Detail Letting Schedule for Martin County (FY 2018)

Last Update: Monday, November 20, 2017
Martin County (FY 2018)

CCSJ: 0005-04-071

District:ODESSALet Date:Nov 2017
Highway:IH 20Let Status:Actual
Project ID:NH 2018(266)CSJ:0005-04-071
Description:REHABILITATION OF EXISTING ROADHandling
Code:
 
Limits From:WEST OF SH 137Fund Cat:1
Limits To:EAST OF BI 20-F EAST INTERCHANGEESTIMATE:$7,645,549
Length:3.5Actual$5,784,005
 
Proposal Request
List Showing Order
Bid List
Bid Tabulations
Award Status
Back...
Totals for 0005-04-071
Length:3.5
Estimate:$7,645,549
Actual:$5,784,005

CCSJ: 0005-16-016

District:ODESSALet Date:Aug 2018
Highway:BI 20-FLet Status:Tentative
Project ID:STP ( )CSJ:0005-16-016
Description:IMPROVE AT GRADE CROSSING & DRAINAGEHandling
Code:
XX
Limits From:AT SH 137Fund Cat:8
Limits To:.ESTIMATE:$5,000,000
Length:0.2Actual$0
 
Back...
Totals for 0005-16-016
Length:0.2
Estimate:$0
Actual:TOTAL

Handling CodeDefinition
XXProject not processed through statewide letting
TRTransfer of funds
LCProject let through local entity
LCProject not charged against district apportionment



Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract