Detail Letting Schedule for Hudspeth County (FY 2018)

Last Update: Monday, November 13, 2017
Hudspeth County (FY 2018)

CCSJ: 0002-07-049

District:EL PASOLet Date:Aug 2018
Highway:IH 10Let Status:Tentative
Project ID:BR ( )CSJ:0002-07-049
Description:REPLACE BRIDGES AND APPROACHESHandling
Code:
 
Limits From:1.17 MI W OF RM 1111Fund Cat:6
Limits To:0.01 MI E OF RM 1111ESTIMATE:$4,100,000
Length:0.8Actual$0
 
District:EL PASOLet Date:Aug 2018
Highway:IH 10Let Status:Tentative
Project ID:BR ( )CSJ:0002-08-054
Description:BRIDGE APPROACH AND ROADWAY WORKHandling
Code:
 
Limits From:0.01 MI E OF RM 1111Fund Cat:1
Limits To:0.89 MI E OF RM 1111ESTIMATE:$400,000
Length:1.2Actual$0
 
Back...
Totals for 0002-07-049
Length:2
Estimate:$4,500,000
Actual:

CCSJ: 0374-05-027

District:EL PASOLet Date:Feb 2018
Highway:US 62Let Status:Approved
Project ID:BR 2018(524)CSJ:0374-05-027
Description:BOX CULVERT STRUCTURAL REPAIRHandling
Code:
 
Limits From:4.387 MI W OF RM 2317Fund Cat:6
Limits To:3.387 MI W OF RM 2317ESTIMATE:$76,981
Length:1.0Actual$0
 
Back...
Totals for 0374-05-027
Length:1
Estimate:$76,981
Actual:

CCSJ: 0374-07-026

District:EL PASOLet Date:Dec 2017
Highway:US 62Let Status:Approved
Project ID:NH 2018(340)CSJ:0374-07-026
Description:INTERSECTION/ROADWAY REHABILITATIONHandling
Code:
 
Limits From:1 MI W OF FM 1437Fund Cat:1
Limits To:1 MI E OF FM 1437ESTIMATE:$3,247,622
Length:2.0Actual$0
 
Proposal Request
Back...
Totals for 0374-07-026
Length:2
Estimate:$3,247,622
Actual:

Handling CodeDefinition
XXProject not processed through statewide letting
TRTransfer of funds
LCProject let through local entity
LCProject not charged against district apportionment



Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract