Detail Letting Schedule for Coryell County (FY 2018)

Last Update: Monday, August 27, 2018
Coryell County (FY 2018)

CCSJ: 0055-05-050

District:WACOLet Date:Sep 2017
Highway:US 84Let Status:Actual
Project ID:STP 2018(006)CSJ:0055-05-050
Description:SEAL COATHandling
Code:
 
Limits From:SH 36 BYPASSFund Cat:1
Limits To:0.653 MI E OF BONE RDESTIMATE:$828,992
Length:4.8Actual$753,505
 
District:WACOLet Date:Sep 2017
Highway:SH 171Let Status:Actual
Project ID:STP 2018(006)CSJ:0019-03-027
Description:SEAL COATHandling
Code:
 
Limits From:JOHNSON CO LINEFund Cat:1
Limits To:FM 2719ESTIMATE:$225,354
Length:5.0Actual$221,989
 
District:WACOLet Date:Sep 2017
Highway:US 84Let Status:Actual
Project ID:STP 2018(006)CSJ:0055-06-032
Description:SEAL COATHandling
Code:
 
Limits From:0.653 MI E OF BONE RDFund Cat:1
Limits To:CORYELL CREEKESTIMATE:$117,040
Length:2.2Actual$115,348
 
District:WACOLet Date:Sep 2017
Highway:SH 31Let Status:Actual
Project ID:STP 2018(006)CSJ:0162-02-040
Description:SEAL COATHandling
Code:
 
Limits From:MCCLENNAN CO LINEFund Cat:1
Limits To:0.4 MI S OF CR 3266ESTIMATE:$648,848
Length:6.5Actual$640,095
 
District:WACOLet Date:Sep 2017
Highway:SH 36Let Status:Actual
Project ID:STP 2018(006)CSJ:0183-03-051
Description:SEAL COATHandling
Code:
 
Limits From:US 281Fund Cat:1
Limits To:CORYELL CO LINEESTIMATE:$793,131
Length:15.8Actual$780,687
 
District:WACOLet Date:Sep 2017
Highway:SH 36Let Status:Actual
Project ID:STP 2018(007)CSJ:0183-04-055
Description:SEAL COATHandling
Code:
 
Limits From:0.73 MI N OF FM 215Fund Cat:1
Limits To:0.61 MI S OF FM 215ESTIMATE:$128,371
Length:1.3Actual$122,883
 
District:WACOLet Date:Sep 2017
Highway:SH 36Let Status:Actual
Project ID:STP 2018(006)CSJ:0184-01-064
Description:SEAL COATHandling
Code:
 
Limits From:BU 36Fund Cat:1
Limits To:0.7 MI W OF FM 931ESTIMATE:$557,030
Length:9.0Actual$545,106
 
District:WACOLet Date:Sep 2017
Highway:FM 310Let Status:Actual
Project ID:STP 2018(006)CSJ:0209-06-038
Description:SEAL COATHandling
Code:
 
Limits From:IH 35Fund Cat:1
Limits To:FM 933ESTIMATE:$255,817
Length:9.4Actual$256,380
 
District:WACOLet Date:Sep 2017
Highway:SH 53Let Status:Actual
Project ID:STP 2018(006)CSJ:0232-01-052
Description:SEAL COATHandling
Code:
 
Limits From:TEMPLE EAST CITY LIMITSFund Cat:1
Limits To:FALLS CO LINEESTIMATE:$611,320
Length:12.0Actual$587,212
 
District:WACOLet Date:Sep 2017
Highway:SH 164Let Status:Actual
Project ID:STP 2018(006)CSJ:0413-02-032
Description:SEAL COATHandling
Code:
 
Limits From:MCLENNAN CO LINEFund Cat:1
Limits To:SH 14ESTIMATE:$789,342
Length:17.0Actual$734,308
 
District:WACOLet Date:Sep 2017
Highway:SH 171Let Status:Actual
Project ID:STP 2018(006)CSJ:0418-03-024
Description:SEAL COATHandling
Code:
 
Limits From:FM 2719Fund Cat:1
Limits To:SH 22ESTIMATE:$525,657
Length:12.2Actual$518,766
 
District:WACOLet Date:Sep 2017
Highway:SH 236Let Status:Actual
Project ID:STP 2018(006)CSJ:0513-01-018
Description:SEAL COATHandling
Code:
 
Limits From:SH 36Fund Cat:1
Limits To:FM 107ESTIMATE:$187,891
Length:6.9Actual$184,311
 
District:WACOLet Date:Sep 2017
Highway:BS 7-BLet Status:Actual
Project ID:STP 2018(006)CSJ:0513-03-023
Description:SEAL COATHandling
Code:
 
Limits From:US 77Fund Cat:1
Limits To:SH 7ESTIMATE:$41,412
Length:1.4Actual$40,655
 
District:WACOLet Date:Sep 2017
Highway:SH 174Let Status:Actual
Project ID:STP 2018(006)CSJ:0519-02-023
Description:SEAL COATHandling
Code:
 
Limits From:JOHNSON CO LINEFund Cat:1
Limits To:BOSQUE CO LINEESTIMATE:$425,628
Length:9.3Actual$418,079
 
District:WACOLet Date:Sep 2017
Highway:FM 1602Let Status:Actual
Project ID:STP 2018(006)CSJ:0550-06-013
Description:SEAL COATHandling
Code:
 
Limits From:US 281Fund Cat:1
Limits To:FM 219ESTIMATE:$305,512
Length:9.9Actual$305,636
 
District:WACOLet Date:Sep 2017
Highway:FM 2417Let Status:Actual
Project ID:STP 2018(007)CSJ:0662-01-012
Description:SEAL COATHandling
Code:
 
Limits From:BU 77LFund Cat:1
Limits To:1.458 MI EASTESTIMATE:$69,969
Length:1.5Actual$68,707
 
District:WACOLet Date:Sep 2017
Highway:FM 342Let Status:Actual
Project ID:STP 2018(006)CSJ:0831-01-018
Description:SEAL COATHandling
Code:
 
Limits From:LIMESTONE CO LINEFund Cat:1
Limits To:FM 939ESTIMATE:$16,221
Length:0.6Actual$16,319
 
District:WACOLet Date:Sep 2017
Highway:FM 339Let Status:Actual
Project ID:STP 2018(006)CSJ:1662-03-014
Description:SEAL COATHandling
Code:
 
Limits From:FM 73Fund Cat:1
Limits To:HILL CO LINEESTIMATE:$221,664
Length:8.4Actual$222,450
 
District:WACOLet Date:Sep 2017
Highway:FM 339Let Status:Actual
Project ID:STP 2018(006)CSJ:1662-04-006
Description:SEAL COATHandling
Code:
 
Limits From:US 84Fund Cat:1
Limits To:FM 73ESTIMATE:$9,632
Length:0.4Actual$9,485
 
District:WACOLet Date:Sep 2017
Highway:FM 2484Let Status:Actual
Project ID:STP 2018(006)CSJ:2304-03-014
Description:SEAL COATHandling
Code:
 
Limits From:5.44 MI W OF IH 35Fund Cat:1
Limits To:IH 35ESTIMATE:$165,522
Length:5.5Actual$161,860
 
District:WACOLet Date:Sep 2017
Highway:FM 3051Let Status:Actual
Project ID:STP 2018(007)CSJ:2311-01-040
Description:SEAL COATHandling
Code:
 
Limits From:BU 77LFund Cat:1
Limits To:AIRPORT ROADESTIMATE:$408,852
Length:6.2Actual$395,886
 
District:WACOLet Date:Sep 2017
Highway:FM 2484Let Status:Actual
Project ID:STP 2018(006)CSJ:2390-01-015
Description:SEAL COATHandling
Code:
 
Limits From:SH 195Fund Cat:1
Limits To:UNION GROVE LANEESTIMATE:$401,737
Length:13.5Actual$395,443
 
District:WACOLet Date:Sep 2017
Highway:FM 1245Let Status:Actual
Project ID:C 2394-2-8CSJ:2394-02-008
Description:SEAL COATHandling
Code:
 
Limits From:SH 14Fund Cat:1
Limits To:3.583 MI EASTESTIMATE:$103,099
Length:3.6Actual$96,479
 
District:WACOLet Date:Sep 2017
Highway:FM 2490Let Status:Actual
Project ID:STP 2018(006)CSJ:2396-01-007
Description:SEAL COATHandling
Code:
 
Limits From:FM 56Fund Cat:1
Limits To:MCLENNAN CO LINEESTIMATE:$331,912
Length:7.9Actual$327,819
 
Proposal Request
Bid List
List Showing Order
Addenda
Bid Tabulations
Award Status
Back...
Totals for 0055-05-050
Length:170.3
Estimate:$8,169,954
Actual:$7,919,406

CCSJ: 0055-06-033

District:WACOLet Date:Dec 2017
Highway:US 84Let Status:Actual
Project ID:BR 2018(345)CSJ:0055-06-033
Description:DECK AND RAILING REPAIRS/REHABILITATIONHandling
Code:
 
Limits From:@ CORYELL CREEKFund Cat:6
Limits To:(STR #074)ESTIMATE:$375,124
Length:0.1Actual$277,779
 
Proposal Request
Bid List
List Showing Order
Bid Tabulations
Award Status
Back...
Totals for 0055-06-033
Length:0.1
Estimate:$375,124
Actual:$277,779

CCSJ: 0184-01-063

District:WACOLet Date:Jul 2018
Highway:SH 36Let Status:Actual
Project ID:C 184-1-63CSJ:0184-01-063
Description:WIDEN ROADWAY AND ADD PASSING LANESHandling
Code:
 
Limits From:.7 MI W OF FM 931Fund Cat:1
Limits To:BELL CO LINEESTIMATE:$9,065,132
Length:8.2Actual$8,038,471
 
District:WACOLet Date:Jul 2018
Highway:SH 36Let Status:Actual
Project ID:C 184-2-53CSJ:0184-02-053
Description:WIDEN ROADWAY AND ADD PASSING LANESHandling
Code:
 
Limits From:CORYELL CO LINEFund Cat:1
Limits To:LAKE BELTON BRDGESTIMATE:$3,462,588
Length:3.2Actual$3,149,000
 
Proposal Request
Bid List
List Showing Order
Addenda
Bid Tabulations
Award Status
Back...
Totals for 0184-01-063
Length:11.4
Estimate:$12,527,719
Actual:$11,187,471

CCSJ: 0909-39-127

District:WACOLet Date:Jul 2018
Highway:CRLet Status:Actual
Project ID:BR 1502(366)CSJ:0909-39-127
Description:REPLACE BRIDGE AND APPROACHESHandling
Code:
 
Limits From:ON CR 210 @ LEON RIVERFund Cat:6
Limits To:(MAP #10)ESTIMATE:$985,729
Length:0.1Actual$1,020,198
 
Proposal Request
Bid List
List Showing Order
Bid Tabulations
Award Status
Back...
Totals for 0909-39-127
Length:0.1
Estimate:$985,729
Actual:$1,020,198

CCSJ: 1594-02-012

District:WACOLet Date:Feb 2018
Highway:FM 1783Let Status:Actual
Project ID:BR 2018(547)CSJ:1594-02-012
Description:REPLACE BRIDGE AND APPROACHESHandling
Code:
 
Limits From:@ DODDS CREEKFund Cat:11
Limits To:(STR #003)ESTIMATE:$1,126,439
Length:0.2Actual$1,048,921
 
List Showing Order
Proposal Request
Bid List
Bid Tabulations
Award Status
Back...
Totals for 1594-02-012
Length:0.2
Estimate:$1,126,439
Actual:$1,048,921

CCSJ: 3623-01-003

District:WACOLet Date:Jan 2018
Highway:SH 9Let Status:Actual
Project ID:STP 2018(500)CSJ:3623-01-003
Description:SLOPE REPAIRHandling
Code:
 
Limits From:0.6 MI N OF BU 190Fund Cat:1
Limits To:BU 190ESTIMATE:$588,069
Length:0.6Actual$661,980
 
Proposal Request
List Showing Order
Bid List
Bid Tabulations
Award Status
Back...
Totals for 3623-01-003
Length:0.6
Estimate:$588,069
Actual:$661,980

Handling CodeDefinition
XXProject not processed through statewide letting
TRTransfer of funds
LCProject let through local entity
LCProject not charged against district apportionment



Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract