Detail Letting Schedule for Baylor County (FY 2018)
Baylor County (FY 2018) |
CCSJ: 0124-05-029 |
|||
District: | WICHITA FALLS | Let Date: | Jun 2018 |
Highway: | US 183 | Let Status: | Actual |
Project ID: | C 124-5-29 | CSJ: | 0124-05-029 |
Description: | ADD SHOULDERS | Handling Code: | |
Limits From: | WICHITA RIVER | Fund Cat: | 1 |
Limits To: | US 82 | ESTIMATE: | $724,500 |
Length: | 6.3 | Actual | $588,100 |
District: | WICHITA FALLS | Let Date: | Jun 2018 |
Highway: | US 183 | Let Status: | Actual |
Project ID: | C 124-5-30 | CSJ: | 0124-05-030 |
Description: | SAFETY TREAT FIXED OBJECTS, PROVIDE ADDITIONAL PAVED SURFACE | Handling Code: | |
Limits From: | 6.296 MI N OF US 82 | Fund Cat: | 8 |
Limits To: | US 82 | ESTIMATE: | $4,987,764 |
Length: | 6.3 | Actual | $5,463,996 |
Proposal Request Bid List List Showing Order Addenda Bid Tabulations Award Status Back... | Totals for 0124-05-029 | ||
---|---|---|---|
Length: | 12.6 | ||
Estimate: | $5,712,264 | ||
Actual: | $6,052,096 | ||
CCSJ: 0156-06-052 |
|||
District: | WICHITA FALLS | Let Date: | May 2018 |
Highway: | US 82 | Let Status: | Actual |
Project ID: | NH 1802(199) | CSJ: | 0156-06-052 |
Description: | RE-ALIGN ROADWAY | Handling Code: | |
Limits From: | APPROX. 1 MILE WEST OF US 183 (WB) | Fund Cat: | 1 |
Limits To: | APPROX. 1 MILE EAST OF US 183 (WB) | ESTIMATE: | $4,156,857 |
Length: | 2.0 | Actual | $3,745,738 |
Proposal Request List Showing Order Bid List Addenda Bid Tabulations Award Status Back... | Totals for 0156-06-052 | ||
Length: | 2 | ||
Estimate: | $4,156,857 | ||
Actual: | $3,745,738 |
Handling Code | Definition |
---|---|
XX | Project not processed through statewide letting |
TR | Transfer of funds |
LC | Project let through local entity |
LC | Project not charged against district apportionment |
Let Status | Definition |
---|---|
Tentative | Estimated letting date for this project |
Approved | Project has administrative approval to be let |
Actual | Project was let to contract |