Detail Letting Schedule for Motley County (FY 2018)

Last Update: Monday, August 27, 2018
Motley County (FY 2018)

CCSJ: 0146-01-051

District:CHILDRESSLet Date:Aug 2018
Highway:US 62Let Status:Actual
Project ID:BR 1802(481)CSJ:0146-01-051
Description:REPLACEMENT OF EXISTING BRIDGE FACILITYHandling
Code:
 
Limits From:@ HACKBERRY CREEKFund Cat:6
Limits To:.___________________________7ESTIMATE:$2,253,025
Length:0.8Actual$2,119,656
 
Proposal Request
List Showing Order
Bid List
Addenda
Bid Tabulations
Back...
Totals for 0146-01-051
Length:0.8
Estimate:$2,253,025
Actual:$2,119,656

CCSJ: 0704-05-022

District:CHILDRESSLet Date:Jun 2018
Highway:FM 94Let Status:Actual
Project ID:C 704-5-22CSJ:0704-05-022
Description:WIDENING OF NON-FREEWAY FACILITYHandling
Code:
 
Limits From:MIDDLE PEASE RIVER, NEFund Cat:1
Limits To:7.357 MILES S OF NORTHFIELDESTIMATE:$6,578,166
Length:10.2Actual$7,493,681
 
Proposal Request
Bid List
List Showing Order
Addenda
Bid Tabulations
Award Status
Back...
Totals for 0704-05-022
Length:10.2
Estimate:$6,578,166
Actual:$7,493,681

Handling CodeDefinition
XXProject not processed through statewide letting
TRTransfer of funds
LCProject let through local entity
LCProject not charged against district apportionment



Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract