Detail Letting Schedule for Hidalgo County (FY 2018)

Last Update: Monday, November 13, 2017
Hidalgo County (FY 2018)

CCSJ: 0255-07-141

District:PHARRLet Date:Oct 2017
Highway:IH 69CLet Status:Actual
Project ID:NH 1702(836)CSJ:0255-07-141
Description:SEAL COAT_(NB & SB FRONTAGE ROADS)Handling
Code:
 
Limits From:SH 107Fund Cat:1
Limits To:3.052 MI N OF SH 107ESTIMATE:$498,533
Length:3.1Actual$426,623
 
District:PHARRLet Date:Oct 2017
Highway:SH 345Let Status:Actual
Project ID:STP 1702(837)CSJ:0630-01-052
Description:SEAL COATHandling
Code:
 
Limits From:BUS 77Fund Cat:1
Limits To:FM 1561ESTIMATE:$257,311
Length:4.8Actual$232,643
 
District:PHARRLet Date:Oct 2017
Highway:FM 1419Let Status:Actual
Project ID:STP 1702(837)CSJ:1426-01-050
Description:SEAL COATHandling
Code:
 
Limits From:SH_4Fund Cat:1
Limits To:FM 511ESTIMATE:$173,615
Length:2.8Actual$161,035
 
District:PHARRLet Date:Oct 2017
Highway:FM 1924Let Status:Actual
Project ID:NH 1702(836)CSJ:1802-01-041
Description:SEAL COATHandling
Code:
 
Limits From:SH 107Fund Cat:1
Limits To:FM 492ESTIMATE:$313,781
Length:3.9Actual$280,655
 
District:PHARRLet Date:Oct 2017
Highway:FM 2061Let Status:Actual
Project ID:NH 1702(836)CSJ:1939-01-054
Description:SEAL COATHandling
Code:
 
Limits From:FM 1925Fund Cat:1
Limits To:SH 107ESTIMATE:$158,252
Length:2.5Actual$140,498
 
District:PHARRLet Date:Oct 2017
Highway:FM 2520Let Status:Actual
Project ID:STP 1702(837)CSJ:2356-01-024
Description:SEAL COATHandling
Code:
 
Limits From:FM 800Fund Cat:1
Limits To:IH-69EESTIMATE:$204,050
Length:3.4Actual$166,205
 
District:PHARRLet Date:Oct 2017
Highway:FM 509Let Status:Actual
Project ID:STP 1702(837)CSJ:2369-01-025
Description:SEAL COATHandling
Code:
 
Limits From:BUS 77Fund Cat:1
Limits To:FM 106ESTIMATE:$170,768
Length:2.9Actual$165,282
 
Proposal Request
Bid List
List Showing Order
Addenda
Bid Tabulations
Award Status
Back...
Totals for 0255-07-141
Length:23.4
Estimate:$1,776,311
Actual:$1,572,941

CCSJ: 0433-01-030

District:PHARRLet Date:Oct 2017
Highway:SH 186Let Status:Actual
Project ID:STP 1702(838)CSJ:0433-01-030
Description:REHABILITATE ROADWAY_(SUPER 2)Handling
Code:
 
Limits From:US 281Fund Cat:1
Limits To:HIDALGO/ WILLACY C.L.ESTIMATE:$13,005,934
Length:9.5Actual$12,133,439
 
Bid List
List Showing Order
Proposal Request
Addenda
Bid Tabulations
Award Status
Back...
Totals for 0433-01-030
Length:9.5
Estimate:$13,005,934
Actual:$12,133,439

CCSJ: 0698-02-052

District:PHARRLet Date:Dec 2017
Highway:FM 88Let Status:Approved
Project ID:STP 2018(336)HESCSJ:0698-02-052
Description:PROFILE EDGELINE MARKINGS, RAISED CENTERLINE RUMBLE STRIPSHandling
Code:
 
Limits From:WILLACY/ HIDALGO COUNTY LINEFund Cat:8
Limits To:FM 1422ESTIMATE:$116,817
Length:4.2Actual$0
 
District:PHARRLet Date:Dec 2017
Highway:US 83Let Status:Approved
Project ID:STP 2018(337)HESGCSJ:0038-07-071
Description:PROFILE EDGELINE MARKINGS, PROFILE CENTERLINE MARKINGSHandling
Code:
 
Limits From:FM 649Fund Cat:8
Limits To:FM 3167ESTIMATE:$109,782
Length:5.5Actual$0
 
District:PHARRLet Date:Dec 2017
Highway:SH 48Let Status:Approved
Project ID:STP 2018(337)HESGCSJ:0220-07-059
Description:PROFILE EDGELINE MARKINGS, PROFILE CENTERLINE MARKINGSHandling
Code:
 
Limits From:1.54 MI E OF SH 550Fund Cat:11
Limits To:5.25 MI E OF SH 550ESTIMATE:$72,912
Length:3.8Actual$0
 
District:PHARRLet Date:Dec 2017
Highway:SH 16Let Status:Approved
Project ID:STP 2018(336)HESCSJ:0517-06-033
Description:PROFILE EDGELINE MARKINGS, RAISED CENTERLINE RUMBLE STRIPSHandling
Code:
 
Limits From:FM 3073Fund Cat:8
Limits To:JIM HOGG/ZAPATA COUNTY LINEESTIMATE:$340,421
Length:25.3Actual$0
 
District:PHARRLet Date:Dec 2017
Highway:FM 88Let Status:Approved
Project ID:STP 2018(336)HESCSJ:0698-02-053
Description:PROFILE EDGELINE MARKINGS, RAISED CENTERLINE RUMBLE STRIPSHandling
Code:
 
Limits From:FM 2812Fund Cat:8
Limits To:FM 1925ESTIMATE:$58,794
Length:3.7Actual$0
 
Proposal Request
Back...
Totals for 0698-02-052
Length:42.5
Estimate:$698,725
Actual:

CCSJ: 0921-02-304

District:PHARRLet Date:Jul 2018
Highway:CSLet Status:Tentative
Project ID:BR 1402(233)CSJ:0921-02-304
Description:REPLACE BRIDGE AND RECONSTRUCT APPROACHESHandling
Code:
 
Limits From:ON 11TH ST, .70 MI E OF FM 493Fund Cat:6
Limits To:@ DRAINAGE DITCH,STR# AA03-48-002ESTIMATE:$520,000
Length:0.1Actual$0
 
Back...
Totals for 0921-02-304
Length:0.1
Estimate:$520,000
Actual:

CCSJ: 0921-02-305

District:PHARRLet Date:Jul 2018
Highway:CSLet Status:Tentative
Project ID:BR 2015(640)CSJ:0921-02-305
Description:REPLACE BRIDGE AND RECONSTRUCT APPROACHESHandling
Code:
 
Limits From:ON CHAPIN RD, .25 MI E OF FM 2061Fund Cat:6
Limits To:STR# E000-95-001 @ N MAIN DRAINAGEESTIMATE:$700,000
Length:0.1Actual$0
 
Back...
Totals for 0921-02-305
Length:0.1
Estimate:$700,000
Actual:

CCSJ: 0921-02-311

District:PHARRLet Date:May 2018
Highway:CSLet Status:Tentative
Project ID:STP 2016(494)MMCSJ:0921-02-311
Description:NEW LOCATION 2-LANE RURAL ROADWAYHandling
Code:
LC
Limits From:ON NORTH ALAMO RD., FROM FM 1925Fund Cat:7
Limits To:0.5 MI NORTHESTIMATE:$703,040
Length:0.5Actual$0
 
Back...
Totals for 0921-02-311
Length:0.5
Estimate:$703,040
Actual:

CCSJ: 0921-02-328

District:PHARRLet Date:May 2018
Highway:VALet Status:Tentative
Project ID:STP ( )MMCSJ:0921-02-328
Description:WIDEN TO 4 LANE ROADWAYHandling
Code:
 
Limits From:ON TAYLOR RD., FROM BUS 83Fund Cat:3
Limits To:0.36 MI S OF MILE 2ESTIMATE:$5,795,764
Length:1.6Actual$0
 
Back...
Totals for 0921-02-328
Length:1.6
Estimate:$5,795,764
Actual:

CCSJ: 0921-02-333

District:PHARRLet Date:Feb 2018
Highway:CSLet Status:Approved
Project ID:CBI 1702(648)CSJ:0921-02-333
Description:FEDERAL COMMERCIAL VEHICLE INSPECTION FACILITIES AT DONNAHandling
Code:
LC
Limits From:@ DONNA INTERNATIONAL BRIDGEFund Cat:3
Limits To:.ESTIMATE:$9,000,000
Length:0.1Actual$0
 
Back...
Totals for 0921-02-333
Length:0.1
Estimate:$9,000,000
Actual:

CCSJ: 0921-02-346

District:PHARRLet Date:Apr 2018
Highway:VALet Status:Tentative
Project ID:STP ( )TPCSJ:0921-02-346
Description:REGIONAL LINEAR HIKE & BIKE TRAIL (PH II)Handling
Code:
LC
Limits From:RIDGE RD. (PHARR)Fund Cat:9
Limits To:S 2ND ST. (MCALLEN)ESTIMATE:$5,600,000
Length:5.1Actual$0
 
Back...
Totals for 0921-02-346
Length:5.1
Estimate:$5,600,000
Actual:

CCSJ: 0921-02-352

District:PHARRLet Date:May 2018
Highway:CSLet Status:Tentative
Project ID:STP ( )MMCSJ:0921-02-352
Description:CONSTRUCT 4 LANE URBAN ROADWAYHandling
Code:
LC
Limits From:ON BICENTENNIAL BLVD., FROM SH 107Fund Cat:3
Limits To:TRENTON RD.ESTIMATE:$14,679,968
Length:2.9Actual$0
 
Back...
Totals for 0921-02-352
Length:2.9
Estimate:$14,679,968
Actual:

CCSJ: 0921-02-383

District:PHARRLet Date:Aug 2018
Highway:CSLet Status:Tentative
Project ID:CSJ:0921-02-383
Description:CONSTRUCT SECOND EXIT TO BORDER SAFETY INSPECTION FACILITYHandling
Code:
 
Limits From:@ PHARR/REYNOSA INT. BRIDGEFund Cat:3
Limits To:.ESTIMATE:$2,500,370
Length:0.1Actual$0
 
Back...
Totals for 0921-02-383
Length:0.1
Estimate:$2,500,370
Actual:

CCSJ: 0921-02-394

District:PHARRLet Date:Aug 2018
Highway:CSLet Status:Tentative
Project ID:CC 921-2-394CSJ:0921-02-394
Description:CONSTRUCTION OF COMMERCIAL FACILITIES, NORTHBOUND/EMPTY ANDHandling
Code:
 
Limits From:@ DONNA INTERNATIONAL BRIDGEFund Cat:3
Limits To:.ESTIMATE:$43,500,000
Length:1.2Actual$0
 
Back...
Totals for 0921-02-394
Length:1.2
Estimate:$43,500,000
Actual:

CCSJ: 1429-01-033

District:PHARRLet Date:Apr 2018
Highway:FM 2557Let Status:Tentative
Project ID:CC 1429-1-33CSJ:1429-01-033
Description:REHABILITATE ROADWAYHandling
Code:
 
Limits From:FLOODWAY BRIDGEFund Cat:3
Limits To:US 281ESTIMATE:$6,500,000
Length:4.5Actual$0
 
Back...
Totals for 1429-01-033
Length:4.5
Estimate:$6,500,000
Actual:

CCSJ: 1804-01-068

District:PHARRLet Date:May 2018
Highway:FM 1926Let Status:Tentative
Project ID:STP ( )MMCSJ:1804-01-068
Description:ADDITION OF NORTH AND SOUTH BOUND CENTER TURN LANESHandling
Code:
LC
Limits From:@ FM 1926 (23RD ST.)Fund Cat:7
Limits To:HACKBERRY AVE.ESTIMATE:$86,265
Length:0.1Actual$0
 
District:PHARRLet Date:May 2018
Highway:SH 336Let Status:Tentative
Project ID:NH ( )CSJ:0621-01-106
Description:ADDITION OF NORTH BOUND RIGHT TURN LANEHandling
Code:
LC
Limits From:INTERSECTION OF BUS 83Fund Cat:7
Limits To:135 FT S OF INTERSECTION OF BUS 83ESTIMATE:$77,958
Length:0.1Actual$0
 
District:PHARRLet Date:May 2018
Highway:FM 1926Let Status:Tentative
Project ID:STP ( )MMCSJ:1804-01-069
Description:ADDITION OF NORTH & SOUTHBOUND CENTER TURN LANESHandling
Code:
LC
Limits From:@ FM 1926 (23RD ST.) &Fund Cat:7
Limits To:KENDLEWOOD AVE.ESTIMATE:$94,785
Length:0.1Actual$0
 
District:PHARRLet Date:May 2018
Highway:FM 1926Let Status:Tentative
Project ID:STP ( )MMCSJ:1804-01-071
Description:ADDITION OF EAST, NORTH & SOUTHBOUND CENTER TURN LANESHandling
Code:
LC
Limits From:@ FM 1926 (23RD ST.) &Fund Cat:7
Limits To:EBONY AVE.ESTIMATE:$141,219
Length:0.1Actual$0
 
District:PHARRLet Date:May 2018
Highway:SS 115Let Status:Tentative
Project ID:STP ( )MMCSJ:1804-01-072
Description:ADDITION OF NORTH AND SOUTH BOUND CENTER TURN LANESHandling
Code:
LC
Limits From:AT FM 1926 (23RD ST.)Fund Cat:7
Limits To:AT SS 115 (23RD ST.)ESTIMATE:$116,618
Length:0.1Actual$0
 
Back...
Totals for 1804-01-068
Length:0.5
Estimate:$516,845
Actual:

CCSJ: 2094-01-038

District:PHARRLet Date:Jun 2018
Highway:FM 2220Let Status:Tentative
Project ID:STP 1602(275)MMCSJ:2094-01-038
Description:WIDEN TO 6 LANEHandling
Code:
 
Limits From:MILE 5 ROADFund Cat:1
Limits To:FM 1924ESTIMATE:$14,711,591
Length:2.2Actual$0
 
Back...
Totals for 2094-01-038
Length:2.2
Estimate:$14,711,591
Actual:

Handling CodeDefinition
XXProject not processed through statewide letting
TRTransfer of funds
LCProject let through local entity
LCProject not charged against district apportionment



Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract