Detail Letting Schedule for Eastland County (FY 2018)
Eastland County (FY 2018) |
CCSJ: 0007-04-126 |
|||
District: | BROWNWOOD | Let Date: | Nov 2017 |
Highway: | SH 206 | Let Status: | Actual |
Project ID: | STP 1702(798) | CSJ: | 0007-04-126 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | FM 2943 | Fund Cat: | 1 |
Limits To: | .1 MI N OF IH 20 S.F.R IN CISCO | ESTIMATE: | $170,150 |
Length: | 0.7 | Actual | $30,724 |
District: | BROWNWOOD | Let Date: | Nov 2017 |
Highway: | SH 6 | Let Status: | Actual |
Project ID: | STP 1702(798) | CSJ: | 0007-04-127 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | US 183 IN CISCO E | Fund Cat: | 1 |
Limits To: | AMERMAN ST IN EASTLAND | ESTIMATE: | $442,880 |
Length: | 9.2 | Actual | $416,481 |
District: | BROWNWOOD | Let Date: | Nov 2017 |
Highway: | IH 20 | Let Status: | Actual |
Project ID: | NH 1702(799) | CSJ: | 0007-06-087 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | 0.4 MI. W OF FM 2461 | Fund Cat: | 1 |
Limits To: | LP 254 | ESTIMATE: | $368,463 |
Length: | 5.6 | Actual | $351,862 |
District: | BROWNWOOD | Let Date: | Nov 2017 |
Highway: | US 180 | Let Status: | Actual |
Project ID: | STP 1702(798) | CSJ: | 0011-07-050 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | FM 3099 | Fund Cat: | 1 |
Limits To: | HARDING STREET | ESTIMATE: | $81,405 |
Length: | 1.5 | Actual | $75,977 |
District: | BROWNWOOD | Let Date: | Nov 2017 |
Highway: | US 180 | Let Status: | Actual |
Project ID: | STP 1702(798) | CSJ: | 0011-08-028 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | HARDING STREET | Fund Cat: | 1 |
Limits To: | ROSE STREET | ESTIMATE: | $56,909 |
Length: | 1.0 | Actual | $53,322 |
District: | BROWNWOOD | Let Date: | Nov 2017 |
Highway: | SL 252 | Let Status: | Actual |
Project ID: | STP 1702(798) | CSJ: | 0011-12-006 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | US 180 W OF CADDO | Fund Cat: | 1 |
Limits To: | US 180 E OF CADDO | ESTIMATE: | $41,428 |
Length: | 1.6 | Actual | $38,828 |
District: | BROWNWOOD | Let Date: | Nov 2017 |
Highway: | US 84 | Let Status: | Actual |
Project ID: | NH 1702(799) | CSJ: | 0054-04-110 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | SH 153 | Fund Cat: | 1 |
Limits To: | US 67 | ESTIMATE: | $435,544 |
Length: | 7.0 | Actual | $395,281 |
District: | BROWNWOOD | Let Date: | Nov 2017 |
Highway: | US 67 | Let Status: | Actual |
Project ID: | NH 1702(799) | CSJ: | 0054-06-099 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | BANGS W CITY LIMITS | Fund Cat: | 1 |
Limits To: | COLEMAN COUNTY LINE | ESTIMATE: | $222,469 |
Length: | 3.7 | Actual | $208,053 |
District: | BROWNWOOD | Let Date: | Nov 2017 |
Highway: | US 67 | Let Status: | Actual |
Project ID: | NH 1702(799) | CSJ: | 0054-06-101 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | CR 152 | Fund Cat: | 1 |
Limits To: | SP 586 | ESTIMATE: | $235,819 |
Length: | 3.2 | Actual | $222,467 |
District: | BROWNWOOD | Let Date: | Nov 2017 |
Highway: | US 67 | Let Status: | Actual |
Project ID: | NH 1702(799) | CSJ: | 0054-06-102 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | SPUR 586 | Fund Cat: | 1 |
Limits To: | BANGS W CITY LIMITS | ESTIMATE: | $90,021 |
Length: | 1.6 | Actual | $84,088 |
District: | BROWNWOOD | Let Date: | Nov 2017 |
Highway: | US 84 | Let Status: | Actual |
Project ID: | NH 1702(799) | CSJ: | 0054-09-036 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | FM 573 | Fund Cat: | 1 |
Limits To: | .2 MI E OF US 183 | ESTIMATE: | $393,334 |
Length: | 9.0 | Actual | $368,887 |
District: | BROWNWOOD | Let Date: | Nov 2017 |
Highway: | US 67 | Let Status: | Actual |
Project ID: | NH 1702(799) | CSJ: | 0078-02-021 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | CR 185 | Fund Cat: | 1 |
Limits To: | RUNNELS COUNTY LINE | ESTIMATE: | $243,023 |
Length: | 6.4 | Actual | $228,523 |
District: | BROWNWOOD | Let Date: | Nov 2017 |
Highway: | US 67 | Let Status: | Actual |
Project ID: | NH 1702(799) | CSJ: | 0078-03-056 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | .8 MI E OF FM 503 | Fund Cat: | 1 |
Limits To: | CR 185 | ESTIMATE: | $77,939 |
Length: | 4.7 | Actual | $73,059 |
District: | BROWNWOOD | Let Date: | Nov 2017 |
Highway: | SH 6 | Let Status: | Actual |
Project ID: | STP 1702(798) | CSJ: | 0126-03-035 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | FM 1853 | Fund Cat: | 1 |
Limits To: | UNION PACIFIC RR | ESTIMATE: | $270,637 |
Length: | 8.1 | Actual | $253,643 |
District: | BROWNWOOD | Let Date: | Nov 2017 |
Highway: | SH 6 | Let Status: | Actual |
Project ID: | STP 1702(798) | CSJ: | 0126-03-037 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | UNION PACIFC RR IN CISCO | Fund Cat: | 1 |
Limits To: | SH 206 | ESTIMATE: | $17,898 |
Length: | 0.3 | Actual | $16,851 |
District: | BROWNWOOD | Let Date: | Nov 2017 |
Highway: | US 183 | Let Status: | Actual |
Project ID: | STP 1702(798) | CSJ: | 0127-01-033 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | SH 206 | Fund Cat: | 1 |
Limits To: | IH 20 N FR | ESTIMATE: | $45,742 |
Length: | 1.0 | Actual | $42,832 |
District: | BROWNWOOD | Let Date: | Nov 2017 |
Highway: | US 377 | Let Status: | Actual |
Project ID: | STP 1702(798) | CSJ: | 0128-01-107 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | 0.220 MI S OF FM 45 | Fund Cat: | 1 |
Limits To: | MCCULLOCH C/L | ESTIMATE: | $641,214 |
Length: | 16.4 | Actual | $603,342 |
District: | BROWNWOOD | Let Date: | Nov 2017 |
Highway: | FM 2376 | Let Status: | Actual |
Project ID: | STP 1702(798) | CSJ: | 0128-02-019 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | END OF STATE MAINTENANCE | Fund Cat: | 1 |
Limits To: | FM 45 | ESTIMATE: | $87,313 |
Length: | 2.2 | Actual | $80,662 |
District: | BROWNWOOD | Let Date: | Nov 2017 |
Highway: | FM 3064 | Let Status: | Actual |
Project ID: | STP 1702(798) | CSJ: | 0128-02-020 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | US 377 | Fund Cat: | 1 |
Limits To: | FM 2376 | ESTIMATE: | $64,789 |
Length: | 1.3 | Actual | $59,546 |
District: | BROWNWOOD | Let Date: | Nov 2017 |
Highway: | SH 36 | Let Status: | Actual |
Project ID: | STP 1702(798) | CSJ: | 0182-02-042 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | FM 1477 | Fund Cat: | 1 |
Limits To: | FM 588 | ESTIMATE: | $138,737 |
Length: | 3.7 | Actual | $130,046 |
District: | BROWNWOOD | Let Date: | Nov 2017 |
Highway: | SH 67 | Let Status: | Actual |
Project ID: | STP 1702(798) | CSJ: | 0256-02-030 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | FM 1148 | Fund Cat: | 1 |
Limits To: | US 180 | ESTIMATE: | $422,474 |
Length: | 11.3 | Actual | $397,529 |
District: | BROWNWOOD | Let Date: | Nov 2017 |
Highway: | US 190 | Let Status: | Actual |
Project ID: | NH 1702(799) | CSJ: | 0272-03-039 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | FM 45 | Fund Cat: | 1 |
Limits To: | WILCOX ST IN SAN SABA | ESTIMATE: | $482,501 |
Length: | 13.7 | Actual | $453,645 |
District: | BROWNWOOD | Let Date: | Nov 2017 |
Highway: | US 190 | Let Status: | Actual |
Project ID: | NH 1702(799) | CSJ: | 0272-04-028 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | MILL ST IN SAN SABA | Fund Cat: | 1 |
Limits To: | LAMPASAS COUNTY LINE | ESTIMATE: | $324,951 |
Length: | 9.0 | Actual | $305,059 |
District: | BROWNWOOD | Let Date: | Nov 2017 |
Highway: | US 183 | Let Status: | Actual |
Project ID: | NH 1702(799) | CSJ: | 0274-02-027 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | CR 2509 | Fund Cat: | 1 |
Limits To: | US 190 | ESTIMATE: | $112,119 |
Length: | 1.7 | Actual | $104,588 |
District: | BROWNWOOD | Let Date: | Nov 2017 |
Highway: | SH 16 | Let Status: | Actual |
Project ID: | STP 1702(798) | CSJ: | 0288-02-029 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | FM 2861 | Fund Cat: | 1 |
Limits To: | US 67 | ESTIMATE: | $170,894 |
Length: | 5.3 | Actual | $159,201 |
District: | BROWNWOOD | Let Date: | Nov 2017 |
Highway: | SH 16 | Let Status: | Actual |
Project ID: | STP 1702(798) | CSJ: | 0289-01-032 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | US 67 | Fund Cat: | 1 |
Limits To: | FM 590 | ESTIMATE: | $29,781 |
Length: | 0.7 | Actual | $27,473 |
District: | BROWNWOOD | Let Date: | Nov 2017 |
Highway: | SH 16 | Let Status: | Actual |
Project ID: | STP 1702(798) | CSJ: | 0289-02-016 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | US 84 | Fund Cat: | 1 |
Limits To: | COMANCHE COUNTY LINE | ESTIMATE: | $615,655 |
Length: | 17.3 | Actual | $577,612 |
District: | BROWNWOOD | Let Date: | Nov 2017 |
Highway: | FM 45 | Let Status: | Actual |
Project ID: | STP 1702(798) | CSJ: | 0480-06-024 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | US 377 E | Fund Cat: | 1 |
Limits To: | FM 2126 | ESTIMATE: | $68,141 |
Length: | 2.5 | Actual | $62,936 |
District: | BROWNWOOD | Let Date: | Nov 2017 |
Highway: | FM 765 | Let Status: | Actual |
Project ID: | STP 1702(798) | CSJ: | 0870-06-018 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | US 377 | Fund Cat: | 1 |
Limits To: | SAN SABA COUNTY LINE | ESTIMATE: | $108,461 |
Length: | 4.7 | Actual | $100,925 |
District: | BROWNWOOD | Let Date: | Nov 2017 |
Highway: | FM 587 | Let Status: | Actual |
Project ID: | STP 1702(798) | CSJ: | 1036-02-007 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | FM 1027 | Fund Cat: | 1 |
Limits To: | COMANCHE COUNTY LINE | ESTIMATE: | $16,286 |
Length: | 0.2 | Actual | $12,658 |
District: | BROWNWOOD | Let Date: | Nov 2017 |
Highway: | FM 587 | Let Status: | Actual |
Project ID: | STP 1702(798) | CSJ: | 1239-01-029 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | SH 36 | Fund Cat: | 1 |
Limits To: | FM 1027 | ESTIMATE: | $15,130 |
Length: | 0.8 | Actual | $13,942 |
District: | BROWNWOOD | Let Date: | Nov 2017 |
Highway: | FM 2231 | Let Status: | Actual |
Project ID: | STP 1702(798) | CSJ: | 2095-01-016 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | END OF PAVEMENT | Fund Cat: | 1 |
Limits To: | US 180 N | ESTIMATE: | $35,775 |
Length: | 1.4 | Actual | $33,125 |
District: | BROWNWOOD | Let Date: | Nov 2017 |
Highway: | FM 2247 | Let Status: | Actual |
Project ID: | STP 1702(798) | CSJ: | 2107-01-016 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | FS 2247 | Fund Cat: | 1 |
Limits To: | SH 16 | ESTIMATE: | $32,298 |
Length: | 0.5 | Actual | $30,197 |
District: | BROWNWOOD | Let Date: | Nov 2017 |
Highway: | FM 2247 | Let Status: | Actual |
Project ID: | STP 1702(798) | CSJ: | 2107-04-005 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | SH 36 | Fund Cat: | 1 |
Limits To: | FM 2247 | ESTIMATE: | $7,310 |
Length: | 0.2 | Actual | $6,403 |
District: | BROWNWOOD | Let Date: | Nov 2017 |
Highway: | FM 2524 | Let Status: | Actual |
Project ID: | NH 1702(799) | CSJ: | 2377-01-046 |
Description: | SEAL COAT | Handling Code: | |
Limits From: | NEAR WILLIS ST | Fund Cat: | 1 |
Limits To: | BROOKS AVE | ESTIMATE: | $52,781 |
Length: | 1.0 | Actual | $50,819 |
Proposal Request List Showing Order Bid List Addenda Bid Tabulations Award Status Back... | Totals for 0007-04-126 | ||
---|---|---|---|
Length: | 158.5 | ||
Estimate: | $6,620,272 | ||
Actual: | $6,070,588 | ||
CCSJ: 0127-01-031 |
|||
District: | BROWNWOOD | Let Date: | Apr 2018 |
Highway: | US 183 | Let Status: | Actual |
Project ID: | C 127-1-31 | CSJ: | 0127-01-031 |
Description: | REHABILITATE EXISTING ROADWAY | Handling Code: | |
Limits From: | CR 181 | Fund Cat: | 1 |
Limits To: | CR 173 | ESTIMATE: | $2,627,371 |
Length: | 4.1 | Actual | $2,366,163 |
District: | BROWNWOOD | Let Date: | Apr 2018 |
Highway: | US 183 | Let Status: | Actual |
Project ID: | STP 2018(807)HES | CSJ: | 0127-01-034 |
Description: | IMPROVE GUARDRAIL TO DESIGN STANDARDS, SAFETY TREAT FIXED | Handling Code: | |
Limits From: | CR 181 | Fund Cat: | 8 |
Limits To: | CR 173 | ESTIMATE: | $946,986 |
Length: | 4.2 | Actual | $846,859 |
Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 0127-01-031 | ||
Length: | 8.3 | ||
Estimate: | $3,574,358 | ||
Actual: | $3,213,022 | ||
CCSJ: 0127-02-043 |
|||
District: | BROWNWOOD | Let Date: | Apr 2018 |
Highway: | US 183 | Let Status: | Actual |
Project ID: | C 127-2-43 | CSJ: | 0127-02-043 |
Description: | ADD PASSING LANES | Handling Code: | |
Limits From: | CR 173 | Fund Cat: | 1 |
Limits To: | 5 MI. N OF RISING STAR NCL | ESTIMATE: | $4,923,750 |
Length: | 5.3 | Actual | $4,526,013 |
Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 0127-02-043 | ||
Length: | 5.3 | ||
Estimate: | $4,923,750 | ||
Actual: | $4,526,013 | ||
CCSJ: 0127-02-141 |
|||
District: | BROWNWOOD | Let Date: | Feb 2018 |
Highway: | US 183 | Let Status: | Actual |
Project ID: | STP 2018(542) | CSJ: | 0127-02-141 |
Description: | ADD PASSING LANES | Handling Code: | |
Limits From: | 5 MI. N OF RISING STAR NCL | Fund Cat: | 1 |
Limits To: | RISING STAR NCL | ESTIMATE: | $4,279,880 |
Length: | 5.0 | Actual | $3,673,746 |
List Showing Order Proposal Request Bid List Addenda Bid Tabulations Award Status Back... | Totals for 0127-02-141 | ||
Length: | 5 | ||
Estimate: | $4,279,880 | ||
Actual: | $3,673,746 | ||
CCSJ: 0127-02-142 |
|||
District: | BROWNWOOD | Let Date: | May 2018 |
Highway: | US 183 | Let Status: | Actual |
Project ID: | STP 2018(829) | CSJ: | 0127-02-142 |
Description: | RECONSTRUCT URBAN ROADWAY | Handling Code: | |
Limits From: | RISING STAR NCL | Fund Cat: | 1 |
Limits To: | NEAR SH 36 | ESTIMATE: | $5,261,163 |
Length: | 0.8 | Actual | $5,177,106 |
District: | BROWNWOOD | Let Date: | May 2018 |
Highway: | US 183 | Let Status: | Actual |
Project ID: | STP 2018(829) | CSJ: | 0127-02-143 |
Description: | RECONSTRUCT URBAN ROADWAY | Handling Code: | |
Limits From: | NEAR SH 36 | Fund Cat: | 1 |
Limits To: | NEAR RISING STAR SCL | ESTIMATE: | $5,695,329 |
Length: | 0.7 | Actual | $5,939,605 |
District: | BROWNWOOD | Let Date: | May 2018 |
Highway: | US 183 | Let Status: | Actual |
Project ID: | STP 2018(212) | CSJ: | 0127-02-146 |
Description: | ACQUISITION AND UTILITY ADJUSTMENTS | Handling Code: | |
Limits From: | RISING STAR NCL | Fund Cat: | ROW |
Limits To: | NEAR SH 36 | ESTIMATE: | $1,468,192 |
Length: | 0.8 | Actual | $3,038,242 |
District: | BROWNWOOD | Let Date: | May 2018 |
Highway: | US 183 | Let Status: | Actual |
Project ID: | STP 2018(211) | CSJ: | 0127-02-147 |
Description: | UTILITY ADJUSTMENTS | Handling Code: | |
Limits From: | NEAR SH 36 | Fund Cat: | ROW |
Limits To: | NEAR RISING STAR SCL | ESTIMATE: | $1,246,704 |
Length: | 0.7 | Actual | $2,732,059 |
Proposal Request List Showing Order Bid List Addenda Bid Tabulations Award Status Back... | Totals for 0127-02-142 | ||
Length: | 3 | ||
Estimate: | $13,671,388 | ||
Actual: | $16,887,012 |
Handling Code | Definition |
---|---|
XX | Project not processed through statewide letting |
TR | Transfer of funds |
LC | Project let through local entity |
LC | Project not charged against district apportionment |
Let Status | Definition |
---|---|
Tentative | Estimated letting date for this project |
Approved | Project has administrative approval to be let |
Actual | Project was let to contract |