CCSJ | County/ District | Highway | Let Status | Contract Cost | Fund Cat | Description | DBE Goal |
---|---|---|---|---|---|---|---|
0517-01-043 | Atascosa/ San Antonio | SH 16 | Actual | $21,209,226 | 11 | REHAB AND WIDEN TO PROVIDE OPERATIONAL IMPROVEMENTS | 2.0 |
0271-02-055 | Austin/ Yoakum | IH 10 | Actual | $249,353,725 | 1 | UPGRADING OF A FREEWAY FACILITY CONSISTING OF WIDENING TO | 9.0 |
0145-01-031 | Bailey/ Lubbock | US 70 | Actual | $255,400 | 8 | TREE REMOVAL IN CLEAR ZONE | 0.0 |
0471-05-047 | Bastrop/ Austin | SH 21 | Actual | $1,895,236 | 8 | IMPROVE GUARDRAIL TO DESIGN STANDARDS | 0.0 |
0322-01-049 | Bastrop/ Austin | SH 95 | Actual | $1,215,218 | 1 | MILL, SEAL & TOM OVERLAY | 0.0 |
0909-36-164 | Bell/ Waco | CS | Tentative | $250,000 | 8 | UPGRADE RR CROSSING SIGNALS FEDERAL SAFETY PROGRAM (FSP) | 0.0 |
0073-08-194 | Bexar/ San Antonio | IH 37 | Actual | $999,969 | 10 | LANDSCAPE PLANTING AND IRRIGATION | 0.0 |
0915-00-199 | Bexar/ San Antonio | VA | Tentative | $2,000,000 | 1 | DISTRICTWIDE ITS OPERATION AND MAINTENANCE FY 2018 | 0.0 |
2230-01-013 | Bexar/ San Antonio | FM 1560 | Actual | $19,217,259 | 1 | EXPAND FROM 2 TO 4 LANES WITH RAISED MEDIANS, BIKE LANES AND | 8.5 |
0017-10-287 | Bexar/ San Antonio | IH 35 | Actual | $454,693 | 8 | WRONG WAY DRIVER ADVANCED TECHNOLOGIES | 0.0 |
0017-01-024 | Bexar/ San Antonio | SL 353 | Actual | $2,422,475 | 8 | PROFILE EDGELINE/CENTERLINE MARKINGS | 0.0 |
0016-08-036 | Bexar/ San Antonio | SL 368 | Actual | $1,543,761 | 1 | INTERSECTION OPERATIONAL IMPROVEMENTS | 5.0 |
1231-01-071 | Bowie/ Atlanta | FM 989 | Tentative | $250,000 | 8 | RAILROAD CROSSING UPGRADES | 0.0 |
0919-19-081 | Bowie/ Atlanta | CS | Tentative | $250,000 | 8 | RAILROAD CROSSING UPGRADES | 0.0 |
2938-02-023 | Brazoria/ Houston | FM 2917 | Actual | $11,000 | 10 | REMOVE AND INSTALL NEW CABINET | 0.0 |
0540-05-048 | Brazos/ Bryan | FM 159 | Actual | $4,155,050 | 1 | REHABILITATE EXISTING ROAD | 0.0 |
0212-03-062 | Brazos/ Bryan | FM 158 | Actual | $4,953,740 | 1 | MILL AND INLAY | 1.5 |
0049-09-079 | Brazos/ Bryan | US 190 | Actual | $432,116 | 8 | INSTALL TRAFFIC SIGNAL | 0.0 |
0117-01-052 | Brazos/ Bryan | US 190 | Actual | $324,763 | 8 | SAFETY WORK CONSISTING OF MODERNIZATION OF INTERSECTION | 0.0 |
0923-06-081 | Brown/ Brownwood | VA | Tentative | $250,000 | 8 | INSTALL PROTECTIVE DEVICES | 0.0 |
0128-01-112 | Brown/ Brownwood | US 377 | Tentative | $250,000 | 8 | INSTALL PROTECTIVE DEVICES | 0.0 |
1349-03-013 | Burnet/ Austin | RM 1174 | Actual | $5,713,341 | 1 | PROVIDE ADDITIONAL PAVED SURFACE | 0.0 |
0252-02-054 | Burnet/ Austin | US 281 | Actual | $7,420,179 | 1 | ADD CENTER LEFT TURN LANE AND SHOULDERS | 4.0 |
0153-01-014 | Caldwell/ Austin | US 183 | Actual | $449,531 | 1 | PAVEMENT REPAIR AND RESURFACING | 1.0 |
0286-03-017 | Caldwell/ Austin | SH 80 | Actual | $5,597,086 | 1 | LEVEL-UP, FULL DEPTH REPAIR AND TOM | 0.0 |
0914-22-070 | Caldwell/ Austin | VA | Actual | $225,000 | 3 | LULING RELIEF ROUTE STUDY | 0.0 |
0921-06-303 | Cameron/ Pharr | VA | Actual | $321,745 | 3 | CONSTRUCTION OF SIDEWALKS, CROSSWALKS, & PAVED SHARED USE | 0.0 |
0788-01-020 | Carson/ Amarillo | FM 294 | Tentative | $250,000 | 8 | DOT#014566N FED RAILROAD SIGNAL PROGRAM | 0.0 |
0919-14-027 | Cass/ Atlanta | CR | Tentative | $0 | 8 | RAILROAD CROSSING UPGRADES | 0.0 |
0242-03-076 | Chambers/ Beaumont | SH 61 | Actual | $210,221 | 10 | REPLACE CROSS CULVERT | 0.0 |
0264-04-052 | Coke/ San Angelo | US 277 | Actual | $6,068,480 | 1 | GRADING, BASE AND STRUCTURES | 0.0 |
0918-24-240 | Collin/ Dallas | CR | Tentative | $250,000 | 8 | INSTALL GRADE CROSSING WARNING DEVICES | 0.0 |
0135-03-050 | Collin/ Dallas | US 380 | Actual | $5,512,580 | 8 | INSTALL RAISED MEDIAN | 3.0 |
0016-04-113 | Comal/ San Antonio | IH 35 | Actual | $1,021,888 | 1 | REVISE RAMPS AND CONVERT FRONTAGE ROADS FROM TWO WAY TO ONE | 7.5 |
0140-11-045 | Crockett/ San Angelo | IH 10 | Actual | $3,677,637 | 1 | RELOCATE EB EXIT RAMP 365 AND EXTEND SOUTH FRONTAGE ROAD | 0.0 |
0374-08-021 | Culberson/ El Paso | US 62 | Actual | $1,387,176 | 1 | INSTALLATION OF SHEET PILING AND GABION MATTRESSES | 0.0 |
0918-47-099 | Dallas/ Dallas | CS | Approved | $3,900,000 | 3 | BIKE AND PEDESTRAIN FACILITY; CONCRETE TRAIL; LIGHTING AND | 0.0 |
0918-47-165 | Dallas/ Dallas | CS | Approved | $2,570,548 | 3 | PLEASANT RUN ROAD TRAIL - INSTALL BIKE/PEDESTRIAN TRAIL | 0.0 |
0918-45-817 | Dallas/ Dallas | CS | Approved | $1,100,000 | 3 | CITYWIDE SIGNAL SYSTEM UPGRADE | 0.0 |
0918-47-140 | Dallas/ Dallas | CS | Approved | $621,797 | 3 | BROOKHAVEN COLLEGE CAMPUS - INTERCITY CONNECTIONS -CONSTRUCT | 0.0 |
0918-46-304 | Denton/ Dallas | CR | Tentative | $250,000 | 8 | INSTALL GRADE CROSSING WARNING DEVICES | 0.0 |
0918-46-292 | Denton/ Dallas | CS | Approved | $2,605,107 | 3 | DCTA A-TRAIN BIKE AND PEDESTRIAN TRAIL - EAGLE POINT SECTION | 0.0 |
0081-05-044 | Denton/ Dallas | FM 3524 | Actual | $1,772,512 | 8 | PROVIDE ADDITIONAL PAVED SURFACE WIDTH, MILLED EDGELINE | 0.0 |
0918-46-308 | Denton/ Dallas | VA | Actual | $480,090 | 3 | VANPOOL SUBSIDY INITIATIVE FOR COMMUTERS TRAVELING LONG DIST | 0.0 |
0270-10-013 | Dewitt/ Yoakum | SH 72 | Actual | $6,500,765 | 6 | REPLACE BRIDGE AND APPROACHES | 1.5 |
0301-04-020 | Dimmit/ Laredo | FM 186 | Actual | $14,234,238 | 1 | REHABILITATION OF EXISTING HIGHWAY | 0.0 |
0237-07-015 | Dimmit/ Laredo | FM 133 | Actual | $18,502,516 | 1 | REHABILITATION OF EXISTING HIGHWAY | 1.0 |
0005-01-109 | Ector/ Odessa | BI 20-E | Actual | $484,111 | 8 | INSTALL INTERSECTION FLASHING BEACONS, WARNING SIGNALS AND | 0.0 |
2296-01-052 | Ector/ Odessa | SH 191 | Actual | $178,385 | 8 | WRONG WAY DRIVER WARNING SIGNS | 0.0 |
0374-02-089 | El Paso/ El Paso | US 62 | Approved | $9,700,000 | 3 | RAPID TRANSIT SYSTEM (RTS) | 0.0 |
1046-01-030 | El Paso/ El Paso | FM 659 | Actual | $18,254,929 | 2M | OPERATIONAL IMPROVEMENTS AT ZARAGOZA RD/MONTWOOD DR/LP 375 | 6.5 |
2121-03-160 | El Paso/ El Paso | IH 10 | Actual | $8,964,329 | 1 | RAMP AND INTERSECTION IMPROVEMENTS AT AIRWAYS, HAWKINS AND V | 7.5 |
0002-01-095 | El Paso/ El Paso | SH 20 | Actual | $511,726 | 11 | EXTEND BOX CULVERT, PEDESTRIAN IMPROVEMENTS AND DRIVEWAYS | 0.0 |
0909-38-078 | Falls/ Waco | CS | Actual | $253,884 | 6 | REPLACE BRIDGE AND APPROACHES | 0.0 |
0909-38-071 | Falls/ Waco | CR | Actual | $522,191 | 6 | REPLACE BRIDGE AND APPROACHES | 0.0 |
0174-04-035 | Fannin/ Paris | FM 79 | Actual | $1,464,159 | 8 | RAISED EDGELINE RUMBLE STRIPS, RAISED CENTERLINE RUMBLE | 0.0 |
0765-02-021 | Fannin/ Paris | FM 1753 | Actual | $11,028,953 | 1 | REHABILITATION OF EXISTING ROAD | 0.0 |
0912-34-194 | Fort Bend/ Houston | VA | Tentative | $3,500,000 | 5 | REIMBURSEMENT FOR FORT BEND COUNTY TRANSNIT ADMINISTRATION | 0.0 |
0912-34-198 | Fort Bend/ Houston | CR | Tentative | $250,000 | 8 | FY 2017 RR SIGNAL AND WARNING DEVICES (UPRR DOT# 743731H) | 0.0 |
1258-02-040 | Fort Bend/ Houston | FM 1093 | Actual | $26,125 | 10 | REMOVED AND REPLACE ASPHALT ROADWAY | 0.0 |
0912-73-214 | Galveston/ Houston | CS | Actual | $445,819 | 3 | CONSTRUCT SHARED USE PATH AND ENHANCE EXISTING PATH | 0.0 |
0192-04-106 | Galveston/ Houston | SH 6 | Actual | $11,000 | 10 | REMOVE AND INSTALL NEW CABINET | 0.0 |
0912-73-204 | Galveston/ Houston | CR | Actual | $3,626,860 | 6 | BRIDGE REPAIR/PREVENTATIVE MAINTENANCE (NBI# 12085B00790001) | 0.0 |
0912-73-208 | Galveston/ Houston | VA | Tentative | $2,454,000 | 3 | CONSTRUCT PARK AND RIDE WITH 400 AUTO AND 40 BUS PARKING | 0.0 |
0978-02-079 | Galveston/ Houston | FM 517 | Actual | $11,000 | 10 | REMOVE AND INSTALL NEW CABINET | 0.0 |
0051-03-116 | Galveston/ Houston | SH 3 | Actual | $11,000 | 10 | REMOVE AND INSTALL NEW CABINET | 0.0 |
0051-03-113 | Galveston/ Houston | SH 3 | Actual | $11,000 | 10 | REMOVE AND INSTALL NEW CABINET | 0.0 |
0500-04-143 | Galveston/ Houston | IH 45 | Actual | $11,000 | 10 | REMOVE AND INSTALL NEW CABINET | 0.0 |
0500-04-142 | Galveston/ Houston | IH 45 | Actual | $11,000 | 10 | REMOVE AND INSTALL NEW CABINET | 0.0 |
0912-73-195 | Galveston/ Houston | CR | Actual | $1,551,233 | 6 | REPLACE BRIDGE AND APPROACHES (NBI# 12085C00138048) | 4.5 |
0112-03-035 | Gillespie/ Austin | US 290 | Actual | $4,251,876 | 8 | IMPROVE GUARDRAIL TO DESIGN STANDARDS | 2.0 |
0025-05-021 | Gonzales/ Yoakum | US 90A | Actual | $2,061,460 | 8 | SAFETY TREAT FIXED OBJECTS | 6.5 |
0153-02-040 | Gonzales/ Yoakum | US 183 | Actual | $6,760,342 | 11 | PAVEMENT REPAIR AND RESURFACING | 1.0 |
0666-01-027 | Grayson/ Paris | FM 691 | Actual | $8,299,255 | 1 | RECONST ROADWAY AND ADD 2 LANES | 5.5 |
0045-19-053 | Grayson/ Paris | US 82 | Actual | $3,011,285 | 8 | SAFETY TREAT FIXED OBJECTS | 6.5 |
0045-03-050 | Grayson/ Paris | SH 56 | Approved | $30,015 | 3 | SH 56 AND RUSK STREET PEDESTRIAN CURB RAMP IMPROVEMENT | 0.0 |
0800-05-028 | Hale/ Lubbock | FM 400 | Tentative | $250,000 | 8 | RAIL HWY CROSSING SIGNALS/STRUCTURES | 0.0 |
0067-04-053 | Hale/ Lubbock | IH 27 | Tentative | $250,000 | 8 | RAIL HWY CROSSING SIGNALS/STRUCTURES | 0.0 |
0909-29-040 | Hamilton/ Waco | CR | Actual | $558,441 | 6 | REPLACE BRIDGE AND APPROACHES | 0.0 |
3184-01-011 | Hardeman/ Childress | FM 2568 | Tentative | $27,680 | 10 | RR REPLANKING | 0.0 |
0920-03-034 | Hardin/ Beaumont | CR | Actual | $718,136 | 6 | REPLACE BRIDGE | 0.0 |
0271-14-236 | Harris/ Houston | IH 610 | Actual | $577,928 | 10 | LANDSCAPE DEVELOPMENT | 0.0 |
0271-16-144 | Harris/ Houston | IH 610 | Actual | $500,517 | 10 | LANDSCAPE DEVELOPMENT | 0.0 |
0177-11-154 | Harris/ Houston | IH 69 | Actual | $2,441,487 | 1 | HIGH FRICTION SURFACE TREATMENT ON CURVE | 0.0 |
0271-06-120 | Harris/ Houston | IH 10 | Actual | $2,126,850 | 1 | EROSION REPAIR AND CHANNEL PROTECTION | 0.0 |
0912-00-541 | Harris/ Houston | VA | Tentative | $2,000,000 | 7 | REGIONAL ITS INFRASTRUCTURE - HARDWARE/SOFTWARE, UTILITIES | 0.0 |
0912-00-546 | Harris/ Houston | VA | Tentative | $3,750,000 | 3 | METRO STAR VANPOOL PROGRAM (FY 2017) | 0.0 |
0720-03-143 | Harris/ Houston | SH 249 | Actual | $4,030,081 | 8 | INTERCONNECT SIGNALS | 0.0 |
0912-00-539 | Harris/ Houston | VA | Tentative | $8,000,000 | 7 | REGIONAL FREEWAY INCIDENT MANAGEMENT-TOWINIG (FY2017/2018) | 0.0 |
0050-06-090 | Harris/ Houston | US 290 | Actual | $1,398,781 | 10 | LANDSCAPE DEVELOPMENT | 0.0 |
0110-05-128 | Harris/ Houston | IH 45 | Actual | $365,229 | 6 | REPLACE/RESET BEARING PADS | 0.0 |
0912-00-549 | Harris/ Houston | VA | Tentative | $4,438,000 | 3 | TRAVEL DEMAND MANAGEMENT, MARKETING, OUTREACH AND PUBLIC | 0.0 |
0912-72-370 | Harris/ Houston | CS | Actual | $3,523,000 | 3 | RECONSTRUCT & WIDEN SIDEWALKS AND ADA RAMPS AND INSTALLATION | 0.0 |
0912-72-387 | Harris/ Houston | CS | Actual | $1,989,000 | 3 | RECONSTRUCT BACK OF CURB INFRASTRUCTURE - SIDEWALKS, CURBS, | 0.0 |
0912-70-126 | Harris/ Houston | CR | Tentative | $250,000 | 8 | FY 2017 RR SIGNAL AND WARNING DEVICES (UPRR DOT# 758192R) | 0.0 |
0912-70-147 | Harris/ Houston | CR | Tentative | $21,185 | 10 | INSTALL NEW CMP (NBI#121020A49377001) | 0.0 |
1844-01-028 | Harris/ Houston | FM 2351 | Actual | $11,455 | 10 | REMOVE AND INSTALL NEW CABINET AND RISER | 0.0 |
0912-72-531 | Harris/ Houston | CR | Tentative | $55,801 | 3 | EROSION REPAIR (NBI #121020AA2430001 & 121020AA2430002) | 0.0 |
1685-05-119 | Harris/ Houston | SH 6 | Actual | $18,536 | 10 | REMOVED DAMAGED CABINET, INSTALLED NEW CABINET | 0.0 |
0912-00-584 | Harris/ Houston | VA | Actual | $1,742,000 | 3 | CONDUCT PUBLIC OUTREACH FOR TRANSPORTATION SAFETY IN THE | 0.0 |
0912-70-120 | Harris/ Houston | CS | Tentative | $622,802 | 8 | FY 2016 RR SIGNAL AND WARNING DEVICES (UPRR DOT# 758 517X) | 0.0 |
0912-00-552 | Harris/ Houston | VA | Tentative | $15,000,000 | 3 | CLEAN CITIES/CLEAN VEHICLES PROGRAM (ENGINE/VEHICLE | 0.0 |
0912-00-583 | Harris/ Houston | VA | Actual | $375,000 | 3 | RESILIENCE AND DURABILITY TO EXTREME WEATHER STUDY | 0.0 |
0912-70-124 | Harris/ Houston | CR | Tentative | $250,000 | 8 | FY 2017 RR SIGNAL AND WARNING DEVICES (UPRR DOT# 755622N) | 0.0 |
0912-70-125 | Harris/ Houston | CR | Tentative | $250,000 | 8 | FY 2017 RR SIGNAL AND WARNING DEVICES (UPRR DOT# 755624C) | 0.0 |
0912-70-122 | Harris/ Houston | CS | Tentative | $583,590 | 8 | FY 2016 RR SIGNAL AND WARNING DEVICES (UPRR DOT# 758 518E) | 0.0 |
0912-70-123 | Harris/ Houston | CR | Tentative | $250,000 | 8 | FY 2017 RR SIGNAL AND WARNING DEVICES (UPRR DOT# 089370C) | 0.0 |
0919-03-061 | Harrison/ Atlanta | CR | Tentative | $250,000 | 8 | RAILROAD CROSSING UPGRADES | 0.0 |
0285-03-059 | Hays/ Austin | RM 12 | Tentative | $400,002 | 3 | ENGINEERING, DESIGN, AND ROW PURCHASE TO ADD TURN LANES AND | 0.0 |
2293-01-030 | Hays/ Austin | FM 2439 | Actual | $532,410 | 1 | RESURFACE ROADWAY | 0.0 |
0016-03-103 | Hays/ Austin | IH 35 | Actual | $32,502,479 | 1 | REPLACE BRIDGE & APPROACHES | 7.5 |
0921-02-333 | Hidalgo/ Pharr | CS | Approved | $9,000,000 | 3 | IMPROVEMENTS AT SOUTHBOUND INSPECTION FACILITY AT THE | 0.0 |
1939-01-059 | Hidalgo/ Pharr | FM 2061 | Actual | $1,154,392 | 8 | INSTALL TRAFFIC SIGNAL | 0.0 |
0921-02-354 | Hidalgo/ Pharr | CS | Actual | $500,000 | 3 | MCINTYRE RAILROAD PEDESTRIAN CROSSING IMPROVEMENTS | 0.0 |
0080-11-001 | Hood/ Ft Worth | US 377 | Actual | $59,311,787 | 1 | CONSTRUCT 0 TO 4 LANE DIVIDED ROADWAY WITH GRADE SEPARATION | 7.5 |
0083-03-055 | Hopkins/ Paris | SH 154 | Actual | $5,647,893 | 1 | MILL AND INLAY | 0.0 |
1503-02-011 | Howard/ Abilene | FM 1584 | Actual | $3,157,591 | 8 | PAVEMENT WIDENING | 3.5 |
0068-08-065 | Howard/ Abilene | US 87 | Actual | $6,974,429 | 6 | BRIDGE REHAB | 0.0 |
0002-07-049 | Hudspeth/ El Paso | IH 10 | Actual | $4,864,588 | 6 | REPLACE BRIDGES AND APPROACHES | 4.0 |
0173-06-042 | Hunt/ Paris | SH 34 | Actual | $1,442,300 | 7 | WIDEN 2 LANE RURAL TO 5 LANE UNDIVIDED ARTERIAL | 0.0 |
0920-38-259 | Jefferson/ Beaumont | CS | Tentative | $250,000 | 8 | PROTECTIVE DEVICES | 0.0 |
0920-00-120 | Jefferson/ Beaumont | VA | Tentative | $1,200,000 | 5 | REPLACE 15 TRANSIT BUSES WITH ALTERNATELY FUELED VEHICLES | 0.0 |
0601-02-024 | Jefferson/ Beaumont | SH 326 | Tentative | $250,000 | 8 | PROTECTIVE DEVICES | 0.0 |
0484-01-023 | Jones/ Abilene | FM 707 | Actual | $15,279,965 | 8 | WIDEN ROADWAY | 4.0 |
0270-03-075 | Karnes/ Corpus Christi | SH 72 | Actual | $19,468,999 | 11 | REHABILITATE ROADWAY AND ADD PASSING LANES | 2.0 |
2512-01-014 | Kaufman/ Dallas | FM 2728 | Tentative | $250,000 | 8 | INSTALL GRADE CROSSING WARNING DEVICES | 0.0 |
0751-01-046 | Kaufman/ Dallas | FM 148 | Actual | $12,737,000 | 3 | WIDEN EXISTING HIGHWAY FROM TWO LANE RURAL | 0.0 |
0435-01-078 | Lamar/ Paris | FM 137 | Actual | $700,000 | 6 | PREVENTATIVE MAINTENANCE | 0.0 |
0901-29-082 | Lamar/ Paris | CR | Actual | $915,649 | 6 | BRIDGE REPLACEMENT | 4.0 |
0116-01-039 | Lee/ Austin | SH 21 | Actual | $11,629,965 | 1 | LEVEL-UP, FULL DEPTH REPAIR AND TOM | 0.0 |
0952-01-059 | Liberty/ Beaumont | FM 1008 | Actual | $5,736 | 8 | TS HARVEY EMERGENCY REPAIRS DONE W/ 47Y00279 | 0.0 |
0338-05-031 | Liberty/ Beaumont | BS 105T | Actual | $336,993 | 10 | EMERGENCY REPAIRS TO ADDRESS DAMAGE CAUSED BY TROPICAL STORM | 0.0 |
0493-02-015 | Loving/ Odessa | RM 652 | Actual | $17,595,799 | 11 | ROADWAY REHABILITATION | 1.5 |
0905-06-113 | Lubbock/ Lubbock | CS | Tentative | $250,000 | 8 | RAIL HWY CROSSING SIGNALS/STRUCTURES | 0.0 |
0905-06-112 | Lubbock/ Lubbock | CS | Tentative | $250,000 | 8 | RAIL HWY CROSSING SIGNALS/STRUCTURES | 0.0 |
0005-04-079 | Martin/ Odessa | IH 20 | Actual | $350,835 | 11 | BRIDGE DEMOLITION | 0.0 |
0380-07-026 | Martin/ Odessa | SH 349 | Actual | $17,633,197 | 11 | ARMORING WITH OVERLAY | 1.0 |
0049-01-094 | Mclennan/ Waco | SH 6 | Actual | $1,023,438 | 8 | IMPROVE TRAFFIC SIGNALS | 0.0 |
0017-05-095 | Medina/ San Antonio | IH 35 | Actual | $2,378,318 | 8 | INSTALL INTERSECTION FLASHING BEACON | 0.0 |
0005-09-021 | Midland/ Odessa | BI 20-E | Tentative | $4,000,000 | 8 | CORRIDOR INTERCONNECT FOR PRE-EMPTION | 0.0 |
0177-14-010 | Montgomery/ Houston | SL 494 | Actual | $15,003,930 | 2M | RECONSTRUCT AND WIDEN TO 4 LANE DIVIDED URBAN SECTION | 7.5 |
0523-08-014 | Montgomery/ Houston | FM 1488 | Actual | $3,901,245 | 1 | BASE REPAIR, OCST, 2IN HMA LEVEL-UP, 2IN HMA OVERLAY | 0.0 |
0177-05-116 | Montgomery/ Houston | IH 69 | Actual | $11,000 | 10 | REMOVE AND INSTALL NEW CABINET | 0.0 |
0912-37-236 | Montgomery/ Houston | CR | Tentative | $250,000 | 8 | FY 2017 RR SIGNAL AND WARNING DEVICES (UPRR DOT# 755882G) | 0.0 |
0912-37-234 | Montgomery/ Houston | CR | Tentative | $250,000 | 8 | FY 2017 RR SIGNAL AND WARNING DEVICES (UPRR DOT# 755879Y) | 0.0 |
0912-37-235 | Montgomery/ Houston | CR | Tentative | $250,000 | 8 | FY 2017 RR SIGNAL AND WARNING DEVICES (UPRR DOT# 755892M) | 0.0 |
3158-01-032 | Montgomery/ Houston | FM 3083 | Actual | $8,378,456 | 2M | WIDEN TO 4-LANE DIVIDED URBAN | 7.5 |
0110-04-199 | Montgomery/ Houston | IH 45 | Actual | $1,140,720 | 6 | REPLACE/RESET BEARING PADS, REPLACE BRIDGE DECK | 0.0 |
0146-01-051 | Motley/ Childress | US 62 | Actual | $2,253,025 | 6 | REPLACEMENT OF EXISTING BRIDGE FACILITY | 2.5 |
0138-06-045 | Nacogdoches/ Lufkin | US 259 | Actual | $638,755 | 8 | UPGRADE INSTALL SAFETY LIGHTING WITHIN PROJECT | 0.0 |
1407-03-018 | Nacogdoches/ Lufkin | FM 1275 | Actual | $237,693 | 8 | IMPROVE TRAFFIC AND PEDESTRIAN SIGNALS AT LOCATION | 0.0 |
0918-18-132 | Navarro/ Dallas | CS | Approved | $653,524 | 3 | HUMPHREY SAFE ROUTES TO SCHOOL - CONSTRUCT SIDEWALKS | 0.0 |
0214-03-036 | Newton/ Beaumont | SH 63 | Actual | $3,778,053 | 3 | RETROFIT BRIDGE BENTS | 0.0 |
0916-35-184 | Nueces/ Corpus Christi | CS | Actual | $3,557,849 | 3 | IMPROVE TRAFFIC SIGNALS, INTERCONNECT SIGNALS | 0.0 |
0920-30-084 | Orange/ Beaumont | CS | Tentative | $250,000 | 8 | PROTECTIVE DEVICES | 0.0 |
3520-01-022 | Parmer/ Lubbock | FM 3333 | Tentative | $250,000 | 8 | RAIL HWY CROSSING SIGNALS/STRUCTURES | 0.0 |
7106-03-003 | Pecos/ Odessa | RL SO | Tentative | $0 | RL | REHABILITATION OF THE SOUTH ORIENT RAIL LINE INCLUDING RAIL, | 0.0 |
0177-01-108 | Polk/ Lufkin | US 59 | Tentative | $430,594 | 10 | REPLACE DAMAGED RIPRAP AND REPAIR SLOPE FAILURE NEXT TO RIPR | 0.0 |
0904-02-044 | Potter/ Amarillo | CS | Tentative | $250,000 | 8 | DOT#014602G FED RAILROAD SIGNAL PROGRAM | 0.0 |
0371-03-122 | Refugio/ Corpus Christi | US 77 | Actual | $21,812 | 10 | REPAIR OR REPLACE SCHOOL ZONE FLASHERS DAMAGED BY HIGH WINDS | 0.0 |
0180-02-043 | Refugio/ Corpus Christi | SH 35 | Actual | $7,039 | 10 | REPAIR OR REPLACE SCHOOL ZONE FLASHERS DAMANGED BY HIGH WIND | 0.0 |
2653-01-014 | Rusk/ Tyler | FM 2658 | Actual | $1,411,839 | 1 | REPAIR & REPAVE ROADWAY | 0.0 |
0592-02-015 | Rusk/ Tyler | FM 840 | Actual | $8,339,689 | 1 | WIDEN TO 26',SAFETY TREAT,IMPROVE GUARDRAIL TO DESIGN STNDS | 4.0 |
0403-01-049 | San Jacinto/ Lufkin | SH 156 | Tentative | $53,076 | 10 | RE-ESTABLISH THE SLOPE AND RESET GUARDRAIL. CONCRETE RIRAP W | 0.0 |
0756-04-013 | San Jacinto/ Lufkin | FM 2693 | Actual | $25,419 | 10 | REMOVE AND RESET SEPARATED BOX CULVERT. REPOUR NEW WINGWALL | 0.0 |
0177-02-102 | San Jacinto/ Lufkin | US 59 | Tentative | $624,386 | 10 | REPAIR PAVING EROSION, REPLACE DAMAGED MBGF AND REBUILD BACK | 0.0 |
0101-04-097 | San Patricio/ Corpus Christi | US 181 | Actual | $40,390,128 | 1 | CONSTRUCT AUXILIARY LANES AND RAMP REVERSAL_TO EXIST 4-LN | 7.0 |
0180-11-014 | San Patricio/ Corpus Christi | SP 202 | Actual | $6,950 | 10 | REPAIR OR REPLACE SCHOOL ZONE FLASHERS DAMAGED BY HIGH WINDS | 0.0 |
0180-06-103 | San Patricio/ Corpus Christi | BS 35-L | Actual | $11,763 | 10 | REPAIR OR REPLACE SCHOOL ZONE FLASHERS DAMAGED BY HIGH WINDS | 0.0 |
0180-06-102 | San Patricio/ Corpus Christi | BS 35-L | Actual | $16,488 | 10 | REPAIR OR REPLACE SCHOOL ZONE FLASHERS DAMAGED BY HIGH WINDS | 0.0 |
0101-03-088 | San Patricio/ Corpus Christi | US 181 | Actual | $13,981,551 | 1 | CONSTRUCT GRADE SEPARATION | 7.5 |
0180-09-019 | San Patricio/ Corpus Christi | SL 90 | Actual | $11,786 | 10 | REPAIR OR REPLACE SCHOOL ZONE FLASHERS DAMAGED BY HIGH WINDS | 0.0 |
3026-01-029 | San Patricio/ Corpus Christi | FM 2986 | Actual | $6,774 | 10 | REPAIR OR REPLACE SCHOOL ZONE FLASHERS DAMAGED BY HIGH WINDS | 0.0 |
0738-03-030 | San Patricio/ Corpus Christi | FM 3284 | Actual | $6,950 | 10 | REPAIR OR REPLACE SCHOOL ZONE FLASHERS DAMAGED BY HIGH WINDS | 0.0 |
0738-04-017 | San Patricio/ Corpus Christi | FM 3284 | Actual | $6,945 | 10 | REPAIR OR REPLACE SCHOOL ZONE FLASHERS DAMAGED BY HIGH WINDS | 0.0 |
1549-04-030 | San Patricio/ Corpus Christi | FM 1069 | Actual | $11,763 | 10 | REPAIR OR REPLACE SCHOOL ZONE FLASHERS DAMAGED BY HIGH WINDS | 0.0 |
0910-16-145 | Smith/ Tyler | VA | Actual | $173,546 | 10 | PLANTING TREES AND SHRUBS | 0.0 |
0191-01-063 | Smith/ Tyler | US 69 | Actual | $16,549,021 | 1 | CONSTRUCT GRADE-SEPARATED INTERCHANGE | 7.5 |
0902-00-175 | Tarrant/ Ft Worth | VA | Tentative | $291,350 | 7 | CONGESTION MGMT OPERATIONS & DATA ARCHIVING, REG ITS ARCH, | 0.0 |
0902-00-209 | Tarrant/ Ft Worth | VA | Actual | $937,932 | 1 | BRIDGE MAINTENANCE | 0.0 |
0902-00-205 | Tarrant/ Ft Worth | VA | Actual | $2,628,553 | 10 | CONSTRUCT CURB RAMS AT VARIOUS LOCATIONS ALONG BU 67-M IN | 7.5 |
0902-00-187 | Tarrant/ Ft Worth | VA | Tentative | $400,000 | 3 | M&O CORRIDOR STUDIES & CAPITAL ASSET MANAGEMENT | 0.0 |
0902-00-213 | Tarrant/ Ft Worth | VA | Actual | $1,760,570 | 1 | CONCRETE PAVEMENT REPAIR, SPOT REPAIRS VARIOUS LOCATIONS | 0.0 |
0902-00-215 | Tarrant/ Ft Worth | VA | Tentative | $3,000,000 | 3 | MANAGED LANE SYSTEM, IMPLEMENT TECHNOLOGY TO DETECT AUTO | 0.0 |
0902-00-214 | Tarrant/ Ft Worth | VA | Tentative | $660,000 | 7 | MULTIPURPOSE AUTOMATID VEHICLE DESIGN, DEVELOPMENT, TESTING, | 0.0 |
0902-00-178 | Tarrant/ Ft Worth | VA | Tentative | $312,500 | 7 | PROGRAM OVERSIGHT COORDINATION, INCLUDING DEPT STREAMLINING | 0.0 |
0353-03-102 | Tarrant/ Ft Worth | SH 114 | Tentative | $62,334 | 3 | RELOCATE ITS FIBER OPTIC CABLE DUE TO CONFLICT WITH TEX RAIL | 0.0 |
0718-02-045 | Tarrant/ Ft Worth | FM 156 | Actual | $55,191,780 | 1 | WIDEN 2 TO 4 LANE DIVIDED | 10.0 |
0172-09-036 | Tarrant/ Ft Worth | US 287 | Actual | $4,261,045 | 5 | INSTALLATION OF ITS FIBER & EQUIPMENT | 0.0 |
0080-07-097 | Tarrant/ Ft Worth | US 377 | Actual | $185,842 | 1 | INSTALLATION OF TRAFFIC SIGNAL | 0.0 |
0094-02-133 | Tarrant/ Ft Worth | SH 10 | Actual | $400,000 | 3 | INSTALLATION OF LANDSCAPING AND IRRIGATION WITHIN MEDIANS OF | 0.0 |
0902-00-172 | Tarrant/ Ft Worth | VA | Actual | $2,500,000 | 3 | REGIONAL MINOR INTERSECTION EQUIP PRGRAM POOL FOR FUTURE | 0.0 |
0902-90-051 | Tarrant/ Ft Worth | VA | Tentative | $300,000 | 5 | ITS EQUIPMENT UPGRADES FOR TECHNOLOGY ADVANCES | 0.0 |
0902-90-091 | Tarrant/ Ft Worth | CS | Tentative | $250,000 | 8 | 2018 FEDERAL RR SIGNAL PROGRAM | 0.0 |
0902-90-092 | Tarrant/ Ft Worth | CS | Tentative | $250,000 | 8 | 2018 FEDERAL RR SIGNAL PROGRAM | 0.0 |
0902-90-025 | Tarrant/ Ft Worth | VA | Actual | $1,558,674 | 3 | LYNN CREEK LINEAR PARK TRAIL EXTENSION FROM END POINT OF | 0.0 |
0902-90-042 | Tarrant/ Ft Worth | VA | Tentative | $25,000 | 3 | DIRECT STATE CHARGES FOR TEX RAIL CONNECTION_PROJECTS | 0.0 |
0902-90-087 | Tarrant/ Ft Worth | VA | Actual | $133,000 | 3 | UPGRADE TRAFFIC SIGNALS BY INSTALLING COMMUNICATION | 0.0 |
0902-90-090 | Tarrant/ Ft Worth | CS | Tentative | $250,000 | 8 | 2018 FEDERAL RR SIGNAL PROGRAM | 0.0 |
0902-90-094 | Tarrant/ Ft Worth | CS | Tentative | $250,000 | 8 | 2018 FEDERAL RR SIGNAL PROGRAM | 0.0 |
0902-90-054 | Tarrant/ Ft Worth | VA | Actual | $1,000,000 | 3 | DEVELOP AND IMPLEMENT TRAFFIC SIGNAL COORDINATION IN 9 | 0.0 |
0902-90-100 | Tarrant/ Ft Worth | VA | Tentative | $1,250,000 | 7 | TEXAS AUTOMATED VEHICLES PROVING GROUND ALONG THE IH 30 | 0.0 |
0902-90-093 | Tarrant/ Ft Worth | CS | Tentative | $250,000 | 8 | 2018 FEDERAL RR SIGNAL PROGRAM | 0.0 |
0908-00-086 | Taylor/ Abilene | VA | Actual | $4,150,000 | 8 | RXR CROSSINGS AND INTERSECTION IMPROVEMENTS | 0.0 |
0034-01-126 | Taylor/ Abilene | US 83 | Actual | $32,308,115 | 1 | CONSTRUCT OVERPASS AND RELOCATE RAMPS | 7.0 |
0908-33-097 | Taylor/ Abilene | CR | Tentative | $250,000 | 8 | UPGRADE/INSTALL RR XING PROTECTION | 0.0 |
0158-02-084 | Tom Green/ San Angelo | US 67 | Actual | $36,145,504 | 11 | CONSTRUCT INTERCHANGE | 7.0 |
0069-07-106 | Tom Green/ San Angelo | US 87 | Approved | $384,600 | 1 | REPLACE TRAFFIC SIGNAL AND RECONFIGURE INTERSECTION | 0.0 |
0907-00-191 | Tom Green/ San Angelo | VA | Actual | $829,917 | 1 | UPGRADE SMALL SIGNS | 0.0 |
1378-01-040 | Travis/ Austin | RM 1431 | Tentative | $856,550 | 1 | CONSTRUCT LEFT & RIGHT TURN LANES @ BALCONES CANYONLANDS NWR | 0.0 |
3417-01-029 | Travis/ Austin | FM 734 | Actual | $2,769,878 | 1 | PAVEMENT REPAIR, UNDERSEAL & OVERLAY | 0.0 |
0113-13-175 | Travis/ Austin | SH 71 | Actual | $4,561,576 | 1 | MILL & INLAY | 0.0 |
0914-00-413 | Travis/ Austin | VA | Actual | $2,480,872 | 1 | RESTRIPING & REPLACEMENT OF RAISED PAVEMENT MARKINGS ON | 0.0 |
0914-00-412 | Travis/ Austin | VA | Tentative | $1,000,000 | 1 | FY 2018 NON-SITE SPECIFIC ITS IMPROVEMENTS_ON SL 1, IH 35 & | 0.0 |
1237-01-035 | Tyler/ Beaumont | FM 1013 | Actual | $6,930 | 10 | TS HARVEY EMERGENCY REPAIRS DONE WITH 47Y00279 | 0.0 |
1238-02-009 | Tyler/ Beaumont | FM 92 | Actual | $9,601 | 10 | TS HARVEY EMERGENCY REPAIR DONE WITH 47Y00279 | 0.0 |
0703-03-024 | Tyler/ Beaumont | FM 256 | Actual | $5,051 | 10 | TS HARVEY EMERGENCY REPAIR DONE WITH 47Y00279 | 0.0 |
3043-01-014 | Tyler/ Beaumont | FM 2992 | Actual | $5,949 | 10 | TS HARVEY EMERGENCY REPAIR DONE WITH 47Y00279 | 0.0 |
3621-01-014 | Val Verde/ Laredo | SL 79 | Actual | $15,000,690 | 1 | REHABILITATION OF EXISTING HIGHWAY | 1.5 |
0922-11-042 | Val Verde/ Laredo | CS | Tentative | $250,000 | 8 | FEDERAL RAILROAD SIGNAL PROGRAM (FSP) | 0.0 |
2350-01-066 | Victoria/ Yoakum | SL 463 | Tentative | $0 | 3 | INSTALL MEMORIAL MARKER SIGNS | 0.0 |
1370-01-021 | Ward/ Odessa | FM 1219 | Tentative | $204,073 | 8 | INSTALL PROTECTIVE DEVICES FOR CROSSING DOT# 864588J | 0.0 |
0917-19-052 | Washington/ Bryan | CS | Tentative | $250,000 | 8 | FEDERAL RAILROAD SIGNAL PROGRAM | 0.0 |
0018-04-060 | Webb/ Laredo | IH 35 | Actual | $1,071,454 | 8 | INSTALL FLASHING BEACON | 0.0 |
0922-33-170 | Webb/ Laredo | CS | Approved | $1,056,250 | 3 | ZACATE CREEK MULTI-USE ALTERNATIVE TRANSPORTATION TRAIL | 0.0 |
0922-33-175 | Webb/ Laredo | CS | Tentative | $1,634,277 | 3 | PS&E INCLUDING ROW MAPPING ONLY | 0.0 |
0089-06-090 | Wharton/ Yoakum | US 59 | Actual | $7,606,821 | 1 | ACP OVERLAY | 0.0 |
0043-08-075 | Wichita/ Wichita Falls | US 287 | Actual | $2,423,817 | 11 | INSTALL MEDIAN BARRIER | 0.0 |
0681-04-041 | Wichita/ Wichita Falls | FM 367 | Actual | $4,277,955 | 8 | SAFETY TREAT FIXED OBJECTS, PROVIDE ADDITIONAL PAVED SURFACE | 6.5 |
0433-02-052 | Willacy/ Pharr | SH 186 | Actual | $22,340,891 | 1 | REHABILITATE ROADWAY (SUPER 2) | 0.0 |
0327-10-062 | Willacy/ Pharr | US 77 | Actual | $14,840,225 | 11 | CONSTRUCT MAINLANES & OVERPASSES | 6.5 |
0015-17-028 | Williamson/ Austin | SS 158 | Actual | $963,493 | 8 | IMPROVE GUARDRAIL TO DESIGN STANDARDS | 0.0 |
1566-02-019 | Williamson/ Austin | FM 1660 | Actual | $9,192,190 | 1 | REHAB RDWY | 0.0 |
0134-07-074 | Wise/ Ft Worth | US 380 | Tentative | $3,187 | 3 | INSTALL MEMORIAL HIGHWAY SIGNS (JAMES BENNETT) | 0.0 |
0902-20-099 | Wise/ Ft Worth | CR | Actual | $652,829 | 6 | REPLACE BRIDGE AND APPROACHES | 0.0 |
0134-12-005 | Wise/ Ft Worth | BU 380F | Actual | $1,038,676 | 11 | REPAIR BASE FAILURES, MILL, HMAC OVERLAY, PAVEMENT MARKINGS | 0.0 |
|