Letting Schedule for September, 2016 County (FY 2017)

Last Update: Monday, October 16, 2017
September, 2016 (FY 2017)(see Links)
SEP 2016 | OCT 2016 | NOV 2016 | DEC 2016 | JAN 2017 | FEB 2017 | MAR 2017 | APR 2017 | MAY 2017 | JUN 2017 | JUL 2017 | AUG 2017 |
CCSJCounty/
District
HighwayLet StatusContract
Cost
Fund
Cat
Description
0961-03-014Andrews/
Odessa
FM 181Actual$7,964,5891SEAL COAT
0271-08-012Austin/
Yoakum
US 90Actual$10,516,9746REPLACE BRIDGE AND APPROACHES
1730-01-040Bandera/
San Antonio
FM 1283Actual$642,5008INSTALL LED FLASHING CHEVRONS -CURVE, TEXTURIZE SHOULDERS-
0914-18-108Bastrop/
Austin
CRActual$397,8156REPLACE BRIDGE & APPROACHES
0015-04-087Bell/
Waco
SS 290Actual$1,271,5631MILL AND INLAY
2104-02-032Bexar/
San Antonio
FM 1957Actual$1,015,2608INSTALL RAISED MEDIAN
1378-04-048Burnet/
Austin
RM 1431Actual$2,001,2431MILL, SEAL AND OVERLAY
0471-04-031Caldwell/
Austin
SH 21Actual$198,57010RIPRAP,EMBANKMENT,SPEC EXCAV WORK,FLOWABLE BACKFILL,MBGF
0384-01-021Caldwell/
Austin
SH 142Actual$3,219,6201SEAL & THIN OVERLAY
0739-01-039Chambers/
Beaumont
IH 10Actual$55,013,3231WIDEN EXISTING FOUR LANE TO SIX LANE
0031-06-032Childress/
Childress
US 62Actual$7,203,3401REHABILITATION OF EXISTING ROADWAY
0016-05-113Comal/
San Antonio
IH 35Actual$837,7058INSTALLING FLASHING BEACON AT FRONTAGE ROAD INTERSECTION
0870-04-039Concho/
San Angelo
FM 765Actual$3,210,0001RESTORATION OF EXISTING ROAD
0251-03-021Coryell/
Waco
US 281Actual$9,192,3491SEAL COAT
0918-00-263Dallas/
Dallas
VAActual$1,714,0511WRONG WAY DRIVING IMPLEMENTATION TO PREVENT WRONG WAY
0047-07-231Dallas/
Dallas
US 75Actual$688,3031INSTALL GUIDE SIGNS
0196-01-106Denton/
Dallas
IH 35EActual$32,190,8623CONSTRUCT GRADE SEPARATION ALONG IH 35E AT BRINKER AND
0623-01-022Duval/
Laredo
SH 339Actual$1,705,3941RESURFACE OF EXISTING HIGHWAY
2121-02-146El Paso/
El Paso
IH 10Actual$1,453,75511INSTALL HIGH MAST LIGHTING
0167-02-058El Paso/
El Paso
BU 54-AActual$770,6658INSTALL CONTINUOUS TURN LANE
0027-06-057Fort Bend/
Houston
US 90AActual$974,2741BASE REPAIR AND 1.5" ACP OVERLAY
0527-06-019Fort Bend/
Houston
FM 360Actual$1,859,9381BASE REPAIR, MILLING, 1.5" ACP OVERLAY AND PAVEMENT MARKINGS
0389-06-106Galveston/
Houston
SH 146Actual$8,783,9921BASE REPAIR AND 1.5" ACP OVERLAY
0045-19-058Grayson/
Paris
US 82Actual$21,96010EMERGENCY REPAIRS DUE TO FLOODING
2640-01-008Grayson/
Paris
FM 1310Actual$44,46110EMERGENCY REPAIRS DUE TO FLOODING
0043-02-073Hardeman/
Childress
US 287Actual$6,007,51511REHABILITATION / ACP OVERLAY
0098-01-038Hardeman/
Childress
SH 6Actual$6,956,6421REHABILITATION OF EXISTING ROAD
0912-72-325Harris/
Houston
CSActual$13,000,0003DESIGN AND RECONSTRUCT ROADWAY WITH TRANSITWAY (YEAR 5)
0912-72-368Harris/
Houston
CSActual$2,385,0003RECONSTRUCT SIDEWALKS AND INSTALL PEDESTRIAN AMENITIES
0912-72-369Harris/
Houston
CSActual$3,412,0003RECONSTRUCT BACK OF CURB INFRASTRUCTURE - SIDEWALKS, CURBS,
0912-70-112Harris/
Houston
CRActual$23,60010REMOVE DAMAGED CONTROL CABINET AND REPLACE WITH PERMANENT
0255-09-095Hidalgo/
Pharr
US 281Actual$5,653,8671OVERLAY
2094-01-059Hidalgo/
Pharr
FM 2220Actual$2,227,2681SEAL COAT
0109-05-040Houston/
Lufkin
SH 19Actual$964,8138SAFETY TREAT FIXED OBJECTS
0908-12-022Howard/
Abilene
VAActual$68,227,77911CONSTRUCT NEW RELIEF ROUTE
0901-22-107Hunt/
Paris
CRActual$515,5616BRIDGE REPLACEMENT
0028-06-081Jefferson/
Beaumont
US 90Actual$9,786,0321SEAL COAT
0014-04-080Johnson/
Ft Worth
IH 35WActual$296,0751CABLE MEDIAN BARRIER INSTALLATION
0366-06-042Karnes/
Corpus Christi
SH 123Actual$21,245,3041REHAB ROADWAY AND ADD PASSING LANES
0142-14-062Kerr/
San Antonio
IH 10Actual$2,649,8521RECONSTRUCT UNDER FM 783 TO INCREASE VERTICAL CLEARANCE;
0680-01-015Lamar/
Paris
FM 196Actual$2,990,2361REHABILITATION OF EXISTING ROAD
0276-02-028Maverick/
Laredo
US 57Actual$2,580,7231RESURFACE OF EXISTING HIGHWAY
1706-03-008Montgomery/
Houston
FM 1097Actual$7,302,1141BASE REPAIR, OCST, 1.5" OVERLAY AND ADD SHOULDER
0918-18-126Navarro/
Dallas
CRActual$1,159,1566REPLACE BRIDGE AND APPROACHES
0904-00-162Potter/
Amarillo
VAActual$453,1291CRACK SEAL
0049-06-076Robertson/
Bryan
SH 6Actual$55,4708SAFETY WORK CONSISTING OF INSTALLATION OF AN INTERSECTION
0009-12-216Rockwall/
Dallas
IH 30Actual$1,637,9495INSTALLATION OF WIRELESS ITS
0059-04-047Shelby/
Lufkin
SH 7Actual$1,879,22910EMERGENCY SLOPE REPAIRS
0059-04-048Shelby/
Lufkin
SH 7Actual$761,57010EMERGENCY SLOPE REPAIRS
0520-01-021Smith/
Tyler
SH 155Actual$6,621,4871REPAIR AND RESURFACE ROADWAY
0902-90-066Tarrant/
Ft Worth
CSActual$14,27110PERMANENT GUARDRAILS REPLACED AND SCOURED ASPHALT MILLED
0010-06-041Titus/
Atlanta
US 67Actual$2,357,1598PROFILE EDGELINE MARKINGS
1377-01-020Travis/
Austin
FM 1327Actual$420,04110RIPRAP,MBGF END TREATMENT, TRAFFIC CONTROL ITEMS, INSTALL
0914-04-304Travis/
Austin
CSActual$56,11310REPAIR EROSION AT BRIDGE ENDS,REMOVE EXISTING CONCRETE
2100-01-062Travis/
Austin
RM 2222Actual$62,08610RIPRAP (STONE COMMON), GABIONS(3'X 3')(GALV), EQUIPMENT HOUR
0402-01-023Upshur/
Atlanta
SH 154Actual$1,515,8648TEXTURIZE SHOULDERS & CL TEXTURING
0036-07-033Uvalde/
San Antonio
US 83Actual$904,4701IMPROVE HORIZONTAL ALIGNMENT
3550-01-014Walker/
Bryan
FM 3478Actual$20,12610ROADWAY REPAIR_(REPAIR PAVEMENT STRUCTURE AND ROADBED)
0004-04-086Ward/
Odessa
IH 20Actual$19,776,6511FACILITY UPGRADES TO MEET FREEWAY STANDARDS
0327-10-058Willacy/
Pharr
IH 69EActual$4,494,3321OVERLAY_(MAIN LANES)
0015-09-179Williamson/
Austin
IH 35Actual$15,486,0711BRIDGE REPLACEMENT & INTERSECTION IMPROVEMENTS @ FM 3406
0914-05-182Williamson/
Austin
VAActual$99,69810ADD ROAD BASE MATERIAL TO WMA ROAD TO BOAT RAMP ON
0143-05-032Wilson/
San Antonio
US 87Actual$11,604,4171REHAB EXISTING ROADWAY


Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract