CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description |
---|---|---|---|---|---|---|
0133-07-026 | SH 114 | Actual | Apr 2017 | $488,977 | 8 | CENTERLINE TEXTURING |
Clay County |
||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description |
0282-01-016 | SH 79 | Actual | Jun 2017 | $6,090,000 | 6 | REPLACE BRIDGE |
0391-02-018 | FM 810 | Actual | May 2017 | $2,010,845 | 1 | EXTEND CULVERTS |
Cooke County |
||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description |
1356-01-027 | FM 1201 | Actual | Nov 2016 | $1,123,298 | 1 | REPAIR DRAINAGE STRUCTURES |
0903-15-082 | CR | Actual | Dec 2016 | $931,937 | 6 | REPLACE BRIDGE AND APPROACHES |
3192-02-009 | FM 1199 | Actual | Mar 2017 | $917,936 | 1 | FULL DEPTH REPAIR AND OVERLAY |
0312-01-078 | FM 51 | Actual | Apr 2017 | $793,989 | 1 | ADD SHOULDERS |
Montague County |
||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description |
0013-05-060 | US 81 | Actual | May 2017 | $1,403,614 | 1 | SAFETY LIGHTING, IMPROVE HORIZONTAL ALIGNMENT |
0044-04-060 | US 82 | Actual | May 2017 | $270,358 | 11 | TRAFFIC SIGNAL |
0423-02-020 | FM 677 | Actual | Feb 2017 | $316,689 | 10 | REPAIR DAMAGE DUE TO FLOODING |
0044-04-059 | US 82 | Actual | Apr 2017 | $6,503,672 | 1 | FULL DEPTH REPAIR AND OVERLAY |
0013-02-021 | US 81 | Actual | Nov 2016 | $6,436,589 | 1 | SEAL COAT |
1352-02-021 | FM 455 | Actual | May 2017 | $586,387 | 8 | IMPROVE HORIZONTAL ALIGNMENT |
0013-03-035 | US 81 | Actual | Feb 2017 | $733,303 | 11 | FULL DEPTH CONCRETE REPAIR |
Wichita County |
||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description |
0903-03-112 | VA | Actual | May 2017 | $1,482,354 | 3 | CONSTRUCT HIKE & BIKE TRAIL |
0043-17-030 | BU 287J | Actual | Dec 2016 | $4,027,873 | 1 | OVERLAY |
0903-03-113 | CS | Actual | May 2017 | $247,977 | 8 | 2017 FEDERAL SIGNAL PROGRAM |
0156-07-109 | IH 44 | Actual | Jun 2017 | $1,062,496 | 8 | INTALL MEDIAN BARRIER |
0903-00-083 | VA | Actual | May 2017 | $938,295 | 10 | INSTALLATION OF ITS CAMERAS & DYNAMIC MESSAGE SIGNS ON US 82 |
0043-09-130 | US 287 | Actual | Jul 2017 | $2,701,548 | 6 | REPLACE BRIDGE AND APPROACHES |
0903-03-083 | CS | Actual | Jun 2017 | $1,085,464 | 6 | REPLACE BRIDGE AND APPROACHES |
0903-03-111 | VA | Actual | Jun 2017 | $559,992 | 3 | CONSTRUCT SIDEWALKS |
0043-14-024 | SL 11 | Actual | Mar 2017 | $320,612 | 6 | UPGRADE BRIDGE AND APPROACH RAILING |
Wilbarger County |
||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description |
0043-07-109 | US 287 | Actual | Oct 2016 | $2,584,285 | 1 | ADD LEFT TURN LANES AT CROSSOVERS |
0043-06-084 | US 70 | Actual | Jul 2017 | $2,823,267 | 6 | BRIDGE MAINTENANCE |
0124-04-031 | US 183 | Actual | Oct 2016 | $7,150,020 | 1 | UPGRADE TO SUPER-2 |
Young County |
||||||
CCSJ | Highway | Let Status | Letting Date | Contract Cost | Fund Cat | Description |
1076-02-040 | FM 209 | Actual | Mar 2017 | $2,500,359 | 1 | EXTEND CULVERTS |
|