Detail Letting Schedule for Titus County (FY 2018)
Titus County (FY 2018) |
CCSJ: 0010-06-043 |
|||
District: | ATLANTA | Let Date: | Apr 2018 |
Highway: | US 67 | Let Status: | Actual |
Project ID: | STP 2018(788)HESG | CSJ: | 0010-06-043 |
Description: | PROFILE CENTERLINE MARKINGS | Handling Code: | |
Limits From: | US 271 | Fund Cat: | 8 |
Limits To: | FRANKLIN C/L | ESTIMATE: | $59,628 |
Length: | 7.7 | Actual | $45,594 |
District: | ATLANTA | Let Date: | Apr 2018 |
Highway: | US 259 | Let Status: | Actual |
Project ID: | STP 2018(788)HESG | CSJ: | 0085-04-047 |
Description: | PROFILE EDGELINE MARKINGS | Handling Code: | |
Limits From: | OKLAHOMA STATE LINE | Fund Cat: | 8 |
Limits To: | US 82 | ESTIMATE: | $164,864 |
Length: | 12.3 | Actual | $141,610 |
District: | ATLANTA | Let Date: | Apr 2018 |
Highway: | US 259 | Let Status: | Actual |
Project ID: | STP 2018(788)HESG | CSJ: | 0085-04-048 |
Description: | PROFILE CENTERLINE MARKINGS | Handling Code: | |
Limits From: | OKLAHOMA STATE LINE | Fund Cat: | 8 |
Limits To: | US 82 | ESTIMATE: | $74,551 |
Length: | 12.3 | Actual | $52,973 |
District: | ATLANTA | Let Date: | Apr 2018 |
Highway: | SH 77 | Let Status: | Actual |
Project ID: | STP 2018(788)HESG | CSJ: | 0277-02-050 |
Description: | PROFILE CENTERLINE MARKINGS | Handling Code: | |
Limits From: | FM 250 | Fund Cat: | 8 |
Limits To: | FM 2065 | ESTIMATE: | $51,778 |
Length: | 5.5 | Actual | $47,187 |
District: | ATLANTA | Let Date: | Apr 2018 |
Highway: | FM 997 | Let Status: | Actual |
Project ID: | STP 2018(788)HESG | CSJ: | 0392-06-010 |
Description: | PROFILE EDGELINE & CENTERLINE MARKINGS | Handling Code: | |
Limits From: | FM 144 | Fund Cat: | 8 |
Limits To: | 3.788 MI. S. OF FM 144 | ESTIMATE: | $76,480 |
Length: | 3.8 | Actual | $62,187 |
District: | ATLANTA | Let Date: | Apr 2018 |
Highway: | SH 315 | Let Status: | Actual |
Project ID: | STP 2018(788)HESG | CSJ: | 0462-03-047 |
Description: | PROFILE EDGELINE & CENTERLINE MARKINGS | Handling Code: | |
Limits From: | RUSK C/L | Fund Cat: | 8 |
Limits To: | US 79 | ESTIMATE: | $393,445 |
Length: | 17.3 | Actual | $348,893 |
District: | ATLANTA | Let Date: | Apr 2018 |
Highway: | SH 43 | Let Status: | Actual |
Project ID: | STP 2018(788)HESG | CSJ: | 0569-01-054 |
Description: | PROFILE EDGELINE MARKINGS | Handling Code: | |
Limits From: | FM 248 | Fund Cat: | 8 |
Limits To: | MARION C/L | ESTIMATE: | $139,452 |
Length: | 10.2 | Actual | $89,213 |
District: | ATLANTA | Let Date: | Apr 2018 |
Highway: | FM 134 | Let Status: | Actual |
Project ID: | STP 2018(788)HESG | CSJ: | 0632-03-047 |
Description: | PROFILE EDGELINE & CENTERLINE MARKINGS | Handling Code: | |
Limits From: | FM 1999 | Fund Cat: | 8 |
Limits To: | FM 1998 | ESTIMATE: | $115,731 |
Length: | 5.1 | Actual | $98,480 |
District: | ATLANTA | Let Date: | Apr 2018 |
Highway: | FM 558 | Let Status: | Actual |
Project ID: | STP 2018(788)HESG | CSJ: | 0945-02-023 |
Description: | PROFILE EDGELINE & CENTERLINE MARKINGS | Handling Code: | |
Limits From: | FM 2516 | Fund Cat: | 8 |
Limits To: | 3.578 MI. S. OF FM 2516 | ESTIMATE: | $71,985 |
Length: | 3.6 | Actual | $58,069 |
District: | ATLANTA | Let Date: | Apr 2018 |
Highway: | FM 2148 | Let Status: | Actual |
Project ID: | STP 2018(788)HESG | CSJ: | 2050-01-022 |
Description: | PROFILE EDGELINE & CENTERLINE MARKINGS | Handling Code: | |
Limits From: | IH 30 | Fund Cat: | 8 |
Limits To: | US 67 | ESTIMATE: | $85,028 |
Length: | 4.0 | Actual | $70,471 |
District: | ATLANTA | Let Date: | Apr 2018 |
Highway: | FM 3287 | Let Status: | Actual |
Project ID: | STP 2018(788)HESG | CSJ: | 2050-02-004 |
Description: | PROFILE EDGELINE & CENTERLINE MARKINGS | Handling Code: | |
Limits From: | PRESLEY ROAD | Fund Cat: | 8 |
Limits To: | FM 989 | ESTIMATE: | $32,638 |
Length: | 1.3 | Actual | $23,491 |
District: | ATLANTA | Let Date: | Apr 2018 |
Highway: | FM 2454 | Let Status: | Actual |
Project ID: | STP 2018(788)HESG | CSJ: | 2338-01-009 |
Description: | PROFILE EDGELINE MARKINGS | Handling Code: | |
Limits From: | FM 556 | Fund Cat: | 8 |
Limits To: | UPSHUR C/L | ESTIMATE: | $6,581 |
Length: | 0.6 | Actual | $5,690 |
District: | ATLANTA | Let Date: | Apr 2018 |
Highway: | FM 2454 | Let Status: | Actual |
Project ID: | STP 2018(788)HESG | CSJ: | 2338-02-014 |
Description: | PROFILE EDGELINE MARKINGS | Handling Code: | |
Limits From: | CAMP C/L | Fund Cat: | 8 |
Limits To: | FM 2088 | ESTIMATE: | $71,210 |
Length: | 7.1 | Actual | $60,969 |
District: | ATLANTA | Let Date: | Apr 2018 |
Highway: | FM 3001 | Let Status: | Actual |
Project ID: | STP 2018(788)HESG | CSJ: | 3041-02-019 |
Description: | PROFILE CENTERLINE MARKINGS | Handling Code: | |
Limits From: | FM 726 | Fund Cat: | 8 |
Limits To: | HARRISON C/L | ESTIMATE: | $53,557 |
Length: | 6.6 | Actual | $42,652 |
Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 0010-06-043 | ||
---|---|---|---|
Length: | 97.4 | ||
Estimate: | $1,396,926 | ||
Actual: | $1,147,480 | ||
CCSJ: 0221-05-090 |
|||
District: | ATLANTA | Let Date: | Mar 2018 |
Highway: | US 271 | Let Status: | Actual |
Project ID: | STP 2018(646) | CSJ: | 0221-05-090 |
Description: | RESURFACE EXISTING 2-LANE HIGHWAY | Handling Code: | |
Limits From: | FM 1896 | Fund Cat: | 1 |
Limits To: | BU 271 | ESTIMATE: | $2,629,224 |
Length: | 7.7 | Actual | $2,501,082 |
List Showing Order Proposal Request Bid List Addenda Bid Tabulations Award Status Back... | Totals for 0221-05-090 | ||
Length: | 7.7 | ||
Estimate: | $2,629,224 | ||
Actual: | $2,501,082 | ||
CCSJ: 0610-03-085 |
|||
District: | ATLANTA | Let Date: | Jan 2018 |
Highway: | IH 30 | Let Status: | Actual |
Project ID: | BR 2018(387) | CSJ: | 0610-03-085 |
Description: | BRIDGE PREVENTATIVE MAINTENANCE | Handling Code: | |
Limits From: | AT HAYES CREEK | Fund Cat: | 6 |
Limits To: | . | ESTIMATE: | $38,270 |
Length: | 0.1 | Actual | $38,560 |
District: | ATLANTA | Let Date: | Jan 2018 |
Highway: | IH 30 | Let Status: | Actual |
Project ID: | BR 2018(387) | CSJ: | 0610-07-106 |
Description: | BRIDGE PREVENTATIVE MAINTENANCE | Handling Code: | |
Limits From: | AT RAIN CREEK | Fund Cat: | 6 |
Limits To: | . | ESTIMATE: | $26,620 |
Length: | 0.1 | Actual | $28,695 |
List Showing Order Bid List Proposal Request Bid Tabulations Award Status Back... | Totals for 0610-03-085 | ||
Length: | 0.2 | ||
Estimate: | $64,890 | ||
Actual: | $67,255 | ||
CCSJ: 3404-01-016 |
|||
District: | ATLANTA | Let Date: | Apr 2018 |
Highway: | FM 3417 | Let Status: | Actual |
Project ID: | SSW 3404-1-16 | CSJ: | 3404-01-016 |
Description: | PROVIDE ADDITIONAL PAVED SURFACE WIDTH, MILLED EDGELINE | Handling Code: | |
Limits From: | FM 127 | Fund Cat: | 1 |
Limits To: | US 271 | ESTIMATE: | $3,929,961 |
Length: | 4.3 | Actual | $3,193,652 |
Proposal Request List Showing Order Bid List Bid Tabulations Award Status Back... | Totals for 3404-01-016 | ||
Length: | 4.3 | ||
Estimate: | $3,929,961 | ||
Actual: | $3,193,652 |
Handling Code | Definition |
---|---|
XX | Project not processed through statewide letting |
TR | Transfer of funds |
LC | Project let through local entity |
LC | Project not charged against district apportionment |
Let Status | Definition |
---|---|
Tentative | Estimated letting date for this project |
Approved | Project has administrative approval to be let |
Actual | Project was let to contract |