Detail Letting Schedule for Pecos County (FY 2018)

Last Update: Monday, November 13, 2017
Pecos County (FY 2018)

CCSJ: 0076-01-029

District:ODESSALet Date:Jul 2018
Highway:US 67Let Status:Tentative
Project ID:NH ( )CSJ:0076-01-029
Description:ROADWAY WIDENING TO A MODIFIED SUPER 2Handling
Code:
 
Limits From:CROCKETT COUNTY LINEFund Cat:1
Limits To:IH 10ESTIMATE:$27,138,000
Length:22.6Actual$0
 
District:ODESSALet Date:Jul 2018
Highway:US 67Let Status:Tentative
Project ID:NH ( )CSJ:0076-03-021
Description:ROADWAY WIDENING TO A MODIFIED SUPER 2Handling
Code:
 
Limits From:CRANE COUNTY LINEFund Cat:1
Limits To:PECOS COUNTY LINEESTIMATE:$1,018,800
Length:0.8Actual$0
 
District:ODESSALet Date:Jul 2018
Highway:US 67Let Status:Tentative
Project ID:NH ( )CSJ:0076-04-026
Description:ROADWAY WIDENING TO A MODIFIED SUPER 2Handling
Code:
 
Limits From:UPTON COUNTY LINEFund Cat:1
Limits To:CROCKETT COUNTY LINEESTIMATE:$4,006,800
Length:3.3Actual$0
 
District:ODESSALet Date:Jul 2018
Highway:US 67Let Status:Tentative
Project ID:NH ( )CSJ:0076-05-030
Description:ROADWAY WIDENING TO A MODIFIED SUPER 2Handling
Code:
 
Limits From:US 385Fund Cat:1
Limits To:CRANE COUNTY LINEESTIMATE:$5,830,800
Length:4.9Actual$0
 
Back...
Totals for 0076-01-029
Length:31.6
Estimate:$37,994,400
Actual:

Handling CodeDefinition
XXProject not processed through statewide letting
TRTransfer of funds
LCProject let through local entity
LCProject not charged against district apportionment



Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract