTY LINEESTIMATE:$538,346
Length:11.8Actual$469,924
 
District:CORPUS CHRISTILet Date:Oct 2016
Highway:SH 72Let Status:Actual
Project ID:STP 2017(220)CSJ:0270-09-029
Description:2017 DISTRICT WIDE SEAL COAT ROADWAYHandling
Code:
 
Limits From:US 281Fund Cat:1
Limits To:IH 37ESTIMATE:$162,389
Length:2.6Actual$140,701
 
District:CORPUS CHRISTILet Date:Oct 2016
Highway:FM 99Let Status:Actual
Project ID:STP 2017(220)CSJ:0348-11-016
Description:2017 DISTRICT WIDE SEAL COAT ROADWAYHandling
Code:
 
Limits From:ATASCOSA COUNTY LINEFund Cat:1
Limits To:IH 37ESTIMATE:$197,218
Length:6.2Actual$170,430
 
District:CORPUS CHRISTILet Date:Oct 2016
Highway:FM 99Let Status:Actual
Project ID:STP 2017(220)CSJ:0348-12-012
Description:2017 DISTRICT WIDE SEAL COAT PROJECTHandling
Code:
 
Limits From:US 281AFund Cat:1
Limits To:MCMULLEN COUNTY LINEESTIMATE:$162,056
Length:5.0Actual$139,145
 
District:CORPUS CHRISTILet Date:Oct 2016
Highway:SH 119Let Status:Actual
Project ID:STP 2017(220)CSJ:0359-02-020
Description:2017 DISTRICT WIDE SEAL COAT PROJECTHandling
Code:
 
Limits From:DEWITT COUNTY LINEFund Cat:1
Limits To:US 183ESTIMATE:$209,506
Length:8.1Actual$169,319
 
District:CORPUS CHRISTILet Date:Oct 2016
Highway:IH 69ELet Status:Actual
Project ID:NH 2017(219)CSJ:0373-01-105
Description:2017 DISTRICT WIDE SEAL COAT PROJECTHandling
Code:
 
Limits From:I69 AND IH37 INTERCHANGEFund Cat:1
Limits To:CR 52 (NB & SB FRTG LANES)ESTIMATE:$128,553
Length:1.7Actual$100,043
 
District:CORPUS CHRISTILet Date:Oct 2016
Highway:FM 774Let Status:Actual
Project ID:STP 2017(220)CSJ:0447-05-069
Description:2017 DISTRICT WIDE SEAL COAT PROJECTHandling
Code:
 
Limits From:SH 35Fund Cat:1
Limits To:SH 239ESTIMATE:$243,912
Length:10.4Actual$197,173
 
District:CORPUS CHRISTILet Date:Oct 2016
Highway:SH 188Let Status:Actual
Project ID:STP 2017(220)CSJ:0507-03-043
Description:2017 DISTRICT WIDE SEAL COAT PROJECTHandling
Code:
 
Limits From:CONTROL SECTION BREAKFund Cat:1
Limits To:FM 136ESTIMATE:$35,901
Length:0.9Actual$29,302
 
District:CORPUS CHRISTILet Date:Oct 2016
Highway:SH 188Let Status:Actual
Project ID:STP 2017(220)CSJ:0507-03-044
Description:2017 DISTRICT WIDE SEAL COAT PROJECTHandling
Code:
 
Limits From:SH 89Fund Cat:1
Limits To:FM 631ESTIMATE:$261,747
Length:6.4Actual$214,531
 
District:CORPUS CHRISTILet Date:Oct 2016
Highway:SH 188Let Status:Actual
Project ID:STP 2017(220)CSJ:0507-04-044
Description:2017 DISTRICT WIDE SEAL COAT PROJECTHandling
Code:
 
Limits From:FM 1069Fund Cat:1
Limits To:CONTROL SECTION BREAKESTIMATE:$264,301
Length:6.4Actual$216,819
 
District:CORPUS CHRISTILet Date:Oct 2016
Highway:FM 81Let Status:Actual
Project ID:STP 2017(220)CSJ:0691-01-039
Description:2017 DISTRICT WIDE SEAL COAT PROJECTHandling
Code:
 
Limits From:SH 80Fund Cat:1
Limits To:FM 2773ESTIMATE:$235,305
Length:8.3Actual$190,531
 
District:CORPUS CHRISTILet Date:Oct 2016
Highway:FM 623Let Status:Actual
Project ID:STP 2017(220)CSJ:0988-04-009
Description:2017 DISTRICT WIDE SEAL COAT PROJECTHandling
Code:
 
Limits From:FM 1358Fund Cat:1
Limits To:BEE COUNTY LINEESTIMATE:$41,052
Length:1.6Actual$32,875
 
District:CORPUS CHRISTILet Date:Oct 2016
Highway:FM 623Let Status:Actual
Project ID:STP 2017(220)CSJ:0988-05-010
Description:2017 DISTRICT WIDE SEAL COAT PROJECTHandling
Code:
 
Limits From:LIVE OAK COUNTY LINEFund Cat:1
Limits To:FM 673 INTERS.ESTIMATE:$175,080
Length:7.0Actual$140,705
 
District:CORPUS CHRISTILet Date:Oct 2016
Highway:FM 624Let Status:Actual
Project ID:STP 2017(220)CSJ:0989-02-055
Description:2017 DISTRICT WIDE SEAL COAT PROJECTHandling
Code:
 
Limits From:CR 95Fund Cat:1
Limits To:FM 666ESTIMATE:$143,429
Length:2.7Actual$124,853
 
District:CORPUS CHRISTILet Date:Oct 2016
Highway:FM 665Let Status:Actual
Project ID:STP 2017(220)CSJ:1052-02-083
Description:2017 DISTRICT WIDE SEAL COAT PROJECTHandling
Code:
 
Limits From:SH 357Fund Cat:1
Limits To:SH 44ESTIMATE:$271,137
Length:4.8Actual$225,622
 
District:CORPUS CHRISTILet Date:Oct 2016
Highway:FM 665Let Status:Actual
Project ID:STP 2017(220)CSJ:1052-02-084
Description:2017 DISTRICT WIDE SEAL COAT PROJECTHandling
Code:
 
Limits From:US 77Fund Cat:1
Limits To:FM 43ESTIMATE:$622,301
Length:13.0Actual$543,629
 
District:CORPUS CHRISTILet Date:Oct 2016
Highway:FM 3377Let Status:Actual
Project ID:STP 2017(220)CSJ:1052-04-007
Description:2017 DISTRICT WIDE SEAL COAT PROJECTHandling
Code:
 
Limits From:IH 37Fund Cat:1
Limits To:FM 3024ESTIMATE:$10,009
Length:0.3Actual$7,932
 
District:CORPUS CHRISTILet Date:Oct 2016
Highway:FM 3377Let Status:Actual
Project ID:STP 2017(220)CSJ:1052-05-008
Description:2017 DISTRICT WIDE SEAL COAT PROJECTHandling
Code:
 
Limits From:FM 3024Fund Cat:1
Limits To:END OF MAINTESTIMATE:$57,967
Length:1.5Actual$46,607
 
District:CORPUS CHRISTILet Date:Oct 2016
Highway:FM 771Let Status:Actual
Project ID:STP 2017(220)CSJ:1115-01-009
Description:2017 DISTRICT WIDE SEAL COAT PROJECTHandling
Code:
 
Limits From:US 77Fund Cat:1
Limits To:END OF MAINT.ESTIMATE:$221,015
Length:9.2Actual$178,344
 
District:CORPUS CHRISTILet Date:Oct 2016
Highway:FM 883Let Status:Actual
Project ID:STP 2017(220)CSJ:1117-03-120
Description:2017 DISTRICT WIDE SEAL COAT PROJECTHandling
Code:
 
Limits From:BEE COUNTY LINEFund Cat:1
Limits To:US 59ESTIMATE:$357,910
Length:14.6Actual$288,203
 
District:CORPUS CHRISTILet Date:Oct 2016
Highway:FM 796Let Status:Actual
Project ID:STP 2017(220)CSJ:1118-01-022
Description:2017 DISTRICT WIDE SEAL COAT PROJECTHandling
Code:
 
Limits From:US 59Fund Cat:1
Limits To:FM 797ESTIMATE:$213,274
Length:8.5Actual$172,772
 
District:CORPUS CHRISTILet Date:Oct 2016
Highway:FM 893Let Status:Actual
Project ID:STP 2017(220)CSJ:1209-01-031
Description:2017 DISTRICT WIDE SEAL COAT PROJECTHandling
Code:
 
Limits From:FM 631Fund Cat:1
Limits To:FM 1074ESTIMATE:$162,574
Length:5.5Actual$132,545
 
District:CORPUS CHRISTILet Date:Oct 2016
Highway:FM 1356Let Status:Actual
Project ID:STP 2017(220)CSJ:1446-02-021
Description:2017 DISTRICT WIDE SEAL COAT PROJECTHandling
Code:
 
Limits From:END OF MAINT.Fund Cat:1
Limits To:US 77ESTIMATE:$45,300
Length:1.7Actual$38,386
 
District:CORPUS CHRISTILet Date:Oct 2016
Highway:FM 534Let Status:Actual
Project ID:STP 2017(220)CSJ:1808-03-021
Description:2017 DISTRICT WIDE SEAL COAT PROJECTHandling
Code:
 
Limits From:LIVE OAK COUNTY LINEFund Cat:1
Limits To:SH 359ESTIMATE:$148,426
Length:4.6Actual$120,142
 
District:CORPUS CHRISTILet Date:Oct 2016
Highway:FM 2292Let Status:Actual
Project ID:STP 2017(220)CSJ:2142-02-015
Description:2017 DISTRICT WIDE SEAL COAT PROJECTHandling
Code:
 
Limits From:BS 44Fund Cat:1
Limits To:FM 665ESTIMATE:$121,659
Length:4.1Actual$98,069
 
District:CORPUS CHRISTILet Date:Oct 2016
Highway:FM 425Let Status:Actual
Project ID:STP 2017(220)CSJ:2235-01-011
Description:2017 DISTRICT WIDE SEAL COAT PROJECTHandling
Code:
 
Limits From:BU 77-VFund Cat:1
Limits To:FM 3320ESTIMATE:$94,634
Length:1.2Actual$75,221
 
District:CORPUS CHRISTILet Date:Oct 2016
Highway:FM 2619Let Status:Actual
Project ID:STP 2017(220)CSJ:2609-01-007
Description:2017 DISTRICT WIDE SEAL COAT PROJECTHandling
Code:
 
Limits From:FM 1717Fund Cat:1
Limits To:FM 1118ESTIMATE:$66,969
Length:2.7Actual$54,205
 
District:CORPUS CHRISTILet Date:Oct 2016
Highway:FM 3512Let Status:Actual
Project ID:STP 2017(220)CSJ:3578-01-004
Description:2017 DISTRICT WIDE SEAL COAT PROJECTHandling
Code:
 
Limits From:SH 35Fund Cat:1
Limits To:FM 1069ESTIMATE:$98,253
Length:2.3Actual$80,518
 
District:CORPUS CHRISTILet Date:Oct 2016
Highway:FM 632Let Status:Actual
Project ID:STP 2017(220)CSJ:3598-01-003
Description:2017 DISTRICT WIDE SEAL COAT PROJECTHandling
Code:
 
Limits From:US 181Fund Cat:1
Limits To:END OF STATE MAINT.ESTIMATE:$39,233
Length:0.8Actual$32,114
 
Back...
Totals for 0074-02-079
Length:181.8
Estimate:$6,775,847
Actual:$5,498,583

CCSJ: 0348-11-015

District:CORPUS CHRISTILet Date:Jun 2017
Highway:FM 99Let Status:Actual
Project ID:STP 1702(339)CSJ:0348-11-015
Description:REHAB AND WIDENHandling
Code:
 
Limits From:IH 37Fund Cat:1
Limits To:ALT US 281ESTIMATE:$2,760,300
Length:2.4Actual$2,680,559
 
Proposal Request
List Showing Order
Bid List
Bid Tabulations
Award Status
Back...
Totals for 0348-11-015
Length:2.4
Estimate:$2,760,300
Actual:$2,680,559

CCSJ: 0447-01-063

District:CORPUS CHRISTILet Date:Jan 2017
Highway:US 59Let Status:Actual
Project ID:NH 2017(437)CSJ:0447-01-063
Description:OVERLAY ROADWAY_(NB & SB)Handling
Code:
 
Limits From:IH 37, WESTFund Cat:1
Limits To:BU 59-XESTIMATE:$4,091,137
Length:4.8Actual$3,062,746
 
District:CORPUS CHRISTILet Date:Jan 2017
Highway:US 59Let Status:Actual
Project ID:NH 2017(437)CSJ:0447-01-064
Description:SPOT BASE REPAIR AND OVERLAYHandling
Code:
 
Limits From:BEE COUNTY LINEFund Cat:1
Limits To:IH 37ESTIMATE:$7,020,443
Length:8.0Actual$5,929,113
 
Bid Tabulations
Back...
Totals for 0447-01-063
Length:12.8
Estimate:$11,111,580
Actual:$8,991,859

CCSJ: 0916-29-006

District:CORPUS CHRISTILet Date:Mar 2017
Highway:CRLet Status:Actual
Project ID:BR 1502(204)CSJ:0916-29-006
Description:REPLACE BRIDGE AND APPROACHESHandling
Code:
 
Limits From:STR 2 (AA0151002)ON CR 223 @ SULPHUFund Cat:6
Limits To:APPROX 1.0 MI S OF SH 72ESTIMATE:$768,117
Length:0.1Actual$649,191
 
Proposal Request
List Showing Order
Bid Tabulations
Addenda
Bid List
Award Status
Back...
Totals for 0916-29-006
Length:0.1
Estimate:$768,117
Actual:$649,191

CCSJ: 1959-01-014

District:CORPUS CHRISTILet Date:Aug 2017
Highway:FM 2049Let Status:Actual
Project ID:STP 1702(645)CSJ:1959-01-014
Description:REHAB AND WIDENHandling
Code:
 
Limits From:SH 72Fund Cat:1
Limits To:IH 37ESTIMATE:$4,494,438
Length:10.5Actual$4,076,442
 
District:CORPUS CHRISTILet Date:Aug 2017
Highway:FM 3192Let Status:Actual
Project ID:STP 1702(646)CSJ:3297-01-007
Description:REHAB AND WIDENHandling
Code:
 
Limits From:FM 2049Fund Cat:1
Limits To:FM 882ESTIMATE:$2,163,477
Length:6.1Actual$1,949,404
 
Proposal Request
List Showing Order
Bid List
Addenda
Bid Tabulations
Award Status
Back...
Totals for 1959-01-014
Length:16.6
Estimate:$6,657,915
Actual:$6,025,846

Handling CodeDefinition
XXProject not processed through statewide letting
TRTransfer of funds
LCProject let through local entity
LCProject not charged against district apportionment