CCSJ | County/ District | Highway | Let Status | Contract Cost | Fund Cat | Description |
---|---|---|---|---|---|---|
0200-02-042 | Angelina/ Lufkin | US 69 | Actual | $1,115,176 | 1 | CLEARING AND GRUBBING |
1411-02-011 | Austin/ Yoakum | FM 1457 | Actual | $4,647,133 | 1 | RESTORE ROADWAY |
0265-05-081 | Bastrop/ Austin | SH 71 | Actual | $631,755 | 10 | LANDSCAPE AND IRRIGATION |
0322-01-046 | Bastrop/ Austin | SH 95 | Actual | $220,978 | 8 | INSTALL TRAFFIC SIGNAL |
1118-01-019 | Bee/ Corpus Christi | FM 796 | Actual | $461,962 | 6 | REPLACE BRIDGE AND APPROACHES |
0915-00-178 | Bexar/ San Antonio | VA | Actual | $3,958,875 | 10 | CONSTRUCT CURB RAMPS AT VARIOUS LOCATION IN BEXAR COUNTY |
0915-00-186 | Bexar/ San Antonio | VA | Actual | $3,860,673 | 1 | DISTRICTWIDE TRAFFIC SIGNAL REHAB/UPGRADE |
0915-12-518 | Bexar/ San Antonio | CS | Actual | $509,196 | 3 | CONSTRUCTION OF A HIKE & BIKE TRAIL THROUGH FRIENDSHIP PARK |
0610-06-088 | Bowie/ Atlanta | IH 30 | Actual | $638,757 | 1 | REHABILITATE NORTH & SOUTH FRONTAGE ROADS |
0150-05-047 | Burnet/ Austin | SH 29 | Actual | $1,057,034 | 1 | WIDEN PAVED SHOULDER (TO 5 FT. OR LESS), INSTALL CONTINUOUS |
0919-00-077 | Cass/ Atlanta | VA | Actual | $419,000 | 1 | 2017 DISTRICT SEAL COAT PAVEMENT MARKINGS |
2977-01-008 | Collin/ Dallas | FM 2933 | Actual | $1,490,046 | 8 | PROVIDE ADDITIONAL PAVED SURFACE |
0918-24-212 | Collin/ Dallas | CS | Actual | $490,699 | 3 | SIDEWALK IMPROVEMENTS IN SCHOOL WALK ZONES AT OLSEN AND |
0047-14-082 | Collin/ Dallas | US 75 | Actual | $2,311,464 | 3 | LANDSCAPE TREATMENT OF RIGHTS OF WAY AND MEDIANS |
0266-08-011 | Colorado/ Yoakum | BS 71-F | Actual | $9,391,298 | 6 | CONSTRUCT BRIDGE AND APPROACHES |
0216-01-036 | Comal/ San Antonio | SL 337 | Actual | $48,583,421 | 1 | EXPAND FROM 2 TO 4 LANE DIVIDED, INCLUDING SIDEWALK AND BIKE |
0870-04-040 | Concho/ San Angelo | FM 765 | Actual | $3,074,000 | 1 | RESTORATION OF EXISTING ROAD |
0140-11-044 | Crockett/ San Angelo | IH 10 | Actual | $5,476,290 | 1 | PLANE, EMULSION TREAT, SURFACE TREATMENT, AND ACP OVERLAY |
0003-01-057 | Culberson/ El Paso | IH 10 | Actual | $1,198,336 | 1 | INSTALL MEDIAN BARRIER |
0095-02-118 | Dallas/ Dallas | US 80 | Actual | $1,868,326 | 5 | INSTALLATION OF WIRELESS ITS |
2374-01-187 | Dallas/ Dallas | IH 635 | Actual | $3,468,213 | 8 | IMPROVE GUARDRAIL TO DESIGN STANDARDS |
0918-47-118 | Dallas/ Dallas | PW | Actual | $956,448 | 10 | RECONSTRUCT PARK ROAD INCLUDING PARKING LOTS |
0918-00-182 | Dallas/ Dallas | VA | Actual | $300,000 | 1 | WAREHOUSE PROCUREMENT OF MATERIALS TO REFURBISH ITS |
0918-00-271 | Dallas/ Dallas | VA | Actual | $3,841,069 | 3 | PROVIDE ASSISTANCE TO STRANDED MOTORISTS OR NON INJURY |
0918-00-272 | Dallas/ Dallas | VA | Actual | $1,325,000 | 3 | AIR QUALITY MARKETING AND EDUCATION PROGRAM |
0918-00-267 | Dallas/ Dallas | VA | Actual | $2,053,991 | 1 | NON-SITE SPECIFIC TRAFFIC SIGNAL REHABILITATION |
0364-03-099 | Denton/ Dallas | BS 121H | Actual | $2,053,865 | 10 | LANDSCAPE TREATMENT OF MEDIANS AND RIGHT OF WAY |
2054-02-015 | Denton/ Dallas | FM 2181 | Actual | $30,795,137 | 1 | WIDEN 2 LANE RURAL ROADWAY TO 6 LANES DIVIDED URBAN |
0237-07-013 | Dimmit/ Laredo | FM 133 | Actual | $11,035,898 | 1 | REHABILITATION OF AN EXISTING HIGHWAY |
0004-07-126 | Ector/ Odessa | IH 20 | Actual | $3,453,810 | 1 | BRIDGE REPAIR |
0005-13-056 | Ector/ Odessa | IH 20 | Actual | $3,810,111 | 6 | UPGRADE BRIDGE AND APPROACH RAILING |
2121-02-150 | El Paso/ El Paso | IH 10 | Actual | $27,367,381 | 1 | MESA PARK INTERCHANGE AND FRONTAGE ROADS |
0924-06-533 | El Paso/ El Paso | VA | Actual | $1,472,157 | 10 | FY 2017 GREEN RIBBON PROJECT |
0924-06-269 | El Paso/ El Paso | CS | Actual | $2,540,000 | 3 | BUILD 4-LANE DIVIDED NON-FREEWAY FACILITY |
0674-02-011 | El Paso/ El Paso | FM 76 | Actual | $1,417,744 | 6 | REPLACE BRIDGES AND APPROACHES |
0002-12-025 | El Paso/ El Paso | US 62 | Actual | $648,666 | 5 | TRAFFIC SIGNAL MODIFICATIONS AT PAISANO DR/TROWBRIDGE DR |
0092-15-002 | Ellis/ Dallas | SS 469 | Actual | $3,251,742 | 1 | RESTORE EXISTING PAVEMENT |
0808-01-058 | Falls/ Waco | FM 413 | Actual | $2,670,883 | 6 | BRIDGE RE-DECKING |
0232-02-021 | Falls/ Waco | SH 53 | Actual | $2,163,175 | 6 | REPLACE BRIDGE AND APPROACHES |
0925-09-035 | Hall/ Childress | CR | Actual | $588,082 | 6 | REPLACEMENT OF EXISTING BRIDGE FACILITY |
0200-12-014 | Hardin/ Beaumont | FM 418 | Actual | $1,036,815 | 8 | SAFETY TREAT FIXED OBJECTS, HIGH FRICTION SURFACE TREATMENT |
0502-01-220 | Harris/ Houston | SH 225 | Actual | $957,196 | 10 | LANDSCAPING ENHANCEMENT |
0271-14-231 | Harris/ Houston | IH 610 | Actual | $9,017,557 | 1 | RECONSTRUCTION OF FRONTAGE ROADS |
1006-01-072 | Harris/ Houston | FM 529 | Actual | $145,313 | 8 | TEXTURE SHOULDERS (PROFILE PAVEMENT MARKERS) |
0111-01-092 | Harris/ Houston | FM 521 | Actual | $3,966,465 | 1 | BASE REPAIR, MILL, SEAL COAT, AND 1 INCH THIN OVERLAY |
0919-03-057 | Harrison/ Atlanta | CR | Actual | $468,436 | 6 | REPLACE BRIDGE AND APPROACHES |
0162-02-031 | Hill/ Waco | SH 31 | Actual | $74,735,657 | 1 | WIDEN FROM TWO LANE TO FOUR LANE DIVIDED. COMPLETES PH I |
0005-05-112 | Howard/ Abilene | IH 20 | Actual | $6,122,331 | 6 | INSTALL CRASHWALLS |
0002-05-045 | Hudspeth/ El Paso | IH 10 | Actual | $687,614 | 1 | CHANNEL IMPROVEMENTS |
1109-01-021 | Jasper/ Beaumont | FM 777 | Actual | $505,809 | 8 | PROVIDE ADDITIONAL PAVED SURFACE WIDTH |
0028-06-078 | Jefferson/ Beaumont | US 90 | Actual | $1,352,569 | 8 | CONSTRUCT PAVED SHOULDERS (1-4 FT.) |
0920-38-256 | Jefferson/ Beaumont | CS | Actual | $290,072 | 6 | REPLACE BRIDGE AND APPROACHES |
0751-03-037 | Kaufman/ Dallas | FM 148 | Actual | $1,411,831 | 6 | REPLACE BRIDGE AND APPROACHES |
0495-01-074 | Kaufman/ Dallas | IH 20 | Actual | $10,416,959 | 1 | MILL AND OVERLAY EXISTING FREEWAY |
0913-29-033 | Lavaca/ Yoakum | CR | Actual | $780,560 | 6 | REHABILITATE EXISTING BRIDGE |
0783-02-096 | Lubbock/ Lubbock | SL 289 | Actual | $461,840 | 1 | REHABILITATION OF EXISTING ROAD |
0905-06-106 | Lubbock/ Lubbock | VA | Actual | $1,392,469 | 11 | MISCELLANEOUS CONSTRUCTION |
0005-04-072 | Martin/ Odessa | IH 20 | Actual | $1,990,052 | 1 | BRIDGE REPAIR |
0396-02-026 | Mason/ Austin | SH 29 | Actual | $1,254,894 | 8 | UPGRADE METAL BEAM GUARD FENCE, SAFETY TREAT, PROFILE |
0914-26-007 | Mason/ Austin | CR | Actual | $270,763 | 6 | REPLACE BRIDGE & APPROACHES |
0179-14-008 | Matagorda/ Yoakum | BS 35-H | Actual | $1,713,140 | 1 | ACP OVERLAY AND SHOULDER WIDENING |
0605-01-060 | Matagorda/ Yoakum | FM 457 | Actual | $39,245,868 | 6 | REPLACE SWING BRIDGE |
1739-04-010 | Mcmullen/ San Antonio | FM 791 | Actual | $5,350,167 | 3 | CONSTRUCT BRIDGE & APPROACHES |
0915-45-052 | Medina/ San Antonio | CR | Actual | $423,298 | 6 | REPLACE BRIDGE & APPROACHES |
1601-01-031 | Parker/ Ft Worth | FM 730 | Actual | $244,683 | 1 | INSTALLATION OF TRAFFIC SIGNAL |
2635-03-018 | Randall/ Amarillo | SL 335 | Actual | $47,056,724 | 1 | B-1 PHASE I : CONSTRUCT FRONTAGE ROADS AND GRADE SEPARATION |
1091-04-022 | Rockwall/ Dallas | FM 549 | Actual | $13,228,931 | 1 | RECONSTRUCT EXISTING PAVEMENT AND ADD SHOULDERS |
0035-01-033 | Runnels/ San Angelo | US 83 | Actual | $2,921,138 | 8 | CENTERLINE AND SHOULDER TEXTURING |
0118-10-057 | San Augustine/ Lufkin | SH 21 | Actual | $5,600,388 | 6 | REMOVE & REPLACE 2 STRUCTURES |
0911-39-038 | Shelby/ Lufkin | CR | Actual | $756,719 | 6 | REPLACE BRIDGE AND APPROACHES |
0245-06-081 | Smith/ Tyler | SH 64 | Actual | $4,100,402 | 1 | PLANE, REPAIR & REPAVE ROADWAY |
0011-07-051 | Stephens/ Brownwood | US 180 | Actual | $3,547,492 | 6 | CLEAN AND PATCH SPALL AND CRACKS, REHAB EXTERIOR PAN GIRDERS |
0902-00-171 | Tarrant/ Ft Worth | VA | Actual | $2,000,000 | 3 | MANAGED LANE SYSTEM, IMPLEMENT TECHNOLOGY TO DETECT AUTO |
0902-00-200 | Tarrant/ Ft Worth | VA | Actual | $905,000 | 3 | REG. AERIAL PHOTO. DATA COL/PLANNING; IMPROVE TRAVEL DEMAND |
0914-00-396 | Travis/ Austin | VA | Actual | $1,602,345 | 11 | FY 2017 SITE SPECIFIC SIGNALS |
0914-00-406 | Travis/ Austin | VA | Actual | $1,189,562 | 1 | CONCRETE PAVEMENT REPAIRS |
0914-00-366 | Travis/ Austin | VA | Actual | $1,090,398 | 1 | NON-SITE SPECIFIC ITS MAINTENANCE CONTRACT |
0914-04-227 | Travis/ Austin | CR | Actual | $450,523 | 6 | REPLACE BRIDGE AND APPROACHES |
0914-00-407 | Travis/ Austin | VA | Actual | $2,105,034 | 1 | ASPHALTIC PAVEMENT REPAIRS |
3092-01-009 | Tyler/ Beaumont | FM 3065 | Actual | $1,175,518 | 11 | SAFETY TREAT FIXED OBJECTS, PROVIDE ADDITIONAL PAVED SURFACE |
1672-01-004 | Van Zandt/ Tyler | FM 1652 | Actual | $4,886,864 | 8 | WIDEN ROADWAY TO 24' FOR SAFETY |
1673-01-008 | Van Zandt/ Tyler | FM 1653 | Actual | $3,923,876 | 8 | WIDEN ROADWAY TO 24' FOR SAFETY |
0088-05-094 | Victoria/ Yoakum | US 59 | Actual | $2,621,490 | 1 | INSTALL MEDIAN BARRIER |
0086-14-065 | Webb/ Laredo | SL 20 | Actual | $27,411,185 | 11 | FOR THE CONSTRUCTION OF AN INTERCHANGE FACILITY OVER IH35 |
0240-03-036 | Wharton/ Yoakum | SH 60 | Actual | $2,287,663 | 8 | SAFETY TREAT FIXED OBJECTS |
0089-06-088 | Wharton/ Yoakum | US 59 | Actual | $8,092,301 | 1 | ACP OVERLAY |
0043-09-130 | Wichita/ Wichita Falls | US 287 | Actual | $2,701,548 | 6 | REPLACE BRIDGE AND APPROACHES |
0043-06-084 | Wilbarger/ Wichita Falls | US 70 | Actual | $2,823,267 | 6 | BRIDGE MAINTENANCE |
0134-07-070 | Wise/ Ft Worth | US 380 | Actual | $3,248,037 | 6 | REPLACE BRIDGE DECK ON EB STRUCTURE |
1352-04-014 | Wise/ Ft Worth | FM 455 | Actual | $87,682 | 8 | INSTALL INTERSECTION FLASHING BEACON |
1310-03-026 | Wise/ Ft Worth | FM 2264 | Actual | $8,083,286 | 11 | PROVIDE ADDITIONAL PAVED SURFACE WIDTH, PROPOSED 2-12' LANES |
0134-07-073 | Wise/ Ft Worth | US 380 | Actual | $364,441 | 1 | SAFETY LIGHTING |
|