Letting Schedule for Atlanta District (FY 2018)

Last Update: Monday, August 27, 2018
Atlanta District (FY 2018)
Bowie | Camp | Cass | Harrison | Morris | Panola | Titus | Upshur |

Bowie County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0010-13-094US 67ActualMar 2018$1,101,2518INSTALL CONTINUOUS TURN LANE, MILLED EDGELINE RUMBLE STRIPS0.0
1231-01-071FM 989TentativeAug 2018$250,0008RAILROAD CROSSING UPGRADES0.0
0919-19-081CSTentativeAug 2018$250,0008RAILROAD CROSSING UPGRADES0.0
0218-01-095US 59ActualDec 2017$185,7408INSTALL ADVANCE INTERSECTION WARNING SIGNALS AND SIGNS,0.0
0217-02-035US 71ActualNov 2017$397,2093IMPROVE TRAFFIC SIGNAL, INSTALL ADVANCE WARNING SIGNS,0.0
0010-19-010FM 991ActualSep 2017$2,935,6688PROFILE CENTERLINE & EDGELINE MARKINGS0.0
0010-11-070US 67ActualOct 2017$3,572,0001SEAL COAT AND PAVEMENT MARKINGS0.0
0010-19-012FM 991ActualMar 2018$1,975,6198SAFETY TREAT FIXED OBJECTS0.0

Camp County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0919-21-029CSActualOct 2017$332,9063CONSTRUCT SIDEWALKS TO CONNECT DOWNTOWN TO SCHOOL, PARK &0.0

Cass County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0919-00-078VAActualJul 2018$356,00012018 DISTRICT SEAL COAT PAVEMENT MARKINGS0.0
0946-01-044FM 250ActualJun 2018$250,0008RAILROAD CROSSING UPGRADES0.0
0945-03-009FM 3129ActualJun 2018$11,184,8781IMPROVE GUARDRAIL TO DESIGN STANDARDS & SAFETY TREAT FIXED2.0
0277-03-027SH 77ActualMar 2018$3,702,6778TEXTURIZE SHOULDERS & CL TEXTURING0.0
0919-14-027CRTentativeAug 2018$08RAILROAD CROSSING UPGRADES0.0

Harrison County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0843-06-021FM 450ActualMay 2018$810,7198RAILROAD CROSSING UPGRADES0.0
0495-08-110IH 20ActualMay 2018$1,975,5996BRIDGE PREVENTATIVE MAINTENANCE0.0
0919-03-061CRTentativeAug 2018$250,0008RAILROAD CROSSING UPGRADES0.0
0096-07-045US 80ActualJun 2018$872,7951IMPROVE TRAFFIC SIGNAL AND ADD LEFT TURN LANE0.0
0096-07-049US 80ActualOct 2017$931,2008IMPROVE GUARDRAIL TO DESIGN STANDARDS0.0
0096-07-047US 80ActualSep 2017$471,1351INSTALL TRAFFIC SIGNAL0.0
0919-03-053VAActualJan 2018$1,461,07410REHABILITATE ROADS,PARKING LOTS & CAMPSITES PULLOUTS IN0.0
0063-01-095US 59ActualJan 2018$2,928,5201RESURFACE EXISTING 4-LANE HIGHWAY0.0

Morris County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0392-01-073US 259ActualJul 2018$6,819,0001RESURFACE EXISTING 4-LANE ROADWAY0.0

Panola County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0393-03-034SH 149ActualDec 2017$4,561,9941REHABILITATE EXISTING 2-LANE HIGHWAY0.0
0063-10-017US 59ActualApr 2018$5,079,22911RESURFACE EXISTING 4-LANE HIGHWAY1.0
0207-04-036SH 43ActualJan 2018$2,624,8871RESURFACE EXISTING 2-LANE HIGHWAY0.0
0063-10-013US 59ActualDec 2017$263,5868SAFETY LIGHTING AT INTERSECTION0.0
0394-03-040FM 699ActualJun 2018$1,232,9171RECONSTRUCT INTERSECTION WITH CONCRETE PAVING0.0

Titus County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0010-06-043US 67ActualApr 2018$1,396,9268PROFILE CENTERLINE MARKINGS0.0
0221-05-090US 271ActualMar 2018$2,629,2241RESURFACE EXISTING 2-LANE HIGHWAY0.0
3404-01-016FM 3417ActualApr 2018$3,929,9611PROVIDE ADDITIONAL PAVED SURFACE WIDTH, MILLED EDGELINE0.0
0610-03-085IH 30ActualJan 2018$64,8906BRIDGE PREVENTATIVE MAINTENANCE0.0

Upshur County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0248-05-064US 271ActualMay 2018$5,482,1941RESURFACE EXISTING 4-LANE HIGHWAY0.0


Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract