Detail Letting Schedule for Hopkins County (FY 2018)

Last Update: Monday, August 27, 2018
Hopkins County (FY 2018)

CCSJ: 0009-18-020

District:PARISLet Date:Dec 2017
Highway:BU 67-VLet Status:Actual
Project ID:STP 2018(474)CSJ:0009-18-020
Description:SEAL COATHandling
Code:
 
Limits From:IH 30Fund Cat:1
Limits To:SH 19ESTIMATE:$644,892
Length:2.9Actual$1,233,385
 
District:PARISLet Date:Dec 2017
Highway:US 82Let Status:Actual
Project ID:NH 2018(369)CSJ:0045-12-082
Description:SEAL COATHandling
Code:
 
Limits From:FM 410Fund Cat:1
Limits To:SH 37 NORTHESTIMATE:$607,308
Length:12.4Actual$609,344
 
District:PARISLet Date:Dec 2017
Highway:US 82Let Status:Actual
Project ID:NH 2018(369)CSJ:0045-18-035
Description:SEAL COATHandling
Code:
 
Limits From:COOKE COUNTY LINE (EB LANES)Fund Cat:1
Limits To:FM 901ESTIMATE:$295,957
Length:5.9Actual$296,360
 
District:PARISLet Date:Dec 2017
Highway:US 82Let Status:Actual
Project ID:NH 2018(369)CSJ:0045-18-036
Description:SEAL COATHandling
Code:
 
Limits From:COOKE COUNTY LINE (WB LANES)Fund Cat:1
Limits To:FM 901ESTIMATE:$313,730
Length:5.9Actual$314,274
 
District:PARISLet Date:Dec 2017
Highway:US 69Let Status:Actual
Project ID:NH 2018(369)CSJ:0047-01-067
Description:SEAL COATHandling
Code:
 
Limits From:STATE LINE (WFR)Fund Cat:1
Limits To:US 75ESTIMATE:$34,063
Length:0.9Actual$33,902
 
District:PARISLet Date:Dec 2017
Highway:SS 503Let Status:Actual
Project ID:NH 2018(369)CSJ:0047-02-142
Description:SEAL COATHandling
Code:
 
Limits From:SH 91 (NFR)Fund Cat:1
Limits To:US 69ESTIMATE:$40,245
Length:1.8Actual$40,956
 
District:PARISLet Date:Dec 2017
Highway:SS 503Let Status:Actual
Project ID:NH 2018(369)CSJ:0047-02-143
Description:SEAL COATHandling
Code:
 
Limits From:SH 91 (SFR)Fund Cat:1
Limits To:US 69ESTIMATE:$42,483
Length:1.8Actual$43,256
 
District:PARISLet Date:Dec 2017
Highway:SS 503Let Status:Actual
Project ID:NH 2018(369)CSJ:0047-02-144
Description:SEAL COATHandling
Code:
 
Limits From:SH 91 (EB LANES)Fund Cat:1
Limits To:US 69ESTIMATE:$74,101
Length:1.9Actual$75,632
 
District:PARISLet Date:Dec 2017
Highway:SS 503Let Status:Actual
Project ID:NH 2018(369)CSJ:0047-02-145
Description:SEAL COATHandling
Code:
 
Limits From:SH 91 (WB LANES)Fund Cat:1
Limits To:US 69ESTIMATE:$79,013
Length:1.9Actual$80,818
 
District:PARISLet Date:Dec 2017
Highway:US 75Let Status:Actual
Project ID:NH 2018(369)CSJ:0047-18-078
Description:SEAL COATHandling
Code:
 
Limits From:US 69 (NFR)Fund Cat:1
Limits To:LOY LAKE RDESTIMATE:$201,810
Length:9.8Actual$204,510
 
District:PARISLet Date:Dec 2017
Highway:US 75Let Status:Actual
Project ID:NH 2018(369)CSJ:0047-18-079
Description:SEAL COATHandling
Code:
 
Limits From:US 69 (SFR)Fund Cat:1
Limits To:LOY LAKE RDESTIMATE:$294,705
Length:10.6Actual$301,140
 
District:PARISLet Date:Dec 2017
Highway:SS 503Let Status:Actual
Project ID:NH 2018(369)CSJ:0047-19-014
Description:SEAL COATHandling
Code:
 
Limits From:US 75 (NFR)Fund Cat:1
Limits To:SH 91ESTIMATE:$59,360
Length:1.2Actual$33,919
 
District:PARISLet Date:Dec 2017
Highway:SS 503Let Status:Actual
Project ID:NH 2018(369)CSJ:0047-19-015
Description:SEAL COATHandling
Code:
 
Limits From:US 75 (SFR)Fund Cat:1
Limits To:SH 91ESTIMATE:$49,065
Length:1.5Actual$49,929
 
District:PARISLet Date:Dec 2017
Highway:US 377Let Status:Actual
Project ID:STP 2018(368)CSJ:0081-10-046
Description:SEAL COATHandling
Code:
 
Limits From:STATE LINEFund Cat:1
Limits To:FM 901 SOUTHESTIMATE:$253,796
Length:5.2Actual$254,872
 
District:PARISLet Date:Dec 2017
Highway:SH 50Let Status:Actual
Project ID:STP 2018(368)CSJ:0082-01-017
Description:SEAL COATHandling
Code:
 
Limits From:SH 34Fund Cat:1
Limits To:HUNT COUNTY LINEESTIMATE:$78,295
Length:2.3Actual$78,088
 
District:PARISLet Date:Dec 2017
Highway:SH 11Let Status:Actual
Project ID:STP 2018(368)CSJ:0083-01-018
Description:SEAL COATHandling
Code:
 
Limits From:BS 11Fund Cat:1
Limits To:HOPKINS COUNTY LINEESTIMATE:$109,352
Length:1.5Actual$111,040
 
District:PARISLet Date:Dec 2017
Highway:SH 11Let Status:Actual
Project ID:STP 2018(368)CSJ:0083-02-055
Description:SEAL COATHandling
Code:
 
Limits From:CR 4717Fund Cat:1
Limits To:5.45 MI E OF FM 2653 (CR 4707)ESTIMATE:$213,289
Length:4.7Actual$214,902
 
District:PARISLet Date:Dec 2017
Highway:SH 11Let Status:Actual
Project ID:STP 2018(368)CSJ:0083-04-032
Description:SEAL COATHandling
Code:
 
Limits From:1.6 MI E OF FM 269 NFund Cat:1
Limits To:FRANKLIN COUNTY LINEESTIMATE:$205,758
Length:4.6Actual$206,982
 
District:PARISLet Date:Dec 2017
Highway:SH 11Let Status:Actual
Project ID:STP 2018(368)CSJ:0083-05-017
Description:SEAL COATHandling
Code:
 
Limits From:HOPKINS COUNTY LINEFund Cat:1
Limits To:WOOD COUNTY LINEESTIMATE:$66,736
Length:1.2Actual$66,839
 
District:PARISLet Date:Dec 2017
Highway:SH 19Let Status:Actual
Project ID:STP 2018(368)CSJ:0108-09-048
Description:SEAL COATHandling
Code:
 
Limits From:SH 11 SOUTHFund Cat:1
Limits To:RAINS COUNTY LINEESTIMATE:$490,347
Length:10.2Actual$491,414
 
District:PARISLet Date:Dec 2017
Highway:SH 224Let Status:Actual
Project ID:STP 2018(368)CSJ:0136-01-065
Description:SEAL COATHandling
Code:
 
Limits From:SH 34Fund Cat:1
Limits To:FM 2874ESTIMATE:$639,514
Length:12.5Actual$644,189
 
District:PARISLet Date:Dec 2017
Highway:SH 224Let Status:Actual
Project ID:STP 2018(474)CSJ:0136-02-037
Description:SEAL COATHandling
Code:
 
Limits From:FM 2874Fund Cat:1
Limits To:SH 24ESTIMATE:$138,672
Length:2.6Actual$139,381
 
District:PARISLet Date:Dec 2017
Highway:SH 34Let Status:Actual
Project ID:STP 2018(368)CSJ:0174-01-047
Description:SEAL COATHandling
Code:
 
Limits From:FANNIN COUNTY LINEFund Cat:1
Limits To:SH 224ESTIMATE:$685,207
Length:16.4Actual$688,198
 
District:PARISLet Date:Dec 2017
Highway:BU 69-DLet Status:Actual
Project ID:STP 2018(474)CSJ:0202-05-048
Description:SEAL COATHandling
Code:
 
Limits From:US 69 NORTHFund Cat:1
Limits To:SH 34 NORTHESTIMATE:$154,519
Length:2.7Actual$157,487
 
District:PARISLet Date:Dec 2017
Highway:US 69Let Status:Actual
Project ID:STP 2018(368)CSJ:0202-05-049
Description:SEAL COATHandling
Code:
 
Limits From:0.5 MI SOUTH FM 272Fund Cat:1
Limits To:BU 69 DESTIMATE:$403,659
Length:8.3Actual$403,629
 
District:PARISLet Date:Dec 2017
Highway:FM 1417Let Status:Actual
Project ID:STP 2018(368)CSJ:0202-08-061
Description:SEAL COATHandling
Code:
 
Limits From:FM 996Fund Cat:1
Limits To:FM 691ESTIMATE:$163,650
Length:3.1Actual$166,994
 
District:PARISLet Date:Dec 2017
Highway:US 69Let Status:Actual
Project ID:STP 2018(474)CSJ:0202-10-024
Description:SEAL COATHandling
Code:
 
Limits From:BU 69 DFund Cat:1
Limits To:US 380ESTIMATE:$142,311
Length:2.9Actual$143,351
 
District:PARISLet Date:Dec 2017
Highway:SH 78Let Status:Actual
Project ID:STP 2018(368)CSJ:0279-02-043
Description:SEAL COATHandling
Code:
 
Limits From:RED RIVERFund Cat:1
Limits To:FM 273ESTIMATE:$399,270
Length:9.5Actual$398,569
 
District:PARISLet Date:Dec 2017
Highway:SH 78Let Status:Actual
Project ID:STP 2018(368)CSJ:0280-01-021
Description:SEAL COATHandling
Code:
 
Limits From:FM 896Fund Cat:1
Limits To:COLLIN COUNTY LINEESTIMATE:$252,006
Length:7.8Actual$250,293
 
District:PARISLet Date:Dec 2017
Highway:US 69Let Status:Actual
Project ID:STP 2018(368)CSJ:0410-02-037
Description:SEAL COATHandling
Code:
 
Limits From:SH 56Fund Cat:1
Limits To:0.1 MI SOUTH OF FM 151ESTIMATE:$287,347
Length:6.9Actual$288,817
 
District:PARISLet Date:Dec 2017
Highway:FM 6Let Status:Actual
Project ID:STP 2018(368)CSJ:0619-02-014
Description:SEAL COATHandling
Code:
 
Limits From:COLLIN COUNTY LINEFund Cat:1
Limits To:SH 66ESTIMATE:$125,303
Length:3.4Actual$124,737
 
District:PARISLet Date:Dec 2017
Highway:FM 196Let Status:Actual
Project ID:STP 2018(368)CSJ:0680-01-017
Description:SEAL COATHandling
Code:
 
Limits From:FM 1501Fund Cat:1
Limits To:CR 16300ESTIMATE:$174,640
Length:5.9Actual$173,372
 
District:PARISLet Date:Dec 2017
Highway:FM 900Let Status:Actual
Project ID:STP 2018(368)CSJ:0680-04-014
Description:SEAL COATHandling
Code:
 
Limits From:FM 69Fund Cat:1
Limits To:US 67ESTIMATE:$253,934
Length:8.3Actual$252,605
 
District:PARISLet Date:Dec 2017
Highway:FM 79Let Status:Actual
Project ID:STP 2018(368)CSJ:0688-02-060
Description:SEAL COATHandling
Code:
 
Limits From:CR 34250Fund Cat:1
Limits To:US 82 / LP 286ESTIMATE:$367,533
Length:9.3Actual$367,797
 
District:PARISLet Date:Dec 2017
Highway:SH 91Let Status:Actual
Project ID:STP 2018(474)CSJ:0705-01-028
Description:SEAL COATHandling
Code:
 
Limits From:STATE LINEFund Cat:1
Limits To:MARTIN L KING DRIVEESTIMATE:$183,762
Length:4.3Actual$186,885
 
District:PARISLet Date:Dec 2017
Highway:SH 37Let Status:Actual
Project ID:STP 2018(368)CSJ:0722-02-041
Description:SEAL COATHandling
Code:
 
Limits From:US 82Fund Cat:1
Limits To:FM 411ESTIMATE:$403,336
Length:9.5Actual$405,472
 
District:PARISLet Date:Dec 2017
Highway:FM 514Let Status:Actual
Project ID:STP 2018(368)CSJ:0725-03-011
Description:SEAL COATHandling
Code:
 
Limits From:FM 2081Fund Cat:1
Limits To:WOOD COUNTY LINEESTIMATE:$54,561
Length:1.8Actual$54,323
 
District:PARISLet Date:Dec 2017
Highway:FM 273Let Status:Actual
Project ID:STP 2018(368)CSJ:0765-03-024
Description:SEAL COATHandling
Code:
 
Limits From:FM 1396Fund Cat:1
Limits To:FM 2029ESTIMATE:$407,335
Length:11.6Actual$405,628
 
District:PARISLet Date:Dec 2017
Highway:FM 69Let Status:Actual
Project ID:STP 2018(368)CSJ:0766-04-019
Description:SEAL COATHandling
Code:
 
Limits From:SH 11Fund Cat:1
Limits To:FM 269ESTIMATE:$202,005
Length:7.5Actual$201,350
 
District:PARISLet Date:Dec 2017
Highway:FM 513Let Status:Actual
Project ID:STP 2018(368)CSJ:0768-02-022
Description:SEAL COATHandling
Code:
 
Limits From:IH 30 SFRFund Cat:1
Limits To:US 69ESTIMATE:$312,458
Length:9.3Actual$310,523
 
District:PARISLet Date:Dec 2017
Highway:FM 197Let Status:Actual
Project ID:STP 2018(368)CSJ:0769-01-029
Description:SEAL COATHandling
Code:
 
Limits From:FM 79Fund Cat:1
Limits To:PARSON CR (1.1 MI E OF FM 1499)ESTIMATE:$287,341
Length:9.0Actual$285,393
 
District:PARISLet Date:Dec 2017
Highway:FM 197Let Status:Actual
Project ID:STP 2018(368)CSJ:0769-01-030
Description:SEAL COATHandling
Code:
 
Limits From:FM 906Fund Cat:1
Limits To:US 271ESTIMATE:$116,844
Length:3.9Actual$116,111
 
District:PARISLet Date:Dec 2017
Highway:SH 37Let Status:Actual
Project ID:STP 2018(368)CSJ:0772-03-020
Description:SEAL COATHandling
Code:
 
Limits From:FM 411Fund Cat:1
Limits To:US 271ESTIMATE:$192,337
Length:4.5Actual$193,601
 
District:PARISLet Date:Dec 2017
Highway:FM 1500Let Status:Actual
Project ID:STP 2018(368)CSJ:1455-01-011
Description:SEAL COATHandling
Code:
 
Limits From:FM 1499Fund Cat:1
Limits To:FM 79ESTIMATE:$77,980
Length:2.5Actual$77,286
 
District:PARISLet Date:Dec 2017
Highway:FM 1499Let Status:Actual
Project ID:STP 2018(368)CSJ:1881-01-017
Description:SEAL COATHandling
Code:
 
Limits From:FM 197Fund Cat:1
Limits To:SP 1499ESTIMATE:$184,967
Length:6.7Actual$184,638
 
District:PARISLet Date:Dec 2017
Highway:FM 1499Let Status:Actual
Project ID:C 1881-1-18CSJ:1881-01-018
Description:SEAL COATHandling
Code:
 
Limits From:END OF MAINTENACEFund Cat:1
Limits To:FM 197ESTIMATE:$57,890
Length:2.5Actual$57,691
 
District:PARISLet Date:Dec 2017
Highway:FM 1417Let Status:Actual
Project ID:STP 2018(474)CSJ:2456-01-008
Description:SEAL COATHandling
Code:
 
Limits From:FM 120Fund Cat:1
Limits To:FM 996ESTIMATE:$44,799
Length:0.8Actual$45,413
 
District:PARISLet Date:Dec 2017
Highway:FM 196Let Status:Actual
Project ID:STP 2018(368)CSJ:2490-01-010
Description:SEAL COATHandling
Code:
 
Limits From:CR 16300Fund Cat:1
Limits To:RED RIVER COUNTY LINEESTIMATE:$78,081
Length:2.8Actual$77,706
 
District:PARISLet Date:Dec 2017
Highway:FM 87Let Status:Actual
Project ID:STP 2018(368)CSJ:3600-01-007
Description:SEAL COATHandling
Code:
 
Limits From:US 82Fund Cat:1
Limits To:SH 56ESTIMATE:$108,780
Length:2.4Actual$109,175
 
Proposal Request
Bid List
List Showing Order
Bid Tabulations
Award Status
Back...
Totals for 0009-18-020
Length:266.9
Estimate:$11,054,344
Actual:$11,652,174

CCSJ: 0083-03-055

District:PARISLet Date:Aug 2018
Highway:SH 154Let Status:Actual
Project ID:C 83-3-55CSJ:0083-03-055
Description:MILL AND INLAYHandling
Code:
 
Limits From:BU 67 VFund Cat:1
Limits To:SH 11ESTIMATE:$2,323,708
Length:2.1Actual$2,191,743
 
District:PARISLet Date:Aug 2018
Highway:SH 19Let Status:Actual
Project ID:C 108-9-46CSJ:0108-09-046
Description:MILL AND INLAYHandling
Code:
 
Limits From:SH 154Fund Cat:1
Limits To:BU 67 VESTIMATE:$1,794,300
Length:3.9Actual$1,731,001
 
District:PARISLet Date:Aug 2018
Highway:SH 154Let Status:Actual
Project ID:C 400-2-50CSJ:0400-02-050
Description:MILL AND INLAYHandling
Code:
 
Limits From:LOOP 301Fund Cat:1
Limits To:BU 67 VESTIMATE:$1,529,884
Length:2.7Actual$1,366,354
 
Proposal Request
List Showing Order
Bid List
Bid Tabulations
Back...
Totals for 0083-03-055
Length:8.7
Estimate:$5,647,893
Actual:$5,289,098

CCSJ: 0901-28-085

District:PARISLet Date:Jul 2018
Highway:CRLet Status:Actual
Project ID:BR 2016(211)CSJ:0901-28-085
Description:BRIDGE REPLACEMENTHandling
Code:
 
Limits From:CR 578-1Fund Cat:6
Limits To:AT BLACKS CREEKESTIMATE:$275,981
Length:0.1Actual$253,519
 
Proposal Request
Bid List
List Showing Order
Bid Tabulations
Award Status
Back...
Totals for 0901-28-085
Length:0.1
Estimate:$275,981
Actual:$253,519

CCSJ: 0901-28-090

District:PARISLet Date:Dec 2017
Highway:VALet Status:Actual
Project ID:STP 2017(411)TAPSCSJ:0901-28-090
Description:CONSTRUCT SIDEWALK AND SHARED USE PATHHandling
Code:
XX
Limits From:BU 67VFund Cat:3
Limits To:SH 154 (CONNALLY ST)ESTIMATE:$774,883
Length:1.8Actual$919,861
 
Back...
Totals for 0901-28-090
Length:1.8
Estimate:$774,883
Actual:$919,861

Handling CodeDefinition
XXProject not processed through statewide letting
TRTransfer of funds
LCProject let through local entity
LCProject not charged against district apportionment



Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract