Detail Letting Schedule for Hill County (FY 2018)
Hill County (FY 2018) |
CCSJ: 0014-05-039 |
|||
District: | WACO | Let Date: | Jul 2018 |
Highway: | SH 81 | Let Status: | Actual |
Project ID: | C 14-5-39 | CSJ: | 0014-05-039 |
Description: | MISC SPOT PAVEMENT REPAIRS | Handling Code: | |
Limits From: | FM 66 | Fund Cat: | 1 |
Limits To: | . | ESTIMATE: | $180,362 |
Length: | 3.4 | Actual | $204,361 |
District: | WACO | Let Date: | Jul 2018 |
Highway: | SH 81 | Let Status: | Actual |
Project ID: | C 14-6-42 | CSJ: | 0014-06-042 |
Description: | MISC SPOT PAVEMENT REPAIRS | Handling Code: | |
Limits From: | . | Fund Cat: | 1 |
Limits To: | HILLSBORO CONCRETE | ESTIMATE: | $119,683 |
Length: | 5.1 | Actual | $116,091 |
District: | WACO | Let Date: | Jul 2018 |
Highway: | SH 14 | Let Status: | Actual |
Project ID: | C 93-5-50 | CSJ: | 0093-05-050 |
Description: | MISC SPOT PAVEMENT REPAIRS | Handling Code: | |
Limits From: | SH 164 | Fund Cat: | 1 |
Limits To: | THORNTON | ESTIMATE: | $89,750 |
Length: | 8.6 | Actual | $89,878 |
District: | WACO | Let Date: | Jul 2018 |
Highway: | SH 14 | Let Status: | Actual |
Project ID: | C 93-6-24 | CSJ: | 0093-06-024 |
Description: | MISC SPOT PAVEMENT REPAIRS | Handling Code: | |
Limits From: | THORNTON | Fund Cat: | 1 |
Limits To: | SH 7 | ESTIMATE: | $76,463 |
Length: | 7.5 | Actual | $76,595 |
District: | WACO | Let Date: | Jul 2018 |
Highway: | SH 14 | Let Status: | Actual |
Project ID: | C 93-7-22 | CSJ: | 0093-07-022 |
Description: | MISC SPOT PAVEMENT REPAIRS | Handling Code: | |
Limits From: | LIMESTONE COUNTY LINE | Fund Cat: | 1 |
Limits To: | ROBERTSON COUNTY LINE | ESTIMATE: | $300,963 |
Length: | 6.9 | Actual | $316,217 |
District: | WACO | Let Date: | Jul 2018 |
Highway: | FM 3370 | Let Status: | Actual |
Project ID: | C 209-12-5 | CSJ: | 0209-12-005 |
Description: | MISC SPOT PAVEMENT REPAIRS | Handling Code: | |
Limits From: | FM 310 | Fund Cat: | 1 |
Limits To: | FM 1133 | ESTIMATE: | $249,952 |
Length: | 4.0 | Actual | $245,379 |
District: | WACO | Let Date: | Jul 2018 |
Highway: | SH 7 | Let Status: | Actual |
Project ID: | C 382-2-37 | CSJ: | 0382-02-037 |
Description: | MISC SPOT PAVEMENT REPAIRS | Handling Code: | |
Limits From: | SH 6 | Fund Cat: | 1 |
Limits To: | LIMESTONE COUNTY LINE | ESTIMATE: | $300,963 |
Length: | 13.3 | Actual | $316,217 |
District: | WACO | Let Date: | Jul 2018 |
Highway: | SH 164 | Let Status: | Actual |
Project ID: | C 413-2-33 | CSJ: | 0413-02-033 |
Description: | MISC SPOT PAVEMENT REPAIRS | Handling Code: | |
Limits From: | MCLENNAN COUNTY LINE | Fund Cat: | 1 |
Limits To: | SH 14 | ESTIMATE: | $56,407 |
Length: | 17.0 | Actual | $55,209 |
District: | WACO | Let Date: | Jul 2018 |
Highway: | FM 73 | Let Status: | Actual |
Project ID: | C 673-1-22 | CSJ: | 0673-01-022 |
Description: | MISC SPOT PAVEMENT REPAIRS | Handling Code: | |
Limits From: | US 84 | Fund Cat: | 1 |
Limits To: | SH 171 | ESTIMATE: | $128,440 |
Length: | 11.7 | Actual | $134,971 |
District: | WACO | Let Date: | Jul 2018 |
Highway: | FM 937 | Let Status: | Actual |
Project ID: | C 1191-4-25 | CSJ: | 1191-04-025 |
Description: | MISC SPOT PAVEMENT REPAIRS | Handling Code: | |
Limits From: | SH 164 | Fund Cat: | 1 |
Limits To: | ROBERTSON COUNTY LINE | ESTIMATE: | $56,407 |
Length: | 16.9 | Actual | $55,209 |
District: | WACO | Let Date: | Jul 2018 |
Highway: | FM 1713 | Let Status: | Actual |
Project ID: | C 2547-1-13 | CSJ: | 2547-01-013 |
Description: | MISC SPOT PAVEMENT REPAIRS | Handling Code: | |
Limits From: | SPUR 1713 | Fund Cat: | 1 |
Limits To: | FM 933 | ESTIMATE: | $84,866 |
Length: | 3.8 | Actual | $83,035 |
District: | WACO | Let Date: | Jul 2018 |
Highway: | FM 1713 | Let Status: | Actual |
Project ID: | C 2547-1-14 | CSJ: | 2547-01-014 |
Description: | MISC SPOT PAVEMENT REPAIRS | Handling Code: | |
Limits From: | END OF MAINTENANCE | Fund Cat: | 1 |
Limits To: | FM 1713 | ESTIMATE: | $27,709 |
Length: | 0.5 | Actual | $26,062 |
District: | WACO | Let Date: | Jul 2018 |
Highway: | FM 2959 | Let Status: | Actual |
Project ID: | C 3030-1-9 | CSJ: | 3030-01-009 |
Description: | MISC SPOT PAVEMENT REPAIRS | Handling Code: | |
Limits From: | CR 4235 | Fund Cat: | 1 |
Limits To: | US 77 | ESTIMATE: | $115,770 |
Length: | 4.1 | Actual | $114,683 |
District: | WACO | Let Date: | Jul 2018 |
Highway: | FM 1534 | Let Status: | Actual |
Project ID: | C 3498-1-5 | CSJ: | 3498-01-005 |
Description: | MISC SPOT PAVEMENT REPAIRS | Handling Code: | |
Limits From: | FM 1947 | Fund Cat: | 1 |
Limits To: | FM 933 | ESTIMATE: | $169,499 |
Length: | 4.6 | Actual | $165,681 |
Proposal Request Bid List List Showing Order Addenda Bid Tabulations Award Status Back... | Totals for 0014-05-039 | ||
---|---|---|---|
Length: | 107.4 | ||
Estimate: | $1,957,234 | ||
Actual: | $1,999,585 |
Handling Code | Definition |
---|---|
XX | Project not processed through statewide letting |
TR | Transfer of funds |
LC | Project let through local entity |
LC | Project not charged against district apportionment |
Let Status | Definition |
---|---|
Tentative | Estimated letting date for this project |
Approved | Project has administrative approval to be let |
Actual | Project was let to contract |